Permit Information
Permit NumberBLD15-00243
StatusFinaled
Name BILTMORE COMPANY
Site Address 848 N MAPLE GROVE RD
Project NameAshville Commons
Customer Number 
ePlanReviewNo
Description
Bldg H (8) - Type 1 (Elev 4, A-203): To construct a new 3,804 sq. ft., two story, Four unit, apartment building. Each unit has two bedrooms, two bathrooms, and 951 square feet. The 1st story units are required to be Type 'B' units. All units share a common path of egress into and through a 1/2-hour rated exit corridor with 20 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partitions and one hour horizontal assemblies are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00300 & PUD12-00012 Per Planning and Zoning. **SRZ*
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  3/18/2016 DONE
Zoning Approval3/17/20163/17/20163/17/2016 DONE
DetailsAndrea Tuning
BLD-Final3/11/20163/11/20163/11/2016PPASS
DetailsMike Jordan
BLD-Final3/7/20163/8/20163/8/2016APART
DetailsMike Jordan
Cody Phone #: ###-####. HAndrail repaired. OK for temp occ. will be ok for prm occ. once zoning signs perm.
BLD-Final3/7/20163/7/20163/7/2016PFAIL
DetailsMike Jordan
Cody Phone #: ###-####. Handrail exceeds 38 inch max height.
BLD-Final3/4/20163/4/20163/4/2016PNR
DetailsMike Jordan
Cody Phone #: ###-####. Needs mech. final.
FIRE-Final Inspection2/22/20162/26/20162/26/2016APASS
DetailsTroy Cobbley
Life safety passed
BLD-Energy code compliance1/14/20161/14/20161/14/2016PPASS
DetailsMike Jordan
BLD-Framing/Rough-in1/13/20161/14/20161/14/2016APASS
DetailsMike Jordan
Pat Phone #: ###-####
BLD-Framing/Rough-in1/12/20161/12/20161/12/2016PFAIL
DetailsMike Jordan
Pat Phone #: ###-####. NAil off simpson hangars in breeze way. Repair hole in 5/8 type x rock in coancealed space by bathroom vent fan. Complete firecaulk on tub and toilet drains. Firecaulk penetrations in draft stop. Several areas of foam seal and firecaulk missed on top plates. Correction notice posted.
BLD-Wall Bracing11/19/201511/23/201511/23/2015APASS
DetailsMike Jordan
Pat Phone #: ###-####
BLD-Foundation10/29/201510/29/201510/29/2015PPASS
DetailsMike Jordan
Pat Phone #: ###-####
BLD-Foundation10/27/201510/28/201510/28/2015PPART
DetailsMike Jordan
Jon Phone #: ###-####
BLD-Footing10/26/201510/27/201510/27/2015PPASS
DetailsMike Jordan
John Phone #: ###-####
BLD-Footing10/23/201510/26/201510/26/2015PNR
DetailsMike Jordan
Dane Phone #: ###-####
BLD-Footing10/21/201510/22/201510/22/2015PNR
DetailsMike Jordan
Dane Phone #: ###-####. No forms built, no convrete crew on site.
BLD-Footing10/21/201510/21/201510/21/2015PCANC
DetailsMike Jordan
Cancelled per dane via phone call.
BLD-Footing10/20/201510/21/201510/21/2015PCANC
DetailsMike Jordan
Dane Phone #: ###-####.
OVERRIDE  4/28/2015  
Routing - FIRE4/28/20154/28/20154/28/2015 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  4/28/2015 DONE
DetailsSam Zahorka
Permit Ready to Issue  4/28/2015 DONE
all requirments met
Issue PAID IN FULL permit  4/28/2015 DONE
Print Occupancy Form  4/28/2015 DONE
Plan assigned to (SRZ)2/6/2015 4/28/2015 PASS
DetailsSam Zahorka
Pending others to PASS
Routing PW Street Lights2/9/2015 4/28/2015 PASS
DetailsMike D Hedge
Routing PW Solid Waste4/27/2015 4/27/2015 PASS
DetailsMegan Durrell
Trash Enclosure differs on each site drawing. Jeremy amar did not return calls.
Routing - PLANNING4/23/2015 4/23/2015 PASS
DetailsCody Riddle
Bond for amenities received today.
Routing - Design Review4/23/2015 4/23/2015 PASS
DetailsAndrea Tuning
Routing - PLANNING4/14/2015 4/14/2015 FAIL
DetailsCody Riddle
Bonding for amenities has not been provided.
Routing - MECHANICAL4/13/2015 4/13/2015 PASS
DetailsTroy James
Routing - PLAN CHECK4/13/2015 4/13/2015 PASS
DetailsSam Zahorka
Routing - Addressing4/13/2015 4/13/2015 PASS
DetailsEmily Dixon
Address corrected to 848 N Maple Grove Rd. 4 unit addresses added.
Routing PW Drainage2/9/2015 3/9/2015 PASS
DetailsBrian Murphy
Route to Impact Fee Review2/27/20153/2/20153/6/2015 PASS
DetailsCindy M. Gould
Routing - MECHANICAL2/6/2015 3/2/2015 FAIL
DetailsTroy James
Routing - PLUMBING2/6/2015 3/2/2015 PASS
Details
Routing - FIRE2/6/20152/6/20152/27/2015 FAIL
DetailsScott Arellano
Attached comments to case.
Routing Off Site - STRUCTURAL2/6/2015 2/27/2015 FAIL
DetailsSam Zahorka
1st review completed  2/27/2015 DONE
DetailsSam Zahorka
Routing - PLANNING Land Div2/6/2015 2/27/2015 PASS
DetailsDave Abo
Routing - PUBLIC WORKS2/6/2015 2/27/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment2/6/2015 2/27/2015 PASS
DetailsEvan Jenkins
(SITE PREP INSPECTION REQUIRED)
Bldg H (8) - Type 1 (Elev 4, A-203): Multifamily 4-Plex project consisting of 14 two-story buildings on 3.79 acre site located at 826 N Maple Grove, just north of Emerald. 13 buildings (52 units) will be 2 bedroom, 2 bathroom and 1 building (4 units) will be 1 bedroom, 1 bathroom.

Of the 13, 2 bedroom buildings, the two buildings located adjacent to Maple Grove have a different rear elevation and roof line and are designated as Building Type 3 while the other 2 bedroom buildings are Building Type 1. The 1 bedroom building is designated as Building Type 2.

Since all 14 buildings will be on the same parcel, they will all share the 826 N Maple Grove address. We propose to individually identify each building with a letter (A thru N) as shown on the site plan A-101. Within the plans, the buildings also have a number designation (1 thru 14) for plan referencing.
Routing PW Solid Waste2/9/2015 2/27/2015 FAIL
DetailsMegan Durrell
Does not meet SW policy.
Routing - Design Review2/6/2015 2/27/2015 FAIL
DetailsAndrea Tuning
All planters shall be 8-feet in width.
Install a landscape planter in the parking row so parkign does not exceed 10 spaces.
The site plan and landscape plan should match one another.
All pole lighting and utilities can not be located within the required planter islands.
Routing - PLAN CHECK2/6/2015 2/27/2015 FAIL
DetailsSam Zahorka
Routing PW Sewer Rating2/9/2015 2/9/2015 FAIL
DetailsJennifer Bruner
Needs correct address
Routing - Addressing2/9/2015 2/9/2015 FAIL
DetailsEmily Dixon
Each building needs to have a unique street number that will be assigned by the City of Boise.
Intake Approval  2/6/2015 PASS
DetailsJohn Menard
Pending Assignment by JCM2/6/2015 2/6/2015 DONE
DetailsJohn Menard
Application received  1/30/2015 DONE
Application submitted via PDS Online on Jan 30 2015 11:32AM
First Notice 3/28/2016   
Routing - PLANNING2/6/2015   FAIL
DetailsSusan Riggs
Amenities must be bonded for prior to issuance of a building permits. Amenities consist of walking paths, gazebo, picnic area, and benches. I have left 2 voice messages with the applicant Jeramy.