Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD15-00876
StatusIssued
Name PROBST ELECTRIC
Site Address 11777 W EXECUTIVE DR
Project NameProbst Electric
Customer Number 
ePlanReviewNo
Description
**(PROBST ELECTRIC)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for an existing 12,000 square foot mercantile / office / warehouse building. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT; except that work redlined on the approved floor plan. This building was built in Ada County prior to annexation on Dec. 29th, 2000. This building was previously occupied by Happy Trail Products BLD11-00056. There are no changes to occupancy or use under this permit. **AJS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Conference4/2/20154/3/20154/3/2015ADONE
DetailsForrest France
On site conference with tenant regarding conditions necessary for an occupancy approval. Noted items include; need to verify fire alarm panel is monitored and trouble condition is cleared, post missing fire extinguishers throughout and at each level as discussed, missing knox box, building address numbers are not satisfactory, repair non-functional door leaf at the main entry/exit.
Plan assigned to (AJS)3/25/20153/25/20154/2/2015 PASS
DetailsAdele J Schaffeld-Griffin
My review completed Probst Electrical
PLANS/APPL TAKEN TO FRONT DESK  4/2/2015 DONE
Permit Ready to Issue  4/2/2015 DONE
Print Occupancy Form  4/2/2015 DONE
Telephone call  4/2/2015 DONE
called Ila to let know permit is ready
Issue PAID IN FULL permit  4/2/2015 DONE
Routing - FIRE3/30/20153/30/20154/1/2015 PASS
DetailsScott Arellano
Not plan reviewed. No current information. Final approval will be subject to satisfactory field inspection of all building basic life safety components and fire protection systems.
1st review completed  4/1/2015  
1st review completed  4/1/2015 PASS
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  3/30/2015 DONE
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK3/27/2015 3/30/2015 PASS
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental3/26/2015 3/27/2015 PASS
DetailsTerry Alber
No Issues.
Routing - PUBLIC WORKS3/26/2015 3/27/2015 PASS
DetailsJennifer Bruner
Routing - Addressing3/25/2015 3/26/2015 PASS
DetailsJason C. Taylor
Plans ACCEPTED BY PLAN TECH  3/25/2015 DONE
Intake Approval  3/25/2015 PASS
Recd Pcfee & Taken To Pln CK  3/25/2015 DONE
Application received 3/25/2015