BLD-Final | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Jim Storey
|
|
|
Clint Phone #: ###-####
|
DOC - Permit Finaled | 7/16/2015 | 7/16/2015 | 7/16/2015 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | FAIL |
Jim Storey
|
|
|
Clint Phone #: ###-#### c/n irc12 secr311.3 landing reuired min 36 in direction of travel.
|
BLD-Energy code compliance | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | PASS |
Phil Shearer
|
|
|
Shear // Rudy Phone #: ###-####
|
BLD-Wall Bracing | 4/27/2015 | 4/27/2015 | 4/27/2015 | P | DEFR |
Jim Storey
|
|
|
Shear // Rudy Phone #: ###-#### out of time
|
BLD-Foundation | 3/31/2015 | 4/1/2015 | 4/1/2015 | P | PASS |
Phil Shearer
|
|
|
12:30 inspection request Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Footing | 3/31/2015 | 3/31/2015 | 3/31/2015 | P | PASS |
Phil Shearer
|
|
|
inspections request @ 1:00 pm Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Footing | 3/27/2015 | 3/30/2015 | 3/30/2015 | P | CANC |
Phil Shearer
|
|
|
request time 1:00 Phone #: ###-#### Inspection requested via web by tony L
|
OVERRIDE | | | 3/23/2015 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/23/2015 | | DONE |
|
|
|
|
Telephone call | | | 3/23/2015 | | DONE |
|
|
|
called Leonard- left message fees due and ready for pick up
|
Issue PAID IN FULL permit | | | 3/23/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/23/2015 | | DONE |
|
|
|
All Requirements Met (not checklist?)
|
Plan assigned to (JG) | | 3/9/2015 | 3/21/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 3/19 TH L1*
|
Routing - PLAN CHECK | 3/20/2015 | | 3/21/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
revisions approved ready to issue
|
Case Summary (BLD) | | | 3/21/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/20/2015 | | DONE |
|
|
|
received two copies of sheet 3.1- put on Javier's desk
|
1st review completed | | | 3/16/2015 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 4/13/2015 | | 3/16/2015 | | FAIL |
Javier Guzman
|
|
|
emailed review report to applicant
|
Routing - Addressing | 3/9/2015 | | 3/16/2015 | | PASS |
Jason C. Taylor
|
|
|
signed off in PW report by Jason Taylor 3/11/2015
|
Routing - MECHANICAL | | | 3/13/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/11/2015 | | 3/11/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 3/11/2015 | | 3/11/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/9/2015 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/9/2015 | | DONE |
Christina Prado
|
|
|
|
Application received | | 3/9/2015 | | | |
|
|
|
|