BLD-Final | 6/8/2015 | 6/9/2015 | 6/9/2015 | A | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | NR |
Jim Storey
|
|
|
Zach Phone #: ###-#### need ele final for fireplace.
|
BLD-Energy code compliance | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Jim Storey
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 4/6/2015 | 4/6/2015 | 4/6/2015 | P | PASS |
Jim Storey
|
|
|
Zack Phone #: ###-####
|
Plan Modification Accepted | | | 3/31/2015 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 3/31/2015 | | 3/31/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Footing | 3/20/2015 | 3/20/2015 | 3/20/2015 | P | PASS |
Phil Shearer
|
|
|
Zack Phone #: ###-####
|
PubWorks Subgrade Approval | 3/20/2015 | 3/20/2015 | 3/20/2015 | | DONE |
Jason C. Taylor
|
|
|
* Garage Addition**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Routing Walk-In (BLD) | 3/19/2015 | 3/19/2015 | 3/19/2015 | A | FAIL |
Perry Paine
|
|
|
need approved plan / new site plan / foundation engineering / subgrade inspection and ESC permit.
|
Routing Walk-In (BLD) | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | DONE |
Perry Paine
|
|
|
|
Routing Walk-In (PW Hillside) | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (Zoning) | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | PASS |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | DONE |
Perry Paine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/19/2015 | | DONE |
|
|
|
|
Fees Due Hold | 3/3/2015 | | 3/11/2015 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing - MECHANICAL | 3/4/2015 | | 3/4/2015 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (BLD) | 3/2/2015 | 3/2/2015 | 3/2/2015 | P | PASS |
Tisha Gallop
|
|
|
|
Plan assigned to (LEG) Tisha | 3/2/2015 | | 3/2/2015 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/2/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/2/2015 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 2/24/2015 | 2/24/2015 | 2/25/2015 | P | FAIL |
Tisha Gallop
|
|
|
need engineering
|
1st review completed | | | 2/25/2015 | | |
|
|
|
|
Application received | | 2/24/2015 | | | |
|
|
|
|