Zoning Approval | 8/21/2015 | 8/21/2015 | 8/21/2015 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 8/21/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 8/17/2015 | 8/18/2015 | 8/18/2015 | P | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once zoning signs perm.
|
FIRE-Final Inspection | 8/18/2015 | 8/18/2015 | 8/18/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 8/13/2015 | 8/17/2015 | 8/17/2015 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning
|
FIRE-Final Inspection | 8/14/2015 | 8/17/2015 | 8/17/2015 | A | FAIL |
Troy Cobbley
|
|
|
Project related fire sprinkler and fire alarm permits are not ready yet. I noted the boxes to cover the piping in the storage closets has not been installed
|
BLD-Other | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PASS |
Mike Jordan
|
|
|
RC1 channel: Pat Phone #: ###-####
|
BLD-Other | 6/23/2015 | 6/25/2015 | 6/25/2015 | A | PASS |
Mike Jordan
|
|
|
RC1 channel // Pat Phone #: ###-####
|
BLD-Energy code compliance | 6/18/2015 | 6/19/2015 | 6/19/2015 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 6/17/2015 | 6/18/2015 | 6/18/2015 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 6/16/2015 | 6/17/2015 | 6/17/2015 | A | FAIL |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Provide double studs under2ply T11 truss upstairs, complete all firecaulking, repair holes on sheet rock at 1hr. exterior wall, repair hole on rated ply at laydwon parapet. Nail off all simson hangars. Correction notice posted.
|
BLD-Wall Bracing | 6/1/2015 | 6/1/2015 | 6/1/2015 | P | PASS |
Mike Jordan
|
|
|
Shear // Pat Phone #: ###-####
|
BLD-Foundation | 5/15/2015 | 5/18/2015 | 5/18/2015 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 5/14/2015 | 5/15/2015 | 5/15/2015 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 5/13/2015 | 5/14/2015 | 5/14/2015 | P | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Footing | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Mike Jordan
|
|
|
john Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/11/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/11/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 4/16/2015 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2015 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 4/16/2015 | | DONE |
|
|
|
All requirements met
|
Plan assigned to (SRZ) | 2/27/2015 | | 4/16/2015 | | PASS |
Sam Zahorka
|
|
|
Pending others to PASS
|
Routing - FIRE | 4/13/2015 | 4/13/2015 | 4/15/2015 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to plans.
|
Routing - MECHANICAL | 4/15/2015 | | 4/15/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 2/27/2015 | | 4/15/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLAN CHECK | 4/10/2015 | | 4/10/2015 | | PASS |
Sam Zahorka
|
|
|
|
Routing - Addressing | 4/1/2015 | | 4/1/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - MECHANICAL | 4/1/2015 | | 4/1/2015 | | FAIL |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/23/2015 | 3/26/2015 | 3/26/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 3/23/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 2/27/2015 | | 3/23/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - MECHANICAL | 2/27/2015 | | 3/12/2015 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 2/27/2015 | 2/27/2015 | 3/4/2015 | | FAIL |
Scott Arellano
|
|
|
Attached comments to plans. Emailed plan review report to applicant.
|
Routing PW Drainage | 2/27/2015 | | 3/3/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 2/27/2015 | | 3/3/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Sewer Rating | 3/2/2015 | | 3/2/2015 | | PASS |
Jennifer Bruner
|
|
|
West Boise Sewer District
|
Routing PW Street Lights | 2/27/2015 | | 3/2/2015 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 2/27/2015 | | 3/2/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLUMBING | 2/27/2015 | | 2/27/2015 | | PASS |
Daryl Spivey
|
|
|
|
Pending Assignment by JCM | 2/27/2015 | | 2/27/2015 | | DONE |
John Menard
|
|
|
|
Routing - Addressing | 2/27/2015 | | 2/27/2015 | | FAIL |
Emily Dixon
|
|
|
No parcel numbers yet for Aberdeen Place Sub No 04.
|
Routing - PUBLIC WORKS | 2/27/2015 | | 2/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 2/27/2015 | | 2/27/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED)
L12B1 - 6650 Winston (Bldg 3): Aberdeen Building Type 3 (8 buildings) as part of a multifamily 4-Plex project consisting of 12 two-story buildings located at Raymond & Colehaven. Interior private streets are named N. Fry Lane and W. Winston Lane. The Subdivision Final Plat is referenced under SUB14-00026. There will be 3 types of buildings and 4 color schemes mixed throughout the buildings.
|
Application received | | | 2/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2015 12:27PM
|
First Notice | | 8/31/2015 | | | |
|
|
|
|
BLD-Final | 8/21/2015 | 8/21/2015 | | P | |
Mike Jordan
|
|
|
|