BLD-Final | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | PASS |
Mike Jordan
|
|
|
Andrea Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2015 | 7/1/2015 | 7/1/2015 | P | PASS |
Mike Jordan
|
|
|
Per email from darrell Fugate with Saint Al's, the site has been stabalized. Ok to release bond.
|
BLD-Final | 5/11/2015 | 5/12/2015 | 5/12/2015 | A | NR |
Mike Jordan
|
|
|
Andrea Phone #: ###-####. Site not stabalized. Called and spoke to andrea and noted that permit could not be finaled until site is stabalized per the ESC conditions.
|
BLD-Final | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | NR |
Mike Jordan
|
|
|
Seth Phone #: ###-####. PEr the ESC conditions, the site must be stabalized prior to passing the final.
|
Issue PAID IN FULL permit | | | 2/4/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 2/3/2015 | | |
|
|
|
|
Telephone call | | | 2/3/2015 | | DONE |
Candy A. Nichols
|
|
|
called David @ Ideal Demolition to let know permit is ready and how much is owed. Also told him we need the sewer cap info
|
Permit Ready to Issue | | | 2/3/2015 | | DONE |
Candy A. Nichols
|
|
|
need sewer cap
|
Telephone call | | | 1/30/2015 | | DONE |
Candy A. Nichols
|
|
|
called David Aparicio to let know the asurety bond we have on file is for $50000.00 but the demo permit bond amount is $140000.00. He said they would get another asurety bond for $90000.00.
|
Routing - Erosion and Sediment | 1/30/2015 | | 1/30/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED)
Demo-Commercial: Project involves Asbestos abatement work, demolition of the commercial buildings, cleanup and disposal of debris, and grading for future pavement parking lot. 1.70 Acres in total disturbance size.
|
First Notice | 7/1/2015 | 7/1/2015 | | | |
Mike Jordan
|
|
|
|
Application received | | 1/30/2015 | | | |
|
|
|
|