Telephone call | | | 9/4/2015 | | DONE |
|
|
|
Sent on email to Tom Allegrezza, 9/2 & 9/4, making sure that the final value he gave me for the mechanical with BS & R Eauipment Co Inc was the correct amount. He gave 82,238 which is 59,238 more than what BS & R gave for thier initial value
|
First Notice | | 7/10/2015 | 8/10/2015 | | DONE |
|
|
|
Mailed 8/11
|
Permanent Occupancy | | | 6/30/2015 | | DONE |
|
|
|
|
BLD-Final | 6/26/2015 | 6/29/2015 | 6/29/2015 | A | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### c/n made ok
|
BLD-Final | 6/24/2015 | 6/25/2015 | 6/25/2015 | P | PART |
Dave Hannah
|
|
|
Tom Phone #: ###-#### needs ada door hardwear on restroom and signage also needs max occ sign posted
|
Temporary Occupancy | 6/25/2015 | 9/23/2015 | 6/25/2015 | | DONE |
Carlos Velazquez
|
|
|
|
FIRE-Final Inspection | 6/8/2015 | 6/9/2015 | 6/9/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
FIRE-Final Inspection | 6/1/2015 | 6/2/2015 | 6/3/2015 | P | CANC |
Jim Page
|
|
|
Called the onsite point of contact, Tom Phone #: ###-####. He informed me that the electrical shut down was not working correctly for the commercial hood system and that the inspection would need to be rescheduled.
|
Routing - PLANNING | 4/15/2015 | | 4/15/2015 | | PASS |
Andrea Tuning
|
|
|
|
Plan Modification Accepted | | | 4/13/2015 | | DONE |
|
|
|
started workflow for exterior modifications
|
Issue PAID IN FULL permit | | | 3/10/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/10/2015 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 3/5/2015 | 3/5/2015 | 3/6/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Plan assigned to (CDM) | 2/19/2015 | 2/19/2015 | 3/6/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
need GC & rev cert of val
|
Routing - PLAN CHECK | 3/5/2015 | | 3/6/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Rating | 2/20/2015 | | 3/5/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Environmental | 2/20/2015 | | 3/4/2015 | | PASS |
Rick Christenson
|
|
|
Contractor needs to verify Thermaco unit is in working condition. Unit can be replaced with Canplas grease trap of appropriate size.
|
Routing - MECHANICAL | 3/4/2015 | | 3/4/2015 | | PASS |
Troy James
|
|
|
red line plans
|
1st review completed | | | 3/4/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/19/2015 | | 2/26/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 2/19/2015 | 2/19/2015 | 2/25/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed report to design professional in charge. Attached report to case.
|
Routing - PLUMBING | 2/19/2015 | | 2/20/2015 | | PASS |
Daryl Spivey
|
|
|
Per plans and ISPC.
|
Routing - MECHANICAL | 2/19/2015 | | 2/20/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 2/19/2015 | | 2/20/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 2/19/2015 | | 2/19/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 2/19/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 2/18/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
2-18-15
Richard I have deleted all of the drawings. Please see the submittal standards and re upload all of the required drawings.
Please upload the check list in the correct orientation in the documents folder.
Please upload the floor plan with the stamp approval from the health department.
The drawings need to be uploaded in the drawing folder not the document folder.
The drawings must be uploaded to read left to right.
The drawings files need to be named per conventional naming standards A-1 Floor Plan, M-1 Mecanical details for example.
|
Intake Approval | | | 2/9/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1- please upload completed check list for pre screen to be completed.
2- Please have licensed architect stamp floor plan as the square footage for existing A occupancy is over the allowed 1500 sq ft tenant space excemption.
3- Please re name drawings to meet standard naming convention -- A1 floor plan
|
Application received | | | 2/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 5 2015 5:27PM
|
Routing - PLANNING | 2/26/2015 | | | | |
Cody Riddle
|
|
|
Increase in dinning area occupant from 52 to 85
|