BLD-Final | 10/29/2015 | 10/29/2015 | 10/29/2015 | P | PASS |
Tony Young
|
|
|
call for garage key code plans on kitchen counter Phone #: ###-#### Inspection requested via web by David Wipper
|
DOC - Permit Finaled | 10/29/2015 | 10/29/2015 | 10/29/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 10/28/2015 | 10/29/2015 | 10/29/2015 | A | DEFR |
Tony Young
|
|
|
call for garage key code plans on kitchen counter Phone #: ###-#### Inspection requested via web by David Wipper// needs mech final
|
PubWorks Occupancy Approval | 10/28/2015 | 10/28/2015 | 10/28/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
FIRE-Final Inspection | 8/28/2015 | 8/31/2015 | 8/31/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
BLD-Energy code compliance | 5/8/2015 | 5/11/2015 | 5/11/2015 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Wall cover | 5/7/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Phil Shearer
|
|
|
Fire rated soffit inspection Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Energy code compliance | 5/7/2015 | 5/8/2015 | 5/8/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Framing/Rough-in | 5/6/2015 | 5/7/2015 | 5/7/2015 | A | PEND |
Tony Young
|
|
|
Phone #: 8507182 >> Inspection requested via mobile web by Dave Wipper,, framing ok,, work in progress on soffits,, ok so far,, still need full mechanical pass,, ok to insululate unaffected areas if needed
|
BLD-Framing/Rough-in | 5/5/2015 | 5/6/2015 | 5/6/2015 | P | PART |
Tony Young
|
|
|
Phone #: 8507182 >> Inspection requested via mobile web by Dave Wipper,, needs mech pass
|
BLD-Framing/Rough-in | 4/30/2015 | 5/5/2015 | 5/5/2015 | P | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by David Wipper Inspection cancelled via mobile web on Tuesday, May 05, 2015.
|
BLD-Wall Bracing | 4/21/2015 | 4/22/2015 | 4/22/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Foundation | 3/20/2015 | 3/23/2015 | 3/23/2015 | P | PASS |
Jim Sly
|
|
|
Shawn-would like insp at 2:00-i told contractor to call inspector Phone #: ###-####
|
BLD-Footing | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PASS |
Tony Young
|
|
|
Shawn-would like insp at 11:00-i told contractor to call inspector Phone #: ###-####
|
PubWorks Subgrade Approval | 3/19/2015 | 3/19/2015 | 3/19/2015 | | DONE |
Jason C. Taylor
|
|
|
*ALL MAIN LEVEL FOUNDATIONS**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 3/18/2015 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 3/17/2015 | | |
|
|
|
|
Routing - FIRE | 3/16/2015 | 3/16/2015 | 3/17/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to case.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (LEG) Tisha | 3/2/2015 | | 3/17/2015 | | DONE |
Tisha Gallop
|
|
|
3/9 fire, plan check
|
Routing - PLAN CHECK | 3/16/2015 | | 3/16/2015 | | PASS |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 3/13/2015 | | |
|
|
|
|
Meeting | | | 3/12/2015 | | DONE |
|
|
|
spoke with Evan Jenkins and Jason Taylor. Ok to early release ESC permit without grading permit so customer can start work. NO footing inspection until full building permit is issued.
|
1st review completed | | | 3/9/2015 | | FAIL |
|
|
|
fire, plan check
|
Routing - FIRE | 3/6/2015 | | 3/6/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed correction item to applicant. Attached report to case.
|
Routing - PLAN CHECK | 3/2/2015 | | 3/5/2015 | | FAIL |
Tisha Gallop
|
|
|
|
Plan assigned to (JG) | 3/2/2015 | 3/2/2015 | 3/4/2015 | | DEFR |
Javier Guzman
|
|
|
3/18 W L2 Hillside eplan**
|
Routing PW Grading-Hillside | 3/2/2015 | | 3/3/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 3/2/2015 | | 3/3/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 3/2/2015 | | 3/3/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED)
For the construction of a new 3346 sq. ft., two story (first story 2437 sq. ft., second story 909 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 198 sq. ft. of covered patio/porch and a 962 sq. ft. attached garage.
|
Routing - MECHANICAL | | | 3/2/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | | | 3/2/2015 | | PASS |
|
|
|
|
Routing - Addressing | 3/2/2015 | | 3/2/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 3/2/2015 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/2/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/2/2015 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2015 | | FAIL |
|
|
|
Missing the ResCheck
|
Application received | | | 2/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2015 1:18PM
|