BLD-Energy code compliance | 4/28/2015 | 4/29/2015 | 4/29/2015 | A | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
BLD-Framing/Rough-in | 4/27/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
BLD-Final | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | CANC |
Mike Jordan
|
|
|
Dan Phone #: ###-####. building conferance. ok to cover roof.
|
BLD-Wall Bracing | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | PASS |
Phil Shearer
|
|
|
Dan Phone #: ###-####
|
BLD-Footing | 4/3/2015 | 4/8/2015 | 4/8/2015 | A | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
OVERRIDE | | | 3/6/2015 | | |
|
|
|
|
Routing Walk-In (BLD) | 3/6/2015 | 3/6/2015 | 3/6/2015 | A | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 3/5/2015 | 3/5/2015 | 3/6/2015 | | PASS |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2015 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
requirements met
|
Telephone call | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
called Daniel to let know permit is ready, how much is owed
|
Issue PAID IN FULL permit | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Routing PW Flood Plain | 3/6/2015 | | 3/6/2015 | | CANC |
Jason C. Taylor
|
|
|
Not in floodway, not requirements or review needed. Jason Taylor ###-####.
|
Routing Walk-In (Zoning) | 3/5/2015 | 3/5/2015 | 3/5/2015 | P | DONE |
Leon Letson
|
|
|
|
Routing Walk-In (BLD) | 3/5/2015 | 3/5/2015 | 3/5/2015 | P | FAIL |
Perry Paine
|
|
|
NEED PUBLIC WORKS SIGNOFF
|
1st review completed | | | 3/5/2015 | | FAIL |
|
|
|
NEED PW FLOOD PLAIN APPROVAL
|
Application received | | 3/5/2015 | | | |
|
|
|
|