Second Notice | | 2/21/2016 | 2/22/2016 | | DONE |
|
|
|
This permit finaled on the web by Mike Snodgrass
|
First Notice | | 2/21/2016 | 2/11/2016 | | DONE |
|
|
|
sent in mail 2-12-16
|
PubWorks Occupancy Approval | 1/21/2016 | 1/21/2016 | 1/21/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 1/21/2016 | | DONE |
|
|
|
|
BLD-Final | 12/30/2015 | 12/31/2015 | 12/31/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once public works signs perm.
|
Temporary Occupancy | 12/31/2015 | 3/30/2016 | 12/31/2015 | | DONE |
Carlos Velazquez
|
|
|
|
BLD-Final | 12/30/2015 | 12/30/2015 | 12/30/2015 | P | NR |
Dave Hannah
|
|
|
Brent Phone #: ###-#### walked project with con
|
Zoning Approval | 12/30/2015 | 12/30/2015 | 12/30/2015 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 12/23/2015 | 12/24/2015 | 12/24/2015 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, Smoke alarms appear to be stand alone, no fire alarm panel/FIR permits. Life fire safety inspection passed/complete
|
PubWorks Temp Occupancy Appr | 12/18/2015 | 12/18/2015 | 12/18/2015 | | DONE |
Tiffany Lowery
|
|
|
Temp Occupancy only. Street Lights still required.
|
BLD-Ceiling Grid Inspection | 12/16/2015 | 12/17/2015 | 12/17/2015 | P | PASS |
Jim Sly
|
|
|
Brent Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. East offices only ok.
|
BLD-Conference | 12/7/2015 | 12/8/2015 | 12/8/2015 | A | NR |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Remove pop rivets from grid.
|
BLD-Other | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Mike Jordan
|
|
|
Fire wall // Brent Phone #: ###-####
|
BLD-Conference | 11/23/2015 | 11/24/2015 | 11/24/2015 | A | DONE |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Wwent over rated penetrations requirements on 1hr. wall.
|
BLD-Wall cover | 11/20/2015 | 11/20/2015 | 11/20/2015 | P | DONE |
Jim Sly
|
|
|
dry wall // Brent Phone #: ###-#### Drywall attachment 1 hr wall at Electrical room ....OK.
|
BLD-Energy code compliance | 11/12/2015 | 11/13/2015 | 11/13/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####
|
BLD-Framing/Rough-in | 11/9/2015 | 11/10/2015 | 11/10/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. INterior steel stud framed walls ok and hard lids.
|
BLD-Framing/Rough-in | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Interior steel stud fur out framed wall in electrical room ok.
|
Plan assigned to (CDM) | 9/29/2015 | 9/29/2015 | 10/12/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/12/2015 | | DONE |
|
|
|
as per Carl Madsen; NO plan mod fee due
|
BLD-Energy code compliance | 10/7/2015 | 10/7/2015 | 10/8/2015 | P | PASS |
Mike Jordan
|
|
|
Insulation // Brent Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 10/7/2015 | | DONE |
|
|
|
all plan mod fees paid
|
OVERRIDE | | | 10/6/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 10/6/2015 | | DONE |
|
|
|
please do not re issue
|
Routing PW Sewer Rating | 9/30/2015 | | 10/6/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Environmental | 9/30/2015 | | 10/6/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLAN CHECK | 10/4/2015 | | 10/4/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLUMBING | 10/1/2015 | | 10/1/2015 | | PASS |
Bill VanDegrift
|
|
|
resubmittals for the mat wash area nad the relocation of the sanitary sewer connection.
|
Plan Modification Accepted | | | 9/29/2015 | | DONE |
Christina Prado
|
|
|
Plan modification requested by Josh Howa to make revisions to Plumbing, Sewer and grading plans, please send to Bill V, Rick Christensen for additional review
|
BLD-Framing/Rough-in | 9/24/2015 | 9/25/2015 | 9/25/2015 | A | PART |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Steel decking and joist welding at office area. Noted areas to be repaired. These areas also noted on special inspection report. Ok to insulate after special inspection has passed. Joist to imbed connections ok to insulate.
|
BLD-Foundation | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | PART |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Pend. special inspection.
|
BLD-Footing | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Column pad footings for pay canopy. Footings for trash enclosure ok.
|
BLD-Other | 8/26/2015 | 8/27/2015 | 8/27/2015 | P | PASS |
Mike Jordan
|
|
|
slab // Brent Phone #: ###-####. Topping slab over hollow panels for roof ok.
|
BLD-Foundation | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Mike Jordan
|
|
|
Wall // Brent Phone #: ###-####
|
BLD-Footing | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | PART |
Mike Jordan
|
|
|
Brent Phone #: ###-####. nterior footings and silicon trash pits. Work in progress. Special inspector on site.
|
BLD-Footing | 7/27/2015 | 7/28/2015 | 7/28/2015 | P | DEFR |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Pending special inspection.
|
BLD-Foundation | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Concrete stemwall for conveyor trench.
|
BLD-Foundation | 7/16/2015 | 7/17/2015 | 7/17/2015 | P | PART |
Jim Sly
|
|
|
Brent-rebar Phone #: ###-#### Concrete Tilt Up walls .....#s 11 thru 13 16 thru 20 and 33 thru 37 OK pending Terricon Special inspection, tests and approvals.
|
BLD-Foundation | 7/15/2015 | 7/16/2015 | 7/16/2015 | P | PASS |
Mike Jordan
|
|
|
Rebar // Brent Phone #: ###-####. Concrete tilt panels ok.
|
BLD-Foundation | 7/13/2015 | 7/14/2015 | 7/14/2015 | P | PASS |
Mike Jordan
|
|
|
Rebar; Brent Phone #: ###-####. All previous ftilt panels that failed have been repaired. ok for concrete.
|
BLD-Foundation | 7/13/2015 | 7/13/2015 | 7/13/2015 | P | FAIL |
Mike Jordan
|
|
|
Brent-wall (tilt up) Phone #: ###-####. Concrete tilt panels, panels inspected noted missing perimeter rebar, incorrect grid spacing of rebar and incorrect lap lengths.
|
BLD-Concrete | 7/7/2015 | 7/9/2015 | 7/9/2015 | P | PART |
Mike Jordan
|
|
|
3 - 4 pm please for Tilt up walls - Brent Phone #: ###-####. Work in progress on concrete tilt panels. Special inspector on site.
|
BLD-Footing | 7/6/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. North perimeter footing ok.
|
OVERRIDE | | | 6/22/2015 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/22/2015 | | DONE |
Christina Prado
|
|
|
Plan mod fees paid- permit changed back to ISS
|
Routing - PLAN CHECK | 6/17/2015 | | 6/22/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 6/17/2015 | | 6/22/2015 | | PASS |
Carl D Madsen
|
|
|
|
Permit Ready to Issue | | | 6/22/2015 | | DONE |
|
|
|
DO NOT RE-ISSUE--- PLAN MOD/// FEES DUE
|
Routing - PLANNING | 6/17/2015 | | 6/18/2015 | | PASS |
Andrea Tuning
|
|
|
|
Issue PAID IN FULL permit | | | 6/11/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/11/2015 | | DONE |
|
|
|
|
Telephone call | | | 6/10/2015 | | DONE |
|
|
|
talked to Valorie and Casey at ACHD-the customer has paid the 200.00 plan review fee but will still owe impact fees. Once the plan review is complete the engineer will assess the impact fees. As per Rita if they pay us the ACHD fees - create a ACHD permit-if the customer is going to pay ACHD then we don't need to create a ACHD permit but we will need the rec or inv from ACHD and at this point please make sure the paper from ACHD says yeah or neay for the inspections....thank you
|
Telephone call | | | 6/9/2015 | | DONE |
|
|
|
called and talked to Mike to let him know there were still fees due. They paid the bldg fees but not others. I also told him he needs to bring us the ACHD invoice or receipt showing the fees were paid and if inspections are needed-BOI15-0006
|
OVERRIDE | | | 6/5/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 6/4/2015 | | 6/5/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/5/2015 | | DONE |
|
|
|
Needs Responsible Person, G.C. form, ACHD & Revised Cert.-received GC form and rev cert of val and RP but need ACHD (can) 6-11-15 (CEV) ACHD approval received
|
Plan assigned to (CDM) | 3/25/2015 | | 6/5/2015 | | PASS |
Carl D Madsen
|
|
|
New building due 4/25
First review completed 4-23
|
Routing - PLANNING Land Div | 6/4/2015 | | 6/4/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 6/4/2015 | | 6/4/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - FIRE | 5/20/2015 | 5/20/2015 | 5/29/2015 | | PASS |
Katie Marron
|
|
|
Attached comments to plans.
|
Routing - PLAN CHECK | 5/7/2015 | | 5/20/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 5/7/2015 | | 5/8/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Check with plumbing deptartment on the use of a reducer. No work being performed in the public R/W. -KR
|
Routing PW Street Lights | 5/7/2015 | | 5/7/2015 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Drainage | 5/7/2015 | | 5/7/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 5/7/2015 | | 5/7/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 5/7/2015 | | 5/7/2015 | | FAIL |
Emily Dixon
|
|
|
We still have not received the new parcel numbers from Ada County.
|
Routing - PLANNING | 5/7/2015 | | 5/7/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING Land Div | 5/7/2015 | | 5/7/2015 | | FAIL |
Dave Abo
|
|
|
Active Record of Survey (ROS15-00034). Not completed. Must finish and provide documents as required in approval prior to issuance of building permit.
|
Routing - MECHANICAL | 5/7/2015 | | 5/7/2015 | | PASS |
Troy James
|
|
|
Owner provided letter stating the office hours are less than 20 hours per week. Low operating hours exempts the requirements for economizer.
|
Routing PW Sewer Rating | 5/7/2015 | | 5/7/2015 | | PASS |
Jennifer Bruner
|
|
|
done by Bev Mountain 4-3-2015 jkb
|
Route to Impact Fee Review | 4/24/2015 | 4/27/2015 | 4/29/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 4/24/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/25/2015 | | 4/23/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/25/2015 | | 4/23/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 3/25/2015 | | 4/23/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
How is the remainder of the property going to be served? Public works is currently performing a sewer service study for an area west of Cloverdale/south of Fairview that includes this parcel. Other properties in the service area are pursuing development as well, it maybe feasible to find a gravity sewer solution for this property. Please contact Kyle Rosenmeyer in Boise Public Works at ###-#### to discuss.
|
Routing - FIRE | 3/25/2015 | | 4/1/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed plan review report to architect. Attached report to case.
|
Routing - PLANNING Land Div | 3/25/2015 | | 3/30/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Sewer Rating | 3/25/2015 | | 3/27/2015 | | FAIL |
Jennifer Bruner
|
|
|
Final approved parcels/lots are needed before the sewer permit can be created.
|
Routing - Addressing | 3/27/2015 | | 3/27/2015 | | FAIL |
Emily Dixon
|
|
|
Parcels need to be consolidated.
|
Routing PW Street Lights | 3/25/2015 | | 3/26/2015 | | FAIL |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 3/25/2015 | | 3/26/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing PW Environmental | 3/25/2015 | | 3/26/2015 | | PASS |
Terry Alber
|
|
|
Water reclaim and pretreatment equipment appears adequate. Oil/Sand Interceptor MUST have submerged inlet on both chambers.
|
Routing - Erosion and Sediment | 3/25/2015 | | 3/26/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE)
The ESC Plan meets the City of Boise's BCC8-17 ESC Requirements, but not the Federal EPA SWPPP Requirements. I call Scott Stanfield (454.0256) and disclosed this to him via phone on 3-26-15 at 10:15am.
Construct one new vehicle wash building, canopy structures and site improvements. 2 Acres of Disturbance
|
Routing - MECHANICAL | 3/25/2015 | | 3/26/2015 | | FAIL |
Troy James
|
|
|
|
Routing - Design Review | 3/25/2015 | | 3/26/2015 | | FAIL |
Andrea Tuning
|
|
|
All pole lighting shall be located outside of the planter islands.
|
Intake Approval | | | 3/25/2015 | | PASS |
John Menard
|
|
|
|
Routing - PLUMBING | 3/25/2015 | | 3/25/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 3/25/2015 | | 3/25/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 3/12/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 12 2015 11:33PM
|
Routing PW Drainage | 3/25/2015 | | | | FAIL |
Brian Murphy
|
|
|
BED ON PLAN 6 FEET CALCS 4 FEET
|
Pending Assignment by JCM | 3/25/2015 | | | | |
John Menard
|
|
|
|