Second Notice | | 6/20/2015 | 6/24/2015 | | DONE |
Christina Prado
|
|
|
completed 6-24-2015
|
First Notice | 5/8/2015 | 5/8/2015 | 6/10/2015 | | DONE |
Mike Jordan
|
|
|
Mailed out 6-10-15
|
BLD-Final | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PART |
Mike Jordan
|
|
|
Please call when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton. everything ok. Need special inspection final letter.
|
FIRE-Final Inspection | 4/28/2015 | 4/28/2015 | 4/28/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 4/10/2015 | 4/10/2015 | 4/10/2015 | P | PASS |
Mike Jordan
|
|
|
Call when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Energy code compliance | 4/10/2015 | 4/10/2015 | 4/10/2015 | P | PASS |
Mike Jordan
|
|
|
Call when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 4/7/2015 | 4/8/2015 | 4/8/2015 | P | NR |
Mike Jordan
|
|
|
Bob Phone #: ###-####.
|
BLD-Conference | 3/23/2015 | 3/23/2015 | 3/23/2015 | A | DONE |
Mike Jordan
|
|
|
Park on the North side and call me. I''ll come out and get you. Phone #: ###-#### Inspection requested via web by Bob Thornton.
|
Issue PAID IN FULL permit | | | 3/12/2015 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 3/11/2015 | | DONE |
Alexandra L. DeYoung
|
|
|
spoke with GC, stated value was not changing, gave him fees
|
Plan assigned to (AJS) | 2/11/2015 | 2/11/2015 | 3/10/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
my review completed Level 3 TI - Paper - Treasure Valley Coffee
|
Routing - PLAN CHECK | 3/9/2015 | | 3/10/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan resubmittals received | | | 3/10/2015 | | DONE |
|
|
|
received 2 copies of sheets CS, A1, OP, and E1, hardware specs, plan review report, and one letter- put on Adele's desk
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/10/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Permit Ready to Issue | | | 3/10/2015 | | DONE |
Candy A. Nichols
|
|
|
need GC, certificate of value & customer needs to sign the permit app and please re scan
|
Inspection Record Card- Bld | | | 3/10/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 3/10/2015 | | DONE |
|
|
|
left message for Greg- said permit is ready for pick up and that application needs signed, we need GC form, and certificate of value- then we will add fees
|
1st review completed | | | 3/6/2015 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - FIRE | 3/2/2015 | | 3/6/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - PLAN CHECK | 2/13/2015 | | 3/2/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 2/11/2015 | | 2/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 2/11/2015 | | 2/13/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 2/11/2015 | | 2/11/2015 | | PASS |
Sarah Schafer
|
|
|
Approved
|
Pending Assignment by JCB | 2/10/2015 | | 2/11/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 2/10/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Plans ACCEPTED BY PLAN TECH | | | 2/10/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/10/2015 | | DONE |
|
|
|
|
Application received | | 2/10/2015 | | | |
|
|
|
|