BLD-Final | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | NH |
Jim Sly
|
|
|
Phone #: 6972363 >> Inspection requested via mobile web by Duane seid No access.......C/N Need Fire sprinkler final.....Electr. Final and ESC final.
|
FIRE-Final Inspection | 5/28/2015 | 5/29/2015 | 5/29/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. New general contractor to provide fire sprinkler and fire alarm contracts/permits.
|
BLD-Final | 5/26/2015 | 5/27/2015 | 5/27/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: 6972363 >> Inspection requested via mobile web by Duane seid
|
BLD-Framing/Rough-in | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | PASS |
Phil Shearer
|
|
|
Phone #: 6972363 >> Inspection requested via mobile web by Duane seid
|
BLD-Footing | 5/4/2015 | 5/4/2015 | 5/4/2015 | P | PASS |
Mike Jordan
|
|
|
Phone #: 6972363 >> Inspection requested via mobile web by Duane seid
|
BLD-Footing | 4/20/2015 | 4/21/2015 | 4/21/2015 | P | PASS |
Phil Shearer
|
|
|
wall // Dwane Phone #: ###-####
|
BLD-Footing | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Phil Shearer
|
|
|
and foundation // Dewain Phone #: ###-####. Loading dock footings
|
Issue PAID IN FULL permit | | | 4/7/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/7/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 4/6/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 3/16/2015 | 3/16/2015 | 4/6/2015 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - Overland Plaza due 4/16 First review completed
|
Routing - PLAN CHECK | 4/6/2015 | | 4/6/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2015 | | DONE |
|
|
|
Need RP, GC and Revised Cert of Value
|
Routing Off Site - STRUCTURAL | 3/16/2015 | | 4/6/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 4/2/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/16/2015 | | 4/2/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 3/16/2015 | 3/16/2015 | 3/19/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - Design Review | 3/16/2015 | | 3/18/2015 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH15-00022
|
Routing - Addressing | 3/16/2015 | | 3/16/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2015 | | 3/16/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 3/16/2015 | | 3/16/2015 | | PASS |
Evan Jenkins
|
|
|
OVERLAND PLAZA) Vanilla shell work in preparation for a future Tenant Improvement under separate permit. Demo of existing loading ramp and the construction of a new loading ramp
|
Intake Approval | | | 3/12/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard and plan review fees paid.
|
Intake Approval | | | 2/26/2015 | | FAIL |
Tim L. Woodard
|
|
|
Please provide the #520 Major Tenant Improvement Checklist. This checklist will require you to submit aditional documents as well. Those documents missing from your application include: #304 Registered Design Proffesional Form, Erosion and Sediment Control Waiver Letter & Fire Flow letter from United Water.
If you have any questions please feel free to call me to discuss.
Best regards,
Tim Woodard
Plans Examiner II
City of Boise
208 384 3817
twoodard@cityofboise.org
|
Application received | | | 2/24/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2015 7:49AM
|
Pending Assignment by JCB | 3/16/2015 | | | | |
Jason Blais
|
|
|
|