Print Statement | | | 9/25/2015 | | DONE |
|
|
|
|
Telephone call | | | 9/25/2015 | | DONE |
|
|
|
Spoke with Darrin about the MEC and PLM final values. He said that they should be the other way around from how he filled out the first notice
|
First Notice | | 8/31/2015 | 9/15/2015 | | DONE |
|
|
|
Mailed 9/16/15
|
Permanent Occupancy | | | 8/21/2015 | | DONE |
|
|
|
|
BLD-Final | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PASS |
Mike Jordan
|
|
|
Looking for Building Final Inspection. Business is usually open at 8 am. If needed earlier, please contact me 30 minutes in advance at ###-#### Phone #: ###-#### Inspection requested via web by Jason Jones. Ok for perm occ.
|
FIRE-Final Inspection | 8/19/2015 | 8/19/2015 | 8/19/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | CANC |
Troy Cobbley
|
|
|
Rescheduled per Jason Jones
|
FIRE-Alarm Testing | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Jason Jones
|
BLD-Final | 7/30/2015 | 7/31/2015 | 7/31/2015 | P | NR |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Needs fire sprinkler and alarm. ok to move in office furniture only.
|
FIRE-Final Inspection | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | PART |
Troy Cobbley
|
|
|
Remaining remodeled area life safety passed. Need the project related fire alarm and fire sprinkler permits finaled/completed.
|
BLD-Ceiling Grid Inspection | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. grid ok pending electrical rough in inspection.
|
BLD-Final | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | CANC |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | PART |
Mike Jordan
|
|
|
Will call to inform you when the electrical rough in inspection has been completed prior to having the framing rough-in inspection. Phone #: ###-#### Inspection requested via web by Jason Jones. INterior steel stud framed walls ok, pending electrical rough in inspection.
|
BLD-Conference | 7/2/2015 | 7/2/2015 | 7/2/2015 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 7/2/2015 | 7/2/2015 | 7/2/2015 | P | PART |
Mike Jordan
|
|
|
Ok to occupy the new training area (siute130) Two code compliant exits have now been provided.
|
BLD-Final | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | FAIL |
Mike Jordan
|
|
|
Temp Certification of Occupancy after (AM) Mechanical inspection and permit for duct detector has been applied for. Please give me a call for an update. Phone #: ###-####Inspection requested via web by Jason Jones.
|
FIRE-Final Inspection | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PART |
Troy Cobbley
|
|
|
Suite 130 life safety temporary is ok per scott until the duct smoke detector has been addressed. Permit has been submitted and approved. Waiting for actual inspection.
|
FIRE-Final Inspection | 7/1/2015 | 7/1/2015 | 7/1/2015 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was again for the large training area. The exit sign has been repaired, an alternative exit path has been approved by tim with additional exit signs and emergency light but the area can not be used until a fire alarm permit has been applied for.
|
BLD-Final | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | FAIL |
Mike Jordan
|
|
|
Not Building Final but Suite 130 Temp. We''''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### Inspection requested via web by Jason Jones Inspection Phone #: ###-#### Inspection requested via web by Jason Jones. Fire/life/safety has not passed, Still needs mech inspection for roof top units installed, duct detector requires a fire alarm permit. Also two exits will be required to exit the building. 2nd. exits is through construction and leads to a locked door. Use of this space not allowed at this time.
|
BLD-Other | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | CANC |
Mike Jordan
|
|
|
Not Building Final but Suite 130 Temp. We''''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### Inspection requested via web by Jason Jones Inspection Phone #: ###-#### Inspection requested via web by Jason Jones
|
FIRE-Final Inspection | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for a partial occupancy in the large open area. I have three issues, first is the non-functional exit sign at the north exit, second is the secondary exit will be through a construction zone and a fire alarm permit is required for the new duct smoke detector.
|
BLD-Final | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | CANC |
Mike Jordan
|
|
|
Not Building Final but Suite 130 Temp. We''''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### >> Inspection requested via web by Jason Jones Phone #: ###-#### >> Inspection requested via web by Jason Jones Inspection cancelled from web by: Jason Jones
|
BLD-Other | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | CANC |
Mike Jordan
|
|
|
Not Building Final but Suite 130 Temp. We''''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### >> Inspection requested via web by Jason Jones Phone #: ###-#### >> Inspection requested via web by Jason Jones Inspection cancelled from web by: Jason Jones
|
FIRE-Final Inspection | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | CANC |
Troy Cobbley
|
|
|
Not Building Final but Suite 130 Temp. We''''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### >> Inspection requested via web by Jason Jones Phone #: ###-#### >> Inspection requested via web by Jason Jones Inspection cancelled from web by: Jason Jones
|
BLD-Other | 6/26/2015 | 6/30/2015 | 6/30/2015 | A | CANC |
Mike Jordan
|
|
|
Not Building Final but Suite 130 Temp. We''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### >> Inspection requested via web by Jason Jones Inspection cancelled from web by: Jason Jones
|
BLD-Final | 6/26/2015 | 6/30/2015 | 6/30/2015 | A | CANC |
Mike Jordan
|
|
|
Not Building Final but Suite 130 Temp. We''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### >> Inspection requested via web by Jason Jones Inspection cancelled from web by: Jason Jones
|
FIRE-Final Inspection | 6/26/2015 | 6/30/2015 | 6/30/2015 | A | CANC |
Troy Cobbley
|
|
|
Not Building Final but Suite 130 Temp. We''ve completed all work in this new suite and are looking to obtain temp certification of occupancy so the training center can be operational in their new space, making their old space available for demo and construction of the proposed offices. Phone #: ###-#### >> Inspection requested via web by Jason Jones Inspection cancelled from web by: Jason Jones
|
BLD-Energy code compliance | 6/26/2015 | 6/29/2015 | 6/29/2015 | A | NR |
Mike Jordan
|
|
|
Not a Building Final but we are looking at obtaining temporary certification of occupancy for suite 130. All work is completed in this suite and we are needing to move the training center into this new space before we can start demoing the existing space they occupy. Phone #: ###-#### Inspection requested via web by Jason Jones
|
BLD-Energy code compliance | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PASS |
Mike Jordan
|
|
|
Before coming out, please give me a call so I make sure not to waste your time. Suite 110 is the current area of concern. This is our status: Temp electrical=passed, mechanical permit pulled-no inspections required for this portion Permit #MEC15-02281, Ceiling grid and insulation have been installed, need inspected. We are looking to get all inspections necessary for the temporary Cert of Occ for the two offices in Suite 110. Phone #: ###-#### Inspection requested via web by Jason Jones
|
BLD-Final | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PART |
Mike Jordan
|
|
|
Before coming out, please give me a call so I make sure not to waste your time. Suite 110 is the current area of concern. This is our status: Temp electrical=passed, mechanical permit pulled-no inspections required for this portion Permit #MEC15-02281, Ceiling grid and insulation have been installed, need inspected. We are looking to get all inspections necessary for the temporary Cert of Occ for the two offices in Suite 110. Phone #: ###-#### Inspection requested via web by Jason Jones. ok to occupy the two new offices that were created i the existing areas only.
|
FIRE-Final Inspection | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PART |
Troy Cobbley
|
|
|
The two offices 103 and 104 in Suite 110 are ok to occuppy. They have been marked and dated on the city approved plan. I noted all fire extinguishers to be current with inspections.
|
BLD-Framing/Rough-in | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Interior steel framing for new offices. no hardlids at this time, nedds sprinkler rough in.
|
BLD-Final | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | NR |
Jim Storey
|
|
|
Sheet rock up, taped, textured and painted, ceiling grid is in but no tiles have been placed, electrical is in place but not finaled (inspection scheduled), fire sprinkler inspection scheduled for 5/21/15 pm, want to complete all inspections for temporary occupancy permitting. Please call me with any questions. Phone #: ###-#### Inspection requested via web by Jason Jones
|
BLD-Energy code compliance | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | NR |
Jim Storey
|
|
|
Sheet rock up, taped, textured and painted, ceiling grid is in but no tiles have been placed, electrical is in place but not finaled (inspection scheduled), fire sprinkler inspection scheduled for 5/21/15 pm, want to complete all inspections for temporary occupancy permitting. Please call me with any questions. Phone #: ###-#### Inspection requested via web by Jason Jones
|
BLD-Ceiling Grid Inspection | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | PART |
Jim Storey
|
|
|
Sheet rock up, taped, textured and painted, ceiling grid is in but no tiles have been placed, electrical is in place but not finaled (inspection scheduled), fire sprinkler inspection scheduled for 5/21/15 pm, want to complete all inspections for temporary occupancy permitting. Please call me with any questions. Phone #: ###-#### Inspection requested via web by Jason Jones two offices south end of building ceilling ok/ ok to use space with progrestion of const.
|
FIRE-Final Inspection | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | NR |
Forrest France
|
|
|
Project not in condition for final inspection at this time. Discussed inspection categories, related trade work, project phasing and completion dates with contractor.
|
BLD-Wall cover | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | PASS |
Mike Jordan
|
|
|
Metal stud wall framed and has electrical roughed in. Ready for cover inspection. Phone #: ###-#### Inspection requested via web by Jason Jones. INterior steel stud framed walls for new offices ok.
|
BLD-Final | 5/5/2015 | 5/6/2015 | 5/6/2015 | P | NR |
Mike Jordan
|
|
|
Dan Phone #: ###-####. No plans or access. Provided phone number is no longer in service.
|
Issue PAID IN FULL permit | | | 4/29/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/29/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/28/2015 | | DONE |
|
|
|
All requirements met
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 4/27/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 2/18/2015 | | 4/27/2015 | | PASS |
Tim L. Woodard
|
|
|
Level 3 The McClain Companies Chane in Occupancy
|
Routing - PLAN CHECK | 4/17/2015 | | 4/27/2015 | | PASS |
Tim L. Woodard
|
|
|
Approved with latest revisions for assembly "Training" room. TLW
|
Routing - MECHANICAL | 4/17/2015 | | 4/20/2015 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 4/17/2015 | | 4/17/2015 | | PASS |
Beverly Mountain
|
|
|
|
Route to Impact Fee Review | 3/11/2015 | 3/14/2015 | 3/16/2015 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
1st review completed | | | 3/7/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 2/18/2015 | | 3/7/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 2/18/2015 | 2/18/2015 | 2/24/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - Erosion and Sediment | 2/18/2015 | | 2/20/2015 | | PASS |
Andy J. Long
|
|
|
No ESC permit needed. No trenching or TI work proposed that requires permit.
|
Routing PW Sewer Rating | 2/18/2015 | | 2/20/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - MECHANICAL | 2/18/2015 | | 2/20/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 2/18/2015 | | 2/18/2015 | | PASS |
Cody Riddle
|
|
|
Requested information from the architect clarifying the proposed use of the space.
2/19/15-Applicant clarified the use of the space as professional office. Use approved by 2005 CUP.
|
Routing - Addressing | 2/18/2015 | | 2/18/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 2/18/2015 | | 2/18/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLUMBING | 2/18/2015 | | 2/18/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 2/18/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan Reviewer's activity | | | 2/18/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
email sent in regards to ACHD, Major TI
Matt, your project has been routed for plan review under the Major TI process. Tim Woodard will be the plans examiner on your project.
Please contact ACHD to inquire if they have any requirements or fees for this change in occupancy. We will need a response from them prior to issuing the permit.
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####
|
Intake Approval | | | 2/9/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
This is a major TI. The existing occupancy is B for othe of the existing spaces. There is no assembly occupancy listed on the certificated of occupancy. Please upload the completed 520 check list.
|
Application received | | | 2/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 4 2015 3:09PM
|