Print Statement | | | 11/18/2015 | | DONE |
|
|
|
|
First Notice | | 10/15/2015 | 11/9/2015 | | DONE |
Candy A. Nichols
|
|
|
sent in mailed
|
Permanent Occupancy | | | 10/5/2015 | | DONE |
|
|
|
|
BLD-Final | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton OK for Perm Occ.
|
BLD-Final | 8/18/2015 | 8/19/2015 | 8/19/2015 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Needs plumbing final.
|
FIRE-Final Inspection | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PART |
Mike Jordan
|
|
|
Later morning if possible. Phone #: ###-#### Inspection requested via web by Darius Saxton. Majority of the work has been completed. Needs to final out the project related fire sprinkler permit and needs fire/life/safety final.
|
FIRE-Final Inspection | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PART |
Jim Page
|
|
|
Life fire safety inspection passed/complete for room 2. Checked the FIR permit for the sprinklers, it was not finaled at time of inspection, was informed by onsite point of contact, Darius phone ###-#### that the contractor is working to get some as builds provided for fire sprinkler work, cannot final life fire and safety until sprinkler FIR is finaled.
|
BLD-Ceiling Grid Inspection | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Final | 6/12/2015 | 6/12/2015 | 6/12/2015 | P | PART |
Mike Jordan
|
|
|
Bi-Plane Phase 1 Phone #: ###-#### Inspection requested via web by Darius Saxton. phase ok. counter top height needs to be lowered to 34 inches in rm #101.
|
FIRE-Final Inspection | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in rooms 6, 101 and 102
|
BLD-Ceiling Grid Inspection | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok pend. mech.
|
BLD-Framing/Rough-in | 5/13/2015 | 5/14/2015 | 5/14/2015 | A | PASS |
Mike Jordan
|
|
|
Radiology room 6 rough-in. Phone #: ###-#### Inspection requested via web by Darius Saxton. All previous issues have been resolved. ok for cover.
|
BLD-Framing/Rough-in | 5/4/2015 | 5/5/2015 | 5/5/2015 | A | PART |
Mike Jordan
|
|
|
This project is in phases. This would be for small office/ break room for phase 1. Darius Saxton Phone #: ###-#### Inspection requested via web by Brad Turk. Interior steel stud framed walls for phase 1 work. Noted that an interior 5" x 5" tube steel coulmn has been found that was not noted on plans, architect to provide a listed assembly for colomn. Aslo noted at radiology room remodel that interior portion of existing corridor is not maintained. Addtional 5/8" type rock will need o be installed.
|
Issue PAID IN FULL permit | | | 4/24/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/19/2015 | 3/19/2015 | 4/15/2015 | | PASS |
Carl Westfall
|
|
|
ST. AL'S RADIOLOGH BI-PLANE REMODEL - Level 3 TI - Paper - (15 days - April 7)
|
1st review completed | | | 4/15/2015 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/15/2015 | | 4/15/2015 | | DONE |
Carl Westfall
|
|
|
Worked 6 hours on a Saturday to get the plan review done. In Fire for part of 3 days. Missed the 1st review time by 1 day.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/15/2015 | | DONE |
|
|
|
Need a GC and Revised Cert of Value // All requirements met 4-17-15 (KRS)
|
Print Occupancy Form | | | 4/15/2015 | | DONE |
|
|
|
|
Telephone call | | | 4/15/2015 | | DONE |
|
|
|
called Jeff- told him permit is ready for pick up and fees due
|
Routing - FIRE | 4/13/2015 | | 4/15/2015 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. No separate comments attached to plans. Fire extinguisher locatins to be field verified. Separate permits will be required for the necessary fire sprinkler and alarm modifications.
|
Routing - PLAN CHECK | 3/27/2015 | | 4/11/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Routing - PLUMBING | 3/27/2015 | | 3/27/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 3/23/2015 | | 3/27/2015 | | PASS |
Troy James
|
|
|
|
Routing PW Sewer Rating | 3/20/2015 | | 3/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 3/20/2015 | | 3/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 3/19/2015 | | 3/19/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Pending Assignment by JCB | 3/18/2015 | | 3/19/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 3/18/2015 | | PASS |
|
|
|
Plan intake approved
|
Plans ACCEPTED BY PLAN TECH | | | 3/18/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/18/2015 | | DONE |
|
|
|
|
Application received | | 3/18/2015 | | | |
|
|
|
|