BLD-Final | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Mike Jordan
|
|
|
|
Permanent Occupancy | | | 3/11/2016 | | DONE |
|
|
|
|
Zoning Approval | 3/10/2016 | 3/10/2016 | 3/10/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 3/8/2016 | 3/8/2016 | 3/8/2016 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 12/17/2015 | 12/17/2015 | 12/18/2015 | P | PASS |
Dave Hannah
|
|
|
Pat Phone #: ###-####
|
Temporary Occupancy | 12/18/2015 | 3/17/2016 | 12/18/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Zoning Approval Temp | 12/18/2015 | 12/18/2015 | 12/18/2015 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 12/16/2015 | 12/17/2015 | 12/17/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Amar
|
BLD-Energy code compliance | 10/14/2015 | 10/14/2015 | 10/14/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Wall Bracing | 9/2/2015 | 9/2/2015 | 9/2/2015 | P | PASS |
Mike Jordan
|
|
|
pat Phone #: ###-####
|
BLD-Foundation | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 8/5/2015 | 8/6/2015 | 8/6/2015 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####. Moved to am.
|
BLD-Footing | 8/4/2015 | 8/5/2015 | 8/5/2015 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
OVERRIDE | | | 4/28/2015 | | |
|
|
|
|
Routing - FIRE | 4/28/2015 | 4/28/2015 | 4/28/2015 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/28/2015 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 4/28/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/28/2015 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 2/6/2015 | | 4/28/2015 | | PASS |
Sam Zahorka
|
|
|
Pending others to PASS
|
Routing PW Street Lights | 2/9/2015 | | 4/28/2015 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 4/14/2015 | | 4/27/2015 | | PASS |
Megan Durrell
|
|
|
Trash enclosure dimensions still differ on each site drawing. Jeremy Amar did not return calls.
|
Routing - PLANNING | 4/23/2015 | | 4/23/2015 | | PASS |
Cody Riddle
|
|
|
Bond for amenities received today.
|
Routing - Design Review | 4/23/2015 | | 4/23/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 4/14/2015 | | 4/14/2015 | | FAIL |
Cody Riddle
|
|
|
Bonding for amenities has not been provided.
|
Routing PW Sewer Rating | 4/14/2015 | | 4/14/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | 4/13/2015 | 4/13/2015 | | DONE |
|
|
|
Address corrected to 808 N Maple Grove Rd. 4 unit addresses added.
|
Routing - MECHANICAL | 4/13/2015 | | 4/13/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 4/13/2015 | | 4/13/2015 | | PASS |
Sam Zahorka
|
|
|
|
Routing PW Drainage | 2/9/2015 | | 3/9/2015 | | PASS |
Brian Murphy
|
|
|
|
Route to Impact Fee Review | 2/27/2015 | 3/2/2015 | 3/6/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 2/6/2015 | | 3/2/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/6/2015 | | 3/2/2015 | | PASS |
|
|
|
|
Routing - FIRE | 2/6/2015 | 2/6/2015 | 2/27/2015 | | FAIL |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing Off Site - STRUCTURAL | 2/6/2015 | | 2/27/2015 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 2/27/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLANNING Land Div | 2/6/2015 | | 2/27/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 2/6/2015 | | 2/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 2/6/2015 | | 2/27/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED)
Bldg M (13) -Type 1 (Elev 4, A-203): Multifamily 4-Plex project consisting of 14 two-story buildings on 3.79 acre site located at 826 N Maple Grove, just north of Emerald. 13 buildings (52 units) will be 2 bedroom, 2 bathroom and 1 building (4 units) will be 1 bedroom, 1 bathroom.
Of the 13, 2 bedroom buildings, the two buildings located adjacent to Maple Grove have a different rear elevation and roof line and are designated as Building Type 3 while the other 2 bedroom buildings are Building Type 1. The 1 bedroom building is designated as Building Type 2.
Since all 14 buildings will be on the same parcel, they will all share the 826 N Maple Grove address. We propose to individually identify each building with a letter (A thru N) as shown on the site plan A-101. Within the plans, the buildings also have a number designation (1 thru 14) for plan referencing.
|
Routing PW Solid Waste | 2/9/2015 | | 2/27/2015 | | FAIL |
Megan Durrell
|
|
|
Does not meet SW policy
|
Routing - PLAN CHECK | 2/6/2015 | | 2/27/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing PW Sewer Rating | 2/9/2015 | | 2/9/2015 | | FAIL |
Jennifer Bruner
|
|
|
Address correction needed
|
Routing - Addressing | 2/9/2015 | | 2/9/2015 | | FAIL |
Emily Dixon
|
|
|
Each building needs to have a unique street number that will be assigned by the City of Boise.
|
Intake Approval | | | 2/6/2015 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 2/6/2015 | | 2/6/2015 | | DONE |
John Menard
|
|
|
|
Application received | | | 1/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 30 2015 11:32AM
|
First Notice | | 3/21/2016 | | | |
|
|
|
|
Routing - Design Review | 2/6/2015 | | | | FAIL |
Andrea Tuning
|
|
|
All planters shall be 8-feet in width.
Install a landscape planter in the parking row so parkign does not exceed 10 spaces.
The site plan and landscape plan should match one another.
All pole lighting and utilities can not be located within the required planter islands.
|
Routing - PLANNING | 2/6/2015 | | | | FAIL |
Susan Riggs
|
|
|
Amenities must be bonded for prior to issuance of a building permits. Amenities consist of walking paths, gazebo, picnic area, and benches. I have left 2 voice messages with the applicant Jeramy.
|