First Notice | 5/1/2015 | 5/1/2015 | 12/16/2016 | | DONE |
Jim Sly
|
|
|
This permit finaled on the web by Ami Tracy
|
BLD-Final | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PASS |
Jim Sly
|
|
|
brad Phone #: ###-####
|
DOC - Permit Finaled | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 4/29/2015 | 4/30/2015 | 4/30/2015 | A | NR |
Jim Sly
|
|
|
Bradden Phone #: ###-####
|
BLD-Footing | 4/14/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/31/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/31/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 3/27/2015 | | |
|
|
|
|
Routing - Addressing | 3/26/2015 | | 3/27/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PLAN CHECK | 3/27/2015 | | 3/27/2015 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2015 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 3/27/2015 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Plan assigned to (SRZ) | 3/17/2015 | | 3/27/2015 | | PASS |
Sam Zahorka
|
|
|
1st review completed. - ePlanReview Carport
|
Route to Impact Fee Review | 3/24/2015 | 3/27/2015 | 3/26/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 3/17/2015 | | 3/26/2015 | | PASS |
Susan Riggs
|
|
|
Signed off in ePlanReview
|
Routing - PLAN CHECK | 3/17/2015 | | 3/24/2015 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 3/24/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing PW Solid Waste | 3/17/2015 | | 3/23/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - FIRE | 3/17/2015 | | 3/23/2015 | | PASS |
Scott Arellano
|
|
|
No comments attached. Approved as shown.
|
Routing - Design Review | 3/17/2015 | | 3/18/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00054
|
Routing PW Drainage | 3/17/2015 | | 3/18/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING Land Div | 3/17/2015 | | 3/18/2015 | | PASS |
Dave Abo
|
|
|
Lot 4, Block 1, Village Chaton Subdivision
|
Routing - PUBLIC WORKS | 3/17/2015 | | 3/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 3/17/2015 | | 3/17/2015 | | PASS |
Evan Jenkins
|
|
|
Installing 4 (4 Stall Carport) at Village Chaton Subdivision.
|
Plan Reviewer's activity | | | 3/17/2015 | | DONE |
|
|
|
2nd plan intake review approved
|
Intake Approval | | | 3/17/2015 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 3/17/2015 | | 3/17/2015 | | DONE |
John Menard
|
|
|
|
Routing - Addressing | 3/17/2015 | | 3/17/2015 | | FAIL |
Emily Dixon
|
|
|
Each carport is on a separate parcel. We need a separate building permit and address for each carport.
|
Intake Approval | | | 2/11/2015 | | FAIL |
|
|
|
(2-11-15) Consider the redlines on the plan intake checklist. Please resolve all circled items.
|
Application received | | | 2/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 9 2015 3:21PM
|