Second Notice | | 11/19/2015 | 11/23/2015 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
First Notice | | 11/1/2015 | 11/9/2015 | | DONE |
|
|
|
Mailed 11-10-15
|
Permanent Occupancy | | | 10/22/2015 | | DONE |
|
|
|
|
BLD-Final | 10/20/2015 | 10/21/2015 | 10/21/2015 | A | PASS |
Mike Jordan
|
|
|
Cecil Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 10/19/2015 | 10/20/2015 | 10/20/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Ceiling Grid Inspection | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | PASS |
Jim Sly
|
|
|
Ceizel Phone #: ###-####
|
BLD-Framing/Rough-in | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PASS |
Mike Jordan
|
|
|
Cecil Phone #: ###-####
|
BLD-Final | 7/27/2015 | 7/28/2015 | 7/28/2015 | P | PART |
Mike Jordan
|
|
|
Ceicel Phone #: ###-####. Ok to occupy phase 3.
|
FIRE-Final Inspection | 7/27/2015 | 7/28/2015 | 7/28/2015 | A | PART |
Troy Cobbley
|
|
|
Phase 3 life safety passed
|
FIRE-Final Inspection | 7/7/2015 | 7/7/2015 | 7/7/2015 | P | PART |
Troy Cobbley
|
|
|
Rooms 206, 207 and the associated offices life safety is passed. This is a phased project.
|
FIRE-Final Inspection | 7/1/2015 | 7/6/2015 | 7/6/2015 | A | CANC |
Troy Cobbley
|
|
|
Jeff is canceling until the project related fire alarm permit can be scheduled.
|
BLD-Ceiling Grid Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | PASS |
Mike Jordan
|
|
|
Cecil Phone #: ###-####
|
BLD-Framing/Rough-in | 6/17/2015 | 6/17/2015 | 6/17/2015 | P | PASS |
Mike Jordan
|
|
|
Cesul Phone #: ###-####. phase 2 pharmacy ok for cover.
|
BLD-Framing/Rough-in | 4/24/2015 | 4/24/2015 | 4/24/2015 | P | PASS |
Mike Jordan
|
|
|
Sycel Phone #: ###-####. Interior steel stud framed wall to creat a office and janitors closet.
|
Issue PAID IN FULL permit | | | 3/19/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 1/28/2015 | | 3/10/2015 | | PASS |
Carl Westfall
|
|
|
SAINT ALPHONSUS - NORTH TOWER - 2ND STORT - Level 3 TI - (15 days - Feb 16)
|
Routing - PLAN CHECK | 3/5/2015 | | 3/10/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/10/2015 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 3/10/2015 | | DONE |
Christina Prado
|
|
|
Need revised certificate of value & GC form for issuance. Sent in by email from Brandon Byington with Kreizenbeck Contructors. blh 3-13-15
|
Telephone call | | | 3/10/2015 | | DONE |
|
|
|
To Jeff
|
Plan resubmittals received | | | 3/5/2015 | | |
Brittany Hill
|
|
|
Two sheets of A0.1, A2.3,A2.4,A3.0,M0.0,M1.1E0.0, and E2.2L
|
1st review completed | | | 2/24/2015 | | FAIL |
|
|
|
Failed plan check. Fire was under staffed so the review took longer than expected. In addition, the time frame included 1 holiday.
|
Routing - FIRE | 2/18/2015 | | 2/24/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to case.
|
Plan resubmittals requested | | | 2/18/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/6/2015 | | 2/18/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - PLUMBING | 2/5/2015 | | 2/6/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 1/28/2015 | | 2/5/2015 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 1/28/2015 | | 1/28/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 1/27/2015 | | 1/28/2015 | | DONE |
Jason Blais
|
|
|
|
Routing PW Sewer Rating | 1/28/2015 | | 1/28/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 1/27/2015 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 1/27/2015 | | DONE |
Carl Westfall
|
|
|
Plan intake review approved
|
Plans ACCEPTED BY PLAN TECH | | | 1/27/2015 | | DONE |
|
|
|
|
Application received | | 1/27/2015 | | | |
|
|
|
|