BLD-Final | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 3/11/2016 | 3/11/2016 | 3/11/2016 | | CANC |
Mike Jordan
|
|
|
|
Permanent Occupancy | | | 3/11/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/11/2016 | | DONE |
|
|
|
|
Zoning Approval | 3/10/2016 | 3/10/2016 | 3/10/2016 | | DONE |
Andrea Tuning
|
|
|
|
Telephone call | | | 3/10/2016 | | DONE |
|
|
|
called Pat-he said his P&Z insp should be PM today then he'll call in the bldg final
|
BLD-Final | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. ok for temp occ. Will be ok for perm occ. once zoning signs perm.
|
Temporary Occupancy | 12/4/2015 | 3/3/2016 | 12/4/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Zoning Approval Temp | 12/3/2015 | 12/3/2015 | 12/3/2015 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 12/2/2015 | 12/2/2015 | 12/2/2015 | P | NR |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
FIRE-Final Inspection | 11/23/2015 | 11/24/2015 | 11/24/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Other | 10/12/2015 | 10/12/2015 | 10/12/2015 | P | PASS |
Mike Jordan
|
|
|
RC1 Channel; Pat Phone #: ###-####
|
BLD-Energy code compliance | 10/6/2015 | 10/6/2015 | 10/6/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Energy code compliance | 10/2/2015 | 10/6/2015 | 10/6/2015 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2015 | 10/2/2015 | 10/2/2015 | A | PASS |
Jim Storey
|
|
|
Pat Phone #: ###-####
|
BLD-Wall Bracing | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 7/23/2015 | 7/24/2015 | 7/24/2015 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Foundation | 7/22/2015 | 7/23/2015 | 7/23/2015 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 7/21/2015 | 7/22/2015 | 7/22/2015 | P | NR |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Routing - FIRE | 4/28/2015 | 4/28/2015 | 4/28/2015 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2015 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 4/28/2015 | | DONE |
|
|
|
all requirments met
|
Issue & PRINT permit | | | 4/28/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/28/2015 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 2/6/2015 | | 4/28/2015 | | PASS |
Sam Zahorka
|
|
|
Pending others to PASS
|
Routing PW Street Lights | 2/9/2015 | | 4/28/2015 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 4/14/2015 | | 4/27/2015 | | PASS |
Megan Durrell
|
|
|
Trash enclosure dimensions still differ on each site drawing. Jeremy Amar did not return calls.
|
Routing - PLANNING | 4/23/2015 | | 4/23/2015 | | PASS |
Cody Riddle
|
|
|
Bond for amenities received today.
|
Routing - Design Review | 4/23/2015 | | 4/23/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 4/14/2015 | | 4/14/2015 | | FAIL |
Cody Riddle
|
|
|
Bonding for amenities has not been provided.
|
Routing PW Sewer Rating | 4/14/2015 | | 4/14/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - MECHANICAL | 4/13/2015 | | 4/13/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 4/13/2015 | | 4/13/2015 | | PASS |
Sam Zahorka
|
|
|
|
Routing - Addressing | 4/13/2015 | | 4/13/2015 | | PASS |
Emily Dixon
|
|
|
Address corrected to 880 N Maple Grove Rd. 4 unit addresses added.
|
Routing PW Drainage | 2/9/2015 | | 3/9/2015 | | PASS |
Brian Murphy
|
|
|
|
Route to Impact Fee Review | 2/27/2015 | 3/2/2015 | 3/6/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 2/6/2015 | | 3/2/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 2/6/2015 | | 3/2/2015 | | PASS |
Daryl Spivey
|
|
|
|
Routing - FIRE | 2/6/2015 | 2/6/2015 | 2/27/2015 | | FAIL |
Scott Arellano
|
|
|
IFC Review comments attached to case.
|
Routing Off Site - STRUCTURAL | 2/6/2015 | | 2/27/2015 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 2/27/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLANNING Land Div | 2/6/2015 | | 2/27/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 2/6/2015 | | 2/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 2/6/2015 | | 2/27/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED)
Bldg C (3) - Type 1 (Elev 4, A-203): Multifamily 4-Plex project consisting of 14 two-story buildings on 3.79 acre site located at 826 N Maple Grove, just north of Emerald. 13 buildings (52 units) will be 2 bedroom, 2 bathroom and 1 building (4 units) will be 1 bedroom, 1 bathroom.
Of the 13, 2 bedroom buildings, the two buildings located adjacent to Maple Grove have a different rear elevation and roof line and are designated as Building Type 3 while the other 2 bedroom buildings are Building Type 1. The 1 bedroom building is designated as Building Type 2.
Since all 14 buildings will be on the same parcel, they will all share the 826 N Maple Grove address. We propose to individually identify each building with a letter (A thru N) as shown on the site plan A-101. Within the plans, the buildings also have a number designation (1 thru 14) for plan referencing.
|
Routing PW Solid Waste | 2/9/2015 | | 2/27/2015 | | FAIL |
Megan Durrell
|
|
|
Enclosure inconsistent between drawings and do not comply with SW policies.
|
Routing - Design Review | 2/6/2015 | | 2/27/2015 | | FAIL |
Andrea Tuning
|
|
|
All planters shall be 8-feet in width.
Install a landscape planter in the parking row so parkign does not exceed 10 spaces.
The site plan and landscape plan should match one another.
All pole lighting and utilities can not be located within the required planter islands.
|
Routing - PLAN CHECK | 2/6/2015 | | 2/27/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Addressing | 2/9/2015 | | 2/9/2015 | | FAIL |
Emily Dixon
|
|
|
Each building needs to have a unique street number that will be assigned by the City of Boise.
|
Routing PW Sewer Rating | 2/9/2015 | | 2/9/2015 | | FAIL |
Jennifer Bruner
|
|
|
correct address needed
|
Intake Approval | | | 2/6/2015 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 2/6/2015 | | 2/6/2015 | | DONE |
John Menard
|
|
|
|
Application received | | | 1/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 30 2015 11:32AM
|
First Notice | | 3/21/2016 | | | |
|
|
|
|
First Notice | | 3/21/2016 | | | |
|
|
|
|
Routing - PLANNING | 2/6/2015 | | | | FAIL |
Susan Riggs
|
|
|
Amenities must be bonded for prior to issuance of a building permits. Amenities consist of walking paths, gazebo, picnic area, and benches. I have left 2 voice messages with the applicant Jeramy.
|