DOC - Permit Finaled | 6/3/2015 | 6/3/2015 | 6/3/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 6/3/2015 | 6/3/2015 | 6/3/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 5/28/2015 | 5/29/2015 | 6/1/2015 | A | CANC |
Phil Shearer
|
|
|
Mike Phone #: ###-####
|
BLD-Final | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | NR |
Phil Shearer
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 4/28/2015 | 4/29/2015 | 4/29/2015 | P | CANC |
Phil Shearer
|
|
|
Tom Phone #: ###-####
|
BLD-Energy code compliance | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PASS |
Phil Shearer
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 4/27/2015 | 4/27/2015 | 4/27/2015 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-#### FRAME AND ENERGY OK.
|
BLD-Wall Bracing | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | PASS |
Phil Shearer
|
|
|
Shear // Mike Phone #: ###-####
|
BLD-Wall Bracing | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | CANC |
Phil Shearer
|
|
|
Insulation // Mike Phone #: ###-####
|
BLD-Energy code compliance | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Phil Shearer
|
|
|
Insulation under slab edges // Mike Phone #: ###-####
|
BLD-Foundation | 4/6/2015 | 4/7/2015 | 4/7/2015 | A | PASS |
Phil Shearer
|
|
|
Late mornring - Mike Phone #: ###-####
|
OVERRIDE | | | 4/6/2015 | | |
|
|
|
|
BLD-Footing | 4/3/2015 | 4/6/2015 | 4/6/2015 | A | PASS |
Phil Shearer
|
|
|
|
Permit Ready to Issue | | | 4/6/2015 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/6/2015 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (Zoning) | 3/16/2015 | 3/16/2015 | 3/16/2015 | A | PASS |
Josh Wilson
|
|
|
Addition to front of house eliminated. Enclosed porch will be removed and rebuilt to edge of concrete dreiveway. Ok per revised plans. JGW 3-16-15
|
Routing Walk-In (BLD) | 3/16/2015 | 3/16/2015 | 3/16/2015 | A | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 3/16/2015 | 3/16/2015 | 3/16/2015 | | PASS |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 3/16/2015 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2015 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 3/12/2015 | 3/12/2015 | 3/12/2015 | P | FAIL |
Perry Paine
|
|
|
substandard lot fail in zoning
|
Routing Walk-In (Zoning) | 3/10/2015 | 3/10/2015 | 3/12/2015 | A | DONE |
Perry Paine
|
|
|
The addition needs substandard review. Applicant called 3/10/15. Will apply for the review. SC
|
1st review completed | | | 3/12/2015 | | FAIL |
Perry Paine
|
|
|
|
Application received | | 3/10/2015 | | | |
|
|
|
substandard lot
|