Third Notice | | 12/17/2017 | 1/4/2018 | | DONE |
|
|
|
This permit finaled on the web by Jeff Miller
|
Second Notice | | 11/24/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
First Notice | | 10/28/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
Permanent Occupancy | | | 10/18/2017 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 10/17/2017 | 10/17/2017 | 10/17/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Telephone call | | | 10/11/2017 | | DONE |
|
|
|
called Clinton to again about the temp c of o-he thought he was done-i emailed him a new sign off card and asked him to call in the 2 inspections required in order to get the fperm c of o. ACHD & PW
|
Print Occupancy Form | | | 10/11/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/11/2017 | | DONE |
|
|
|
|
Telephone call | | | 10/4/2017 | | DONE |
|
|
|
called office and left fmessage on phone-temp c of o is expired and gave the info as to either call in all finals or request an extension
|
BLD-Aging Inspection | 8/30/2017 | 8/30/2017 | 8/30/2017 | | PEND |
Mike Jordan
|
|
|
Building is complete, all issues were resolved. Either needs to pick up c.o. or needs to satisfy other dept. sign offs.
|
Temporary Occupancy | 7/5/2017 | 10/3/2017 | 7/5/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/5/2017 | | DONE |
|
|
|
|
BLD-Aging Inspection | 6/30/2017 | 6/30/2017 | 6/30/2017 | | PASS |
Mike Jordan
|
|
|
Needs to pick up c. o.
|
Print Occupancy Form | | | 6/30/2017 | | DONE |
|
|
|
|
Meeting | | | 6/30/2017 | | DONE |
|
|
|
Quinton from Layton Constrution in office to pick up CO. Told him need sign off card to issue the CO. Need to show ACHD sign off and no record of PW perm occ approval.
|
BLD-Final | 2/15/2017 | 2/16/2017 | 2/16/2017 | P | PASS |
Mike Jordan
|
|
|
Clintun Phone #: ###-####. Ok for perm occ. when ACHD and PW do their finals
|
CHANGE STATUS TO (ISS) | | | 12/22/2016 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 11/18/2016 | 11/18/2016 | 12/15/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/15/2016 | | 12/15/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/15/2016 | | DONE |
|
|
|
plan mod ONLY - DO NOT RE-ISSUE
|
Plan Modification Accepted | | | 11/18/2016 | | DONE |
|
|
|
Plan Modification requested for the addition of accessible transaction counters at service reception & services writers
|
BLD-Final | 10/14/2016 | 10/17/2016 | 10/17/2016 | A | PEND |
Mike Jordan
|
|
|
Please call ahead for access - Dave Phone #: ###-####. Spoke with Dave, waiting for furniture plan to be submitted for review and approval.
|
FIRE-Final Inspection | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. I suggested that the recycle bin next to the FDC be relocated to give fire personell more room to work.
|
CHANGE STATUS TO (ISS) | | | 10/11/2016 | | DONE |
|
|
|
was changed to REV by mistake
|
FIRE-Final Inspection | 9/23/2016 | 9/27/2016 | 9/27/2016 | P | CANC |
Jim Page
|
|
|
Tried calling points of contact, Quenton ###-#### and Paul ###-####, did not receive a call back from either contact, this inspection request cancelled due to no return phone call and a new inspection request will need to be rescheduled.
|
Case Summary (BLD) | | | 8/29/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/27/2016 | 7/29/2016 | 7/29/2016 | P | CANC |
Troy Cobbley
|
|
|
Clinton Phone #: ###-####
|
FIRE-Final Inspection | 7/27/2016 | 7/28/2016 | 7/28/2016 | P | NR |
Troy Cobbley
|
|
|
Need the city approved plans to verify the fire dept access. I did a drive by and noted care blocking access on the west and north sides of the building.
|
BLD-Final | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | NR |
Mike Jordan
|
|
|
Quiton Phone #: ###-####
|
Zoning Approval | 5/3/2016 | 5/3/2016 | 5/3/2016 | | PASS |
Josh Wilson
|
|
|
Site improvements are complete and the bond can be released.
|
BLD-Final | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PART |
Mike Jordan
|
|
|
Contact Tony Phone #: ###-#### Inspection requested via web by Tony Inserra. Ok for temp. occ. only.
|
FIRE-Final Inspection | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy for life safety is being given until the scope of work has been complete. Currently the existing building/dealership has not been demolished and the parking lot/fire lane completed. Contractor is hoping with in the next 6 weeks all work will be complete.
|
FIRE-Final Inspection | 11/4/2015 | 11/5/2015 | 11/5/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire dept review comments, provide the additioanl four fire extinguishers, provide the two additional exit discharge lights and repair the two non-functional emergency lights, replace the bent sprinkler hanger rod and provide cages for the upright heads underneath the stairs. Provide fire dept access around the north side of the building per the approved plans.
|
Zoning Approval Temp | 11/5/2015 | 11/5/2015 | 11/5/2015 | | PASS |
Josh Wilson
|
|
|
90-day temporary ocupancy. Bond is in place.
|
BLD-Conference | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | CANC |
Mike Jordan
|
|
|
Pree-walk for final inspection. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Conference | 11/3/2015 | 11/3/2015 | 11/3/2015 | P | DONE |
Mike Jordan
|
|
|
Pre walk through with contractor. Needs zoning sign off. Appears that furniture plans was not submited and reviewed for ADA compliance. Noted door hardware issues as well.
|
FIRE-Conference | 10/26/2015 | 10/26/2015 | 10/27/2015 | P | DONE |
Troy Cobbley
|
|
|
I performed a walk through with Tony and discussed door hardware issues on several of the doors that are utilizing thumb turn dead bolts on interior doors.
|
BLD-Ceiling Grid Inspection | 10/21/2015 | 10/21/2015 | 10/21/2015 | A | PASS |
Mike Jordan
|
|
|
Ceiling grid inspection requested by Tony. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Ceiling Grid Inspection | 10/9/2015 | 10/12/2015 | 10/12/2015 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/6/2015 | 10/7/2015 | 10/7/2015 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Ceiling grid at service bay and break room ok.
|
BLD-Framing/Rough-in | 9/10/2015 | 9/11/2015 | 9/11/2015 | A | PASS |
Mike Jordan
|
|
|
Tracey Phone #: ###-####. Interior steel stud walls for insuarance and finance offices and vehicle delivery area.
|
BLD-Energy code compliance | 9/8/2015 | 9/9/2015 | 9/9/2015 | P | PART |
Jim Sly
|
|
|
Tony Phone #: ###-#### E. W. and S. walls showroom.
|
BLD-Framing/Rough-in | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Exterior steel stud wall framing and soffits at showroom. Interior steel stud framed walls and soffits at showroom, showroom ofices, conferance room and back offices.
|
BLD-Framing/Rough-in | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Interior steel stud framed walls and hardlids for showroom restrooms ok to cover.
|
BLD-Conference | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | DONE |
Mike Jordan
|
|
|
Job site visit. Check special inspection reports, job status. Contractor has begun interior framing and exterior framing of steel stud walls and soffits. Reviewed approved plans.
|
Fees Due Hold | 7/3/2015 | | 7/22/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/1/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/1/2015 | | DONE |
|
|
|
|
Routing PW Environmental | 6/18/2015 | | 7/1/2015 | | PASS |
Rick Christenson
|
|
|
|
Plan assigned to (TLW) | 5/20/2015 | | 7/1/2015 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod
|
BLD-Foundation | 6/23/2015 | 6/24/2015 | 6/24/2015 | A | PART |
Mike Jordan
|
|
|
CMU pour time 1:00PM; Tony ###-####. Work in progress, pend. special inspection. Also reviewed special inspection check sheet.
|
BLD-Foundation | 6/23/2015 | 6/23/2015 | 6/23/2015 | P | NR |
Tony Young
|
|
|
###-####-Tony-CMU-pour at 1:00
|
Routing - PLUMBING | 6/16/2015 | | 6/23/2015 | | PASS |
Daryl Spivey
|
|
|
See redline notes for venting on oil/sand interceptor tanks and outlet lines.
|
Routing PW Drainage | 6/18/2015 | | 6/22/2015 | | PASS |
Brian Murphy
|
|
|
Per Eplan approval by BGM
|
Routing PW Sewer Rating | 6/18/2015 | | 6/22/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - MECHANICAL | 6/16/2015 | | 6/18/2015 | | PASS |
Troy James
|
|
|
revised location of tailpipe vehicle exhaust
|
Routing - PUBLIC WORKS | 6/16/2015 | | 6/18/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLAN CHECK | 6/16/2015 | | 6/17/2015 | | PASS |
Tim L. Woodard
|
|
|
Approved scope of work in modification only. A rereview of the building was not conducted. TLW
|
Routing - PLANNING | 6/16/2015 | | 6/17/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00005
|
Routing PW Drainage | | | 6/8/2015 | | PASS |
Brian Murphy
|
|
|
|
BLD-Foundation | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU 1:00PM pour; Tony Phone #: ###-####
|
BLD-Foundation | 6/4/2015 | 6/4/2015 | 6/4/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU 1:00PM pour; Tony Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU pour time 1:00PM; Tony Phone #: ###-####. Special inspetor on site.
|
Routing PW Sewer Rating | 5/26/2015 | | 5/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Environmental | 5/26/2015 | | 5/27/2015 | | PASS |
Rick Christenson
|
|
|
2500 Gallon Sand/Oil Interceptor shown for car wash. 2500 Sand/Oil shown for bay.
|
BLD-Foundation | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU Grout 1PM, MTI will be out as well - Tony Phone #: ###-####. Special inspector on site.
|
Routing - Addressing | 5/21/2015 | | 5/26/2015 | | PASS |
Jason C. Taylor
|
|
|
|
BLD-Foundation | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | DEFR |
Phil Shearer
|
|
|
|
BLD-Foundation | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | DEFR |
Mike Jordan
|
|
|
Tony Phone #: ###-####
|
Plan Modification Accepted | | | 5/20/2015 | | DONE |
|
|
|
revised location of light poles @ parking, revision of plumbing @ car wash, revision of interior doors, reduced number of skylight (solar tubes). Routed to Tim W
|
BLD-Foundation | 5/18/2015 | 5/18/2015 | 5/18/2015 | P | DEFR |
Mike Jordan
|
|
|
Tony Phone #: ###-####. grout placement completed. Special inspector on site.
|
BLD-Foundation | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PART |
Mike Jordan
|
|
|
CMU grout pour 2:00PM; Tony Phone #: ###-####. Top of footing to finish floor elevation, work in progress, special inspector on site.
|
BLD-Foundation | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | DEFR |
Mike Jordan
|
|
|
Tony-cmu-pour time 2:00 Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 5/12/2015 | 5/12/2015 | 5/12/2015 | P | PART |
Mike Jordan
|
|
|
CMU, pour time 2:00PM; Tony Phone #: ###-####. masonry wall on gridline 1.3, top of footong to finish floor elevation. Work in progress, special inspector on site.
|
BLD-Foundation | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | CANC |
Phil Shearer
|
|
|
Grout pour time 2:00PM; Rudy Phone #: ###-####
|
BLD-Foundation | 5/7/2015 | 5/8/2015 | 5/8/2015 | P | PART |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Masonry wall, top of footing to finish floor elevation at demissing wall between showroom and service bays.
|
BLD-Footing | 5/7/2015 | 5/8/2015 | 5/8/2015 | A | PASS |
Mike Jordan
|
|
|
Tony// pour time is 1030 Phone #: ###-####. Interior column pad footings and interior footings at showroom and service bays. All previous issues have been resolved.
|
BLD-Foundation | 4/29/2015 | 4/30/2015 | 4/30/2015 | A | FAIL |
Mike Jordan
|
|
|
Tony Phone #: ###-####. No city approved plans on site, Special inspector on jobsite ni ICC certified.
|
Issue PAID IN FULL permit | | | 4/29/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/29/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/22/2015 | | 4/28/2015 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2015 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 4/28/2015 | | DONE |
|
|
|
All requirements met
|
Plan assigned to (JCM) | 2/6/2015 | | 4/28/2015 | | PASS |
John Menard
|
|
|
1st Review Complete 3/23/2015
|
Routing - PLANNING Land Div | 4/22/2015 | | 4/23/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - PLAN CHECK | 4/14/2015 | | 4/14/2015 | | PASS |
John Menard
|
|
|
|
Routing PW Drainage | 3/31/2015 | | 4/8/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 3/31/2015 | | 4/7/2015 | | PASS |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 3/31/2015 | | 4/2/2015 | | FAIL |
Todd Tucker
|
|
|
|
Routing - PLAN CHECK | 3/31/2015 | | 4/1/2015 | | FAIL |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 3/31/2015 | | 3/31/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Route to Impact Fee Review | 3/24/2015 | 3/27/2015 | 3/26/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 2/6/2015 | | 3/24/2015 | | FAIL |
John Menard
|
|
|
|
1st review completed | | | 3/23/2015 | | DONE |
John Menard
|
|
|
|
Routing PW Environmental | 2/6/2015 | | 3/16/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 2/6/2015 | | 2/23/2015 | | FAIL |
Brian Murphy
|
|
|
need grounwater est
|
Routing - Design Review | 2/6/2015 | | 2/20/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00005
|
Routing Off Site - STRUCTURAL | 2/6/2015 | | 2/20/2015 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 2/6/2015 | | 2/10/2015 | | PASS |
Scott Arellano
|
|
|
Attached plan review comments to case.
|
Routing PW Sewer Rating | 2/6/2015 | | 2/10/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Solid Waste | 2/6/2015 | | 2/6/2015 | | PASS |
Peter J. McCullough
|
|
|
Solid waste staff reviewed the trash/recycling enclosure. Size meets criteria. Gates to enclosure must open at least 120-degrees for access.
|
Routing PW Street Lights | 2/6/2015 | | 2/6/2015 | | PASS |
Mike D Hedge
|
|
|
No street lighting required, the Boise Auto Mall has private street lighting with ornamental lights.
|
Routing - PLUMBING | 2/6/2015 | | 2/6/2015 | | PASS |
Daryl Spivey
|
|
|
Seperate vent required on sand and oil interceptor tank. RPBP required on water to garage work area non potable water outlets.
|
Routing - PLANNING Land Div | 2/6/2015 | | 2/6/2015 | | FAIL |
Dave Abo
|
|
|
Do not issue permit until the Record of Survey to consolidate the parcel is complete.
|
Routing - Addressing | 2/6/2015 | | 2/6/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 2/6/2015 | | 2/6/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 2/6/2015 | | 2/6/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP REQUIRED)
LARRY H. MILLER BOISE HONDA - 56,000 sf new auto sales and service facility to replace existing builidng.
Previous SWPPP has been modified for this new portion/phase of the project
|
Intake Approval | | | 2/6/2015 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 2/6/2015 | | 2/6/2015 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 1/21/2015 | | FAIL |
John Menard
|
|
|
I did not see the Verification Of Legal Lot form, signed by the PDS Subdivision staff.
Please submit the required Verification Of Legal Lot form.
|
Application received | | | 1/19/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 19 2015 11:12AM
|