Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD15-00136
StatusFinaled
Name SUNDANCE INVESTMENTS LTD PARTNERS
Site Address 272 N MAPLE GROVE RD
Project Name8 Feathers Distillery
Customer Number 
ePlanReviewNo
Description
(8 FEATHERS DISTILLERY - Racking) To install steel storage racking exceeding 8' in height within an existing building per approved plans and structural engineering. SPECIAL INSPECTIONS ARE REQUIRED. Work to include: To install 149 square feet total area of racking/shelving. Each unit will be bolted to the floor and have more than 36" isles between rows. The design, testing and utilization of industrial steel storage racks shall be in accordance with the RMI/ANSI MH 16.1. A Letter of Completion is to be issued when done. EACH RACKING SYSTEM SHALL HAVE A PLAQUE LOCATED AT EACH RACKING SYSTEM STATING THE MAXIMUM WEIGHT TO BE STORED ON THAT PERTICULAR RACKING SYSTEM PER THE ENGINEERS CRITERIA STATED ON THE PLANS FOR EACH RACKING SYSTEM. This building is fully Fire Sprinklered for allowable area increase and has an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/13/20155/4/2015 DONE
First Notice2/5/20152/5/20153/3/2015 DONE
DetailsMike Jordan
mailed 3-3-15
BLD-Final2/4/20152/5/20152/5/2015PPASS
DetailsMike Jordan
Marjie Phone #: ###-####
DOC - Permit Finaled2/5/20152/5/20152/5/2015PPASS
DetailsMike Jordan
BLD-Conference2/4/20152/5/20152/5/2015PPASS
DetailsMike Jordan
Marjie Phone #: ###-####
FIRE-Final Inspection2/4/20152/5/20152/5/2015APASS
DetailsTroy Cobbley
Life safety passed
Inspection Record Card- Bld  2/4/2015 DONE
Permit Ready to Issue  2/4/2015 DONE
need GC form & need revisedcert of value
Telephone call  2/4/2015 DONE
DetailsCandy A. Nichols
called Patrick Keegan to let know permit is ready and that we need the TG form and rev cert of val
Inspection Record Card- Bld  2/4/2015 DONE
Issue PAID IN FULL permit  2/4/2015 DONE
DetailsCandy A. Nichols
Plan assigned to (SRZ)1/22/20151/22/20152/3/2015 PASS
DetailsSam Zahorka
1st review completed. Level 2 TI - Paper - Racking
PLANS/APPL TAKEN TO FRONT DESK  2/3/2015 DONE
DetailsSam Zahorka
Routing - PLAN CHECK2/2/2015 2/3/2015 PASS
DetailsSam Zahorka
1st review completed  2/2/2015 PASS
Routing - FIRE1/28/2015 2/2/2015 PASS
DetailsScott Arellano
Attached comments to plans. HPS is less than 500 sq.ft.
Case Summary (BLD)  1/28/2015 DONE
DetailsSam Zahorka
Routing - PLAN CHECK1/22/2015 1/28/2015 PASS
DetailsSam Zahorka
Pending Assignment by JCB1/21/2015 1/22/2015 DONE
DetailsJason Blais
Intake Approval  1/21/2015 PASS
DetailsJason Blais
Prescreen approved by Tim Frost and plan review fees paid.
Plans ACCEPTED BY PLAN TECH  1/21/2015 DONE
Application received 1/20/2015