First Notice | 10/20/2015 | 10/20/2015 | 10/28/2015 | | DONE |
Jim Sly
|
|
|
This permit finaled on the web by Michele Rodgers
|
BLD-Conference | 10/19/2015 | 10/20/2015 | 10/20/2015 | A | PASS |
Jim Sly
|
|
|
We would like to final this job...fire has been completed. Please call Chuck Rauch at the above number. Phone #: ###-#### Inspection requested via web by Michele Rodgers
|
DOC - Permit Finaled | 10/20/2015 | 10/20/2015 | 10/20/2015 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 5/8/2015 | 5/11/2015 | 5/11/2015 | A | NR |
Jim Sly
|
|
|
Mike Phone #: ###-#### Need Fire Finals.
|
FIRE-Final Inspection | 5/8/2015 | 5/11/2015 | 5/11/2015 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm permit to be issued/inspected prior to a life safety inspection
|
BLD-Ceiling Grid Inspection | 3/17/2015 | 3/17/2015 | 3/17/2015 | P | PART |
Jim Sly
|
|
|
Mike Phone #: ###-#### Pharmacy
|
BLD-Ceiling Grid Inspection | 3/12/2015 | 3/13/2015 | 3/13/2015 | A | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/10/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/23/2015 | | 3/6/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/23/2015 | | 3/6/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - C.D.H | 2/23/2015 | | 3/6/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Rating | 2/23/2015 | | 3/6/2015 | | PASS |
Jennifer Bruner
|
|
|
|
1st review completed | | | 3/6/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/6/2015 | | DONE |
|
|
|
Need GC Form. Also need signature page for the revised value. Scans not working, Brittany has revised cert of value 3/10/15
|
Routing - FIRE | 2/23/2015 | 2/23/2015 | 3/3/2015 | | PASS |
Scott Arellano
|
|
|
No separate comments attached to plans. However, separate Fire Sprinkler and Fire Alarm permits will be required due to the construction of new partition walls associated with the new Starbucks.
|
Intake Approval | | | 2/23/2015 | | PASS |
|
|
|
|
Routing - PLUMBING | 2/23/2015 | | 2/23/2015 | | PASS |
Bill VanDegrift
|
|
|
need to print the plumbing plans to have in the field for the early start
|
Routing - Addressing | 2/23/2015 | | 2/23/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 2/23/2015 | | 2/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 2/19/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 19 2015 12:54PM
|