Permanent Occupancy | | | 9/10/2015 | | DONE |
|
|
|
|
BLD-Final | 9/8/2015 | 9/9/2015 | 9/9/2015 | A | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
BLD-Final | 9/4/2015 | 9/4/2015 | 9/4/2015 | P | FAIL |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Provide code compliant handrail on stairs in corridor, rear exit/entry treads to noyt meet the minumum 13inch tread depth to use one handrail. A correction notice was posted.
|
FIRE-Final Inspection | 9/1/2015 | 9/1/2015 | 9/1/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Zoning Approval | 9/1/2015 | 9/1/2015 | 9/1/2015 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need knox box, address/suite #, and fire extinguishers.
|
BLD-Other | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PASS |
Mike Jordan
|
|
|
RC1 Channel // Pat Phone #: ###-####
|
BLD-Energy code compliance | 6/24/2015 | 6/25/2015 | 6/25/2015 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 6/23/2015 | 6/23/2015 | 6/23/2015 | P | PASS |
Jim Sly
|
|
|
Pat Phone #: ###-####
|
BLD-Wall Bracing | 6/8/2015 | 6/8/2015 | 6/8/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 5/15/2015 | 5/18/2015 | 5/18/2015 | P | NR |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 5/14/2015 | 5/15/2015 | 5/15/2015 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 5/13/2015 | 5/14/2015 | 5/14/2015 | P | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Footing | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Mike Jordan
|
|
|
john Phone #: ###-####
|
Inspection Record Card- Bld | | | 5/13/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/13/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/13/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 4/16/2015 | | |
|
|
|
|
Plan assigned to (SRZ) | 3/18/2015 | 3/18/2015 | 4/16/2015 | | PASS |
Sam Zahorka
|
|
|
Pending others to PASS
|
Routing - PLUMBING | 3/18/2015 | | 4/16/2015 | | PASS |
Sam Zahorka
|
|
|
signed off in ePlanReview
|
Routing - PLANNING | 3/18/2015 | | 4/16/2015 | | PASS |
Sam Zahorka
|
|
|
signed off in ePlanReview
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2015 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 4/16/2015 | | DONE |
|
|
|
All requirements met
|
Routing - PLANNING Land Div | 3/18/2015 | | 4/15/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 3/18/2015 | | 4/15/2015 | | PASS |
Evan Jenkins
|
|
|
L11B1 - 1472 Fry (Bldg 1): Aberdeen Building Type 1 (3 buildings) as part of a multifamily 4-Plex project consisting of 12 two-story buildings located at Raymond & Colehaven. Interior private streets are named N. Fry Lane and W. Winston Lane.
|
Routing - MECHANICAL | 3/18/2015 | | 4/15/2015 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/18/2015 | | 4/15/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Drainage | 3/2/2015 | | 4/15/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 3/2/2015 | | 4/15/2015 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 3/2/2015 | | 4/15/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLAN CHECK | 4/10/2015 | | 4/10/2015 | | PASS |
Sam Zahorka
|
|
|
|
Route to Impact Fee Review | 3/23/2015 | 3/26/2015 | 3/26/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 3/23/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/18/2015 | | 3/23/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2015 | | 3/2/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 2/27/2015 | | 2/27/2015 | | FAIL |
Emily Dixon
|
|
|
No parcel numbers yet for Aberdeen Place Sub No 04.
|
Application received | | | 2/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2015 12:40PM
|
First Notice | | 9/20/2015 | | | |
|
|
|
|