Third Notice | | 6/14/2015 | 6/23/2015 | | DONE |
Christina Prado
|
|
|
Completed 6-23-15
|
Print Statement | | | 6/23/2015 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 5/14/2015 | 6/9/2015 | | DONE |
|
|
|
sent in mail
|
First Notice | | 4/5/2015 | 5/4/2015 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 3/25/2015 | 3/26/2015 | 3/26/2015 | A | PASS |
Mike Jordan
|
|
|
Jenny Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy | | | 3/26/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PART |
Mike Jordan
|
|
|
Change and time Per Damion// late as possible please Phone #: ###-####. Ok for temp occ. remove the thumbturns from main doors.
|
FIRE-Final Inspection | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Fire alarm contractor and electrical contractor are currently repairing portions of the mall fire alarm system. I spoke to Ray Criner about follow up inspections to verifiy that the entire mall system gets repaired and becomes 100% functional.
|
CHANGE STATUS TO (ISS) | | | 3/25/2015 | | DONE |
Christina Prado
|
|
|
CLosed by mistake
|
BLD-Framing/Rough-in | 3/12/2015 | 3/13/2015 | 3/13/2015 | P | PART |
Mike Jordan
|
|
|
Damion// prefer after 4pm Phone #: ###-####. Store front soffit framing only ok, pending electrical and fire sprinkler rough in inspections.
|
BLD-Framing/Rough-in | 3/9/2015 | 3/11/2015 | 3/11/2015 | P | PART |
Mike Jordan
|
|
|
Damian-partial Phone #: ###-####. iINterior steel stud walls for changing rooms and column bump outs only.
|
Issue PAID IN FULL permit | | | 3/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 3/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (CDM) | 2/17/2015 | 2/17/2015 | 3/4/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 3/4/2015 | | 3/4/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/4/2015 | | DONE |
Candy A. Nichols
|
|
|
need GC and rev cert of val-3-6-15 all requirements met CAN
|
Routing - PLAN CHECK | 2/17/2015 | | 3/2/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 3/2/2015 | | FAIL |
|
|
|
|
Intake Approval | | | 2/17/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
2-17-15
Please complete and upload the completed 518 checklist.
Please see the electronic submittal standards for the drawings.
They need to be uploaded individually and named to meet the standard naming convetion. A0.0 Cover Sheet.
See electronic submittal standard. http://pds.cityofboise.org/media/105041/electronicstandards.pdf
|
Intake Approval | | | 2/17/2015 | | PASS |
|
|
|
|
Application received | | | 2/12/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 12 2015 9:27AM
|
Intake Approval | | | 2/12/2015 | | FAIL |
|
|
|
Please complete and upload the completed 518 checklist.
Please upload the approval from the mall for this renovaiton.
Please see the electronic submittal standards for the drawings.
They need to be uploaded individually and named to meet the standard naming convetion. A0.0 Cover Sheet.
See electronic submittal standard. http://pds.cityofboise.org/media/105041/electronicstandards.pdf
|