Plan resubmittals received | | | 1/31/2020 | | DONE |
|
|
|
three copies of plan sheets A0.0, A1.0, A2.0, A2.1, A3.0, A3.1, A3.2, A3.3, A3.4, A4.0, A4.0.1, A4.1, A4.2, A4.3, A5.0, A10.0, A11.0, A11.1 and A11.2. Taken to Carl W
|
Route to Impact Fee Review | 1/29/2020 | 2/1/2020 | 1/30/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - Design Review | 1/29/2020 | | 1/29/2020 | | FAIL |
KayCee Babb
|
|
|
DRH20-00023 has been submitted, but is still under review. After decision, there will be a ten day appeal period.
|
Permanent Occupancy | | | 10/11/2016 | | DONE |
|
|
|
|
BLD-Final | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
FIRE-Final Inspection | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, smoke detectors are stand-alone and not monitored, fire extinguisher is in common area with a current inspection tag. Final life fire safety inspection passed/complete.
|
BLD-Aging Inspection | 6/2/2016 | 6/2/2016 | 6/3/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 6/1/2016 | 6/1/2016 | 6/2/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | PASS |
Tony Young
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | DONE |
Jim Page
|
|
|
Not a final life fire safety inspection, inspection request for rough to cover on rock-wool installation and fire caulk penetrations. No fire sprinklers, no fire alarms. Life fire safety inspection will need to be performed at project completion.
|
BLD-Foundation | 1/4/2016 | 1/5/2016 | 1/5/2016 | A | CANC |
Tony Young
|
|
|
Matt Phone #: ###-####,, wrong permit
|
CHANGE STATUS TO (ISS) | | | 12/3/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 11/18/2015 | 11/18/2015 | 11/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 11/18/2015 | | 11/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2015 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 11/18/2015 | | DONE |
|
|
|
Provided through penetration detail sheets A11.0, A11.1, A11.2. Provided additional information for intumescent paint to be used at first flppor north bedroom ceilings to provide 1-hour floor/ceiling construction between first and second floor dwelling units. Two copies of sheet A0.0, A3.1, A11.0, A11.1 and A11.2. One copie of letter to Carl M, one copy of ForceFiel FireGuard E-84 intumescent paint packet and one copy of FireFree Coatings Inc Packet. Plans taken to Carl M
|
Permit Ready to Issue | | | 2/17/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/17/2015 | | DONE |
|
|
|
|
Telephone call | | | 2/13/2015 | | DONE |
Christina Prado
|
|
|
Called John to advise review is complete
|
Permit Ready to Issue | | | 2/12/2015 | | DONE |
|
|
|
Need GC Form and Revised Value
|
Print Occupancy Form | | | 2/12/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | | 1/14/2015 | 2/11/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | | | 2/11/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 2/11/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/11/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2015 | | DONE |
|
|
|
|
Routing - MECHANICAL | 2/2/2015 | | 2/2/2015 | | PASS |
Troy James
|
|
|
see bld15-00085 for acca reports
|
Plan resubmittals received | | | 1/29/2015 | | DONE |
Christina Prado
|
|
|
Received one set of upper floor manual J calcs and one set of lower floor manual j calcs; calcs stamped and taken to Carl M for review
|
Routing - MECHANICAL | 1/21/2015 | | 1/23/2015 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 1/20/2015 | | 1/21/2015 | | PASS |
Jason C. Taylor
|
|
|
Addresses all updated. Jason Taylor ###-####
|
Routing - PUBLIC WORKS | 1/21/2015 | | 1/21/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 1/21/2015 | | 1/21/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 1/20/2015 | | PASS |
Carl D Madsen
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/14/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/14/2015 | | FAIL |
Carl D Madsen
|
|
|
addressing corrections
|
Recd Pcfee & Taken To Pln CK | | | 1/14/2015 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 10/21/2016 | | | |
|
|
|
|
Application received | | 1/14/2015 | | | |
|
|
|
|