Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-00483
StatusFinaled
Name BILTMORE COMPANY
Site Address 6650 W WINSTON LN
Project NameAberdeen #4
Customer NumberBLD15-00483 - 490
ePlanReviewYes
Description
L12B1 - 6650 Winston (Bldg 3): To construct a new 3,836 sq. ft., two story, Four unit, apartment building. Each unit has two bedrooms and two bathrooms. The 1st story units are 959 square feet and are required to be Type 'B' units. The 2nd story units are 959 square feet. All units share a common path of egress into and through a 1/2-hour rated exit corridor with 20 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partitions and one hour horizontal assemblies are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00276 & CUP13-00017 Per Planning and Zoning. **SRZ*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Zoning Approval8/21/20158/21/20158/21/2015 PASS
DetailsJosh Wilson
Permanent Occupancy  8/21/2015 DONE
DetailsChristina Prado
BLD-Final8/17/20158/18/20158/18/2015PPART
DetailsMike Jordan
Pat Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once zoning signs perm.
FIRE-Final Inspection8/18/20158/18/20158/18/2015PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection8/13/20158/17/20158/17/2015PCANC
DetailsTroy Cobbley
Rescheduled for tomorrow morning
FIRE-Final Inspection8/14/20158/17/20158/17/2015AFAIL
DetailsTroy Cobbley
Project related fire sprinkler and fire alarm permits are not ready yet. I noted the boxes to cover the piping in the storage closets has not been installed
BLD-Other6/25/20156/25/20156/25/2015PPASS
DetailsMike Jordan
RC1 channel: Pat Phone #: ###-####
BLD-Other6/23/20156/25/20156/25/2015APASS
DetailsMike Jordan
RC1 channel // Pat Phone #: ###-####
BLD-Energy code compliance6/18/20156/19/20156/19/2015APASS
DetailsMike Jordan
Pat Phone #: ###-####
BLD-Framing/Rough-in6/17/20156/18/20156/18/2015APASS
DetailsMike Jordan
Pat Phone #: ###-####
BLD-Framing/Rough-in6/16/20156/17/20156/17/2015AFAIL
DetailsMike Jordan
Pat Phone #: ###-####. Provide double studs under2ply T11 truss upstairs, complete all firecaulking, repair holes on sheet rock at 1hr. exterior wall, repair hole on rated ply at laydwon parapet. Nail off all simson hangars. Correction notice posted.
BLD-Wall Bracing6/1/20156/1/20156/1/2015PPASS
DetailsMike Jordan
Shear // Pat Phone #: ###-####
BLD-Foundation5/15/20155/18/20155/18/2015PPASS
DetailsMike Jordan
John Phone #: ###-####
BLD-Foundation5/14/20155/15/20155/15/2015PNR
DetailsMike Jordan
Dane Phone #: ###-####
BLD-Foundation5/13/20155/14/20155/14/2015PCANC
DetailsMike Jordan
John Phone #: ###-####
BLD-Footing5/14/20155/14/20155/14/2015PPASS
DetailsMike Jordan
john Phone #: ###-####
Issue PAID IN FULL permit  5/11/2015 DONE
Print Occupancy Form  5/11/2015 DONE
OVERRIDE  4/16/2015  
PLANS/APPL TAKEN TO FRONT DESK  4/16/2015 DONE
DetailsSam Zahorka
Permit Ready to Issue  4/16/2015 DONE
All requirements met
Plan assigned to (SRZ)2/27/2015 4/16/2015 PASS
DetailsSam Zahorka
Pending others to PASS
Routing - FIRE4/13/20154/13/20154/15/2015 PASS
DetailsScott Arellano
Attached revised comments to plans.
Routing - MECHANICAL4/15/2015 4/15/2015 PASS
DetailsTroy James
Routing - PLANNING Land Div2/27/2015 4/15/2015 PASS
DetailsTodd Tucker
Routing - PLAN CHECK4/10/2015 4/10/2015 PASS
DetailsSam Zahorka
Routing - Addressing4/1/2015 4/1/2015 PASS
DetailsEmily Dixon
Routing - MECHANICAL4/1/2015 4/1/2015 FAIL
DetailsTroy James
Route to Impact Fee Review3/23/20153/26/20153/26/2015 PASS
DetailsCindy M. Gould
1st review completed  3/23/2015 DONE
DetailsSam Zahorka
Routing - PLAN CHECK2/27/2015 3/23/2015 FAIL
DetailsSam Zahorka
Routing - MECHANICAL2/27/2015 3/12/2015 FAIL
DetailsTroy James
Routing - FIRE2/27/20152/27/20153/4/2015 FAIL
DetailsScott Arellano
Attached comments to plans. Emailed plan review report to applicant.
Routing PW Drainage2/27/2015 3/3/2015 PASS
DetailsBrian Murphy
Routing - Design Review2/27/2015 3/3/2015 PASS
DetailsJosh Wilson
Routing PW Sewer Rating3/2/2015 3/2/2015 PASS
DetailsJennifer Bruner
West Boise Sewer District
Routing PW Street Lights2/27/2015 3/2/2015 PASS
DetailsMike D Hedge
Routing PW Solid Waste2/27/2015 3/2/2015 PASS
DetailsMegan Durrell
Routing - PLUMBING2/27/2015 2/27/2015 PASS
DetailsDaryl Spivey
Pending Assignment by JCM2/27/2015 2/27/2015 DONE
DetailsJohn Menard
Routing - Addressing2/27/2015 2/27/2015 FAIL
DetailsEmily Dixon
No parcel numbers yet for Aberdeen Place Sub No 04.
Routing - PUBLIC WORKS2/27/2015 2/27/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment2/27/2015 2/27/2015 PASS
DetailsEvan Jenkins
(SITE PREP INSPECTION REQUIRED)
L12B1 - 6650 Winston (Bldg 3): Aberdeen Building Type 3 (8 buildings) as part of a multifamily 4-Plex project consisting of 12 two-story buildings located at Raymond & Colehaven. Interior private streets are named N. Fry Lane and W. Winston Lane. The Subdivision Final Plat is referenced under SUB14-00026. There will be 3 types of buildings and 4 color schemes mixed throughout the buildings.
Application received  2/25/2015 DONE
Application submitted via PDS Online on Feb 25 2015 12:27PM
First Notice 8/31/2015   
BLD-Final8/21/20158/21/2015 P 
DetailsMike Jordan