BLD-Final | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 8/10/2015 | | DONE |
|
|
|
|
BLD-Final | 8/4/2015 | 8/5/2015 | 8/5/2015 | P | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
FIRE-Final Inspection | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety inspection passed/complete
|
Zoning Approval | 8/4/2015 | 8/4/2015 | 8/4/2015 | | PASS |
Josh Wilson
|
|
|
|
BLD-Other | 6/15/2015 | 6/15/2015 | 6/15/2015 | P | PASS |
Mike Jordan
|
|
|
Rc1 channel - Pat Phone #: ###-####
|
BLD-Energy code compliance | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Energy code compliance | 6/8/2015 | 6/8/2015 | 6/8/2015 | P | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 6/8/2015 | 6/8/2015 | 6/8/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | NR |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Wall Bracing | 5/19/2015 | 5/19/2015 | 5/19/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
Fees Due Hold | 4/30/2015 | | 5/1/2015 | | DONE |
|
|
|
|
BLD-Foundation | 4/29/2015 | 4/30/2015 | 4/30/2015 | P | PASS |
Phil Shearer
|
|
|
John Phone #: ###-####
|
BLD-Footing | 4/28/2015 | 4/29/2015 | 4/29/2015 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
Fees Due Hold | 4/29/2015 | | 4/29/2015 | | DONE |
Rita DeYoung
|
|
|
|
Fees Due Hold | 4/28/2015 | | 4/28/2015 | | DONE |
Kristal Soland
|
|
|
|
Issue PAID IN FULL permit | | | 4/27/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/27/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 4/16/2015 | | |
|
|
|
|
Plan assigned to (SRZ) | 3/18/2015 | 3/18/2015 | 4/16/2015 | | PASS |
Sam Zahorka
|
|
|
Pending others to PASS
|
Routing - PLUMBING | 3/18/2015 | | 4/16/2015 | | PASS |
Daryl Spivey
|
|
|
signed off in ePlanReview
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2015 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 4/16/2015 | | DONE |
|
|
|
All requirements met
|
Routing PW Sewer Rating | 3/18/2015 | | 4/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - MECHANICAL | 3/18/2015 | | 4/15/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 3/18/2015 | | 4/15/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 3/18/2015 | | 4/15/2015 | | PASS |
Evan Jenkins
|
|
|
L14B1 - 6684 Winston (Bldg 3): To construct a new 3,836 sq. ft., two story, Four unit, apartment building. Each unit has two bedrooms and two bathrooms. The 1st story units are 959 square feet and are required to be Type 'B' units. The 2nd story units are 959 square feet.
|
Routing - Design Review | 3/18/2015 | | 4/15/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Drainage | 3/2/2015 | | 4/15/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 3/2/2015 | | 4/15/2015 | | PASS |
|
|
|
|
Routing PW Solid Waste | 3/2/2015 | | 4/15/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLAN CHECK | 4/10/2015 | | 4/10/2015 | | PASS |
Sam Zahorka
|
|
|
|
Routing - Addressing | 4/1/2015 | | 4/1/2015 | | PASS |
Emily Dixon
|
|
|
|
Route to Impact Fee Review | 3/23/2015 | 3/26/2015 | 3/26/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 3/18/2015 | 3/18/2015 | 3/23/2015 | | PASS |
Scott Arellano
|
|
|
Conditional Approval. See attached comments specifically relating to the fire sprinkler riser room and required 1 hour rated construction.
|
1st review completed | | | 3/23/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/18/2015 | | 3/23/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Pending Assignment by JCM | 3/18/2015 | | 3/18/2015 | | DONE |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2015 | | 3/2/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 2/27/2015 | | 2/27/2015 | | FAIL |
Emily Dixon
|
|
|
No parcel numbers yet for Aberdeen Place Sub No 04.
|
Application received | | | 2/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2015 12:27PM
|
First Notice | | 8/20/2015 | | | |
|
|
|
|