Print Statement | | | 8/24/2015 | | DONE |
|
|
|
|
First Notice | | 7/27/2015 | 8/10/2015 | | DONE |
|
|
|
Mailed 8/11
|
Permanent Occupancy | | | 7/17/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/16/2015 | | DONE |
|
|
|
|
BLD-Final | 7/15/2015 | 7/15/2015 | 7/15/2015 | P | PASS |
Tony Young
|
|
|
Rusty Phone #: ###-####
|
BLD-Final | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | PEND |
Tony Young
|
|
|
Rusty Phone #: ###-####
|
BLD-Final | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | PEND |
Tony Young
|
|
|
Rusty Phone #: ###-####
|
FIRE-Final Inspection | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | PASS |
Jim Page
|
|
|
Previously noted items corrected, small ducuments on site, occupancy load signs installed. Life fire safety passed/complete.
|
CHANGE STATUS TO (ISS) | | | 7/14/2015 | | DONE |
|
|
|
|
BLD-Final | 7/13/2015 | 7/13/2015 | 7/13/2015 | P | PART |
Tony Young
|
|
|
Rusty Phone #: ###-####,, need trades,, address issues
|
FIRE-Final Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide occupant load signs and small documents
|
BLD-Final | 7/10/2015 | 7/13/2015 | 7/13/2015 | A | NR |
Tony Young
|
|
|
Rusty Phone #: ###-####,, need trades,, fls
|
BLD-Wall cover | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 5/6/2015 | 5/7/2015 | 5/7/2015 | A | PEND |
Tony Young
|
|
|
Rusty Phone #: ###-####,, need sprinklers fully signed off for cover,, then ok to cover
|
BLD-Framing/Rough-in | 5/6/2015 | 5/6/2015 | 5/6/2015 | P | PART |
Tony Young
|
|
|
Rusty Phone #: ###-####,, need sprinklers signed off
|
BLD-Framing/Rough-in | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | NR |
Tony Young
|
|
|
Rusty Phone #: ###-####
|
BLD-Framing/Rough-in | 5/5/2015 | 5/5/2015 | 5/5/2015 | P | PART |
Tony Young
|
|
|
Rusty Phone #: ###-####,, need fire blocks,, need sprinklers signed off,, ok to insulate
|
Print Occupancy Form | | | 3/26/2015 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 3/26/2015 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 1/20/2015 | 1/20/2015 | 2/23/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Quail Hollow Banquet Hall
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Permit Ready to Issue | | | 2/23/2015 | | DONE |
|
|
|
NEED GC form and Certificate of Value
|
Routing - PLAN CHECK | 2/20/2015 | | 2/20/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 2/20/2015 | | 2/20/2015 | | PASS |
Daryl Spivey
|
|
|
Install per ISPC.
|
1st review completed | | | 2/11/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 1/20/2015 | | 2/11/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 1/20/2015 | 1/20/2015 | 1/26/2015 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to case.
|
Routing - MECHANICAL | 1/20/2015 | | 1/22/2015 | | PASS |
Troy James
|
|
|
|
Routing PW Sewer Rating | 1/21/2015 | | 1/22/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 1/20/2015 | | 1/21/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 1/20/2015 | | 1/20/2015 | | CANC |
Evan Jenkins
|
|
|
No Review nor ESC Permit Required. No Saw cutting, etc...
|
Intake Approval | | | 1/20/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 1/20/2015 | | 1/20/2015 | | FAIL |
Daryl Spivey
|
|
|
Require a plumbing plan with water, waste and vent pipe sizing and S-1 plumbed per ISPC. This plan is not an adequate plumbing plan. Does restrooms have floor drains?
|
Routing - Addressing | 1/20/2015 | | 1/20/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 1/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 16 2015 10:37AM
|