BLD-Final | 12/16/2015 | 12/16/2015 | 12/16/2015 | P | PASS |
Jim Storey
|
|
|
nate Phone #: ###-####
|
DOC - Permit Finaled | 12/16/2015 | 12/16/2015 | 12/16/2015 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Mike Jordan
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | CANC |
Mike Jordan
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | PASS |
Phil Shearer
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 9/17/2015 | 9/17/2015 | 9/17/2015 | P | NR |
Phil Shearer
|
|
|
Nate Phone #: ###-####
|
BLD-Wall Bracing | 9/8/2015 | 9/8/2015 | 9/8/2015 | P | PASS |
Phil Shearer
|
|
|
Shear // Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 9/8/2015 | 9/8/2015 | 9/8/2015 | P | NR |
Phil Shearer
|
|
|
Nate Phone #: ###-####
|
BLD-Wall Bracing | 9/3/2015 | 9/3/2015 | 9/3/2015 | P | FAIL |
Phil Shearer
|
|
|
Nate Phone #: ###-####. Front portal frame nailing.
|
BLD-Foundation | 5/28/2015 | 5/28/2015 | 5/28/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 5/27/2015 | 5/27/2015 | 5/27/2015 | P | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Telephone call | | | 4/7/2015 | | DONE |
|
|
|
Call to Nathan (12 permits)
|
Issue PAID IN FULL permit | | | 4/7/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 4/6/2015 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/6/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/6/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (LEG) Tisha | 3/16/2015 | | 4/6/2015 | | DONE |
Tisha Gallop
|
|
|
3/27 planning
|
Routing - PLANNING | 3/27/2015 | | 4/6/2015 | | PASS |
Sue Cummings
|
|
|
needs design changes. Done!
|
Plan resubmittals received | | | 3/27/2015 | | DONE |
|
|
|
Two copies of sheet A0.0 and two copies of site plan 8x11
|
Routing - PLAN CHECK | 3/27/2015 | | 3/27/2015 | | PASS |
Tisha Gallop
|
|
|
|
1st review completed | | | 3/26/2015 | | FAIL |
Tisha Gallop
|
|
|
pending approval from planning and building review
|
Routing - PLAN CHECK | 3/25/2015 | | 3/26/2015 | | FAIL |
Tisha Gallop
|
|
|
missing page of plan
|
Plan assigned to (JG) | 3/16/2015 | 3/16/2015 | 3/25/2015 | | DEFR |
Javier Guzman
|
|
|
3/26 TH L1**
|
Routing - MECHANICAL | 3/24/2015 | | 3/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/17/2015 | | 3/24/2015 | | FAIL |
Sue Cummings
|
|
|
Need no build release
|
Routing - Addressing | 3/16/2015 | | 3/17/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2015 | | 3/17/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/16/2015 | | DONE |
|
|
|
|
Intake Approval | | | 3/16/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/16/2015 | | DONE |
|
|
|
|
Application received | | 3/16/2015 | | | |
|
|
|
|
Application received | | 3/16/2015 | | | |
|
|
|
|