Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD15-00890
StatusFinaled
Name PETRA INC
Site Address 1017 N ORCHARD ST
Project NameU-Haul Climate Control Storage
Customer NumberBLD15-02127 DEMO
ePlanReviewYes
Description
(U-HAUL CLIMATE CONTROL STORAGE BUILDING) Permit to construct a new 37,616 square foot two story climate controlled storage building and related site improvements. The building is fully fire sprinklered for S-1 Fire area provisions. Approval contingent upon adhering to the approved plans on file, Planning Approvals and engineering. Work to include: construction of new foundation, new accessible parking, new accessible route, [construction of a tilt up concrete first floor, steel pan deck, and metal building second floor and roof structure], new electrical, new mechanical, new plumbing, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building will be fully Fire Sprinklered with an approved Fire Alarm system per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/25/201612/14/2016 DONE
Mailed 12-16
First Notice 11/13/201611/15/2016 DONE
Mailed 11-16-16
PubWorks Occupancy Approval11/3/201611/3/201611/3/2016 DONE
DetailsTiffany Lowery
Permanent Occupancy  11/3/2016 DONE
Print Occupancy Form  11/3/2016 DONE
BLD-Final10/31/201610/31/201611/2/2016PPASS
DetailsJim Sly
Jake Phone #: ###-####
OK for Perm Occ. (sorry....he didn't have card)
FIRE-Final Inspection11/2/201611/3/201611/2/2016APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection11/2/201611/2/201611/2/2016PFAIL
DetailsTroy Cobbley
Still need the emergency light on the second floor northwest corner repaired. All other items have been corrected.
FIRE-Final Inspection10/31/201611/1/201611/1/2016AFAIL
DetailsTroy Cobbley
Provide correct building address for the fire alarm monitoring, repair three emergency lights, install the missing exit sign, provide fire dept access signage. Per contractor the shown gate/fencing will not be installed.
Zoning Approval10/27/201610/27/201610/27/2016 PASS
DetailsSarah Schafer
BLD-Ceiling Grid Inspection9/15/20169/15/20169/15/2016PPASS
DetailsJim Sly
Keagan Phone #: ###-####
FIRE-Conference9/15/20169/15/20169/15/2016ADONE
DetailsKatie Marron
Phone call with Jake on where Knox box should be installed (entrance or riser room). Advised it should be installed by where the fire alarm panel will be which is he said is the main entrance.
BLD-Framing/Rough-in8/31/20169/1/20169/2/2016PPASS
DetailsJim Sly
Jake Phone #: ###-####
FIRE-Conference9/2/20169/2/20169/2/2016PDONE
DetailsTroy Cobbley
Jake Phone #: ###-####
BLD-Energy code compliance8/18/20168/18/20168/19/2016PPART
DetailsJim Sly
Jake Phone #: ###-####
West wall 2nd floor OK.
BLD-Energy code compliance8/10/20168/11/20168/11/2016APART
DetailsJim Sly
Insulation // Jake Phone #: ###-####
South Wall 2nd floor...OK.
BLD-Energy code compliance8/3/20168/3/20168/3/2016PPART
DetailsJim Sly
Jake Phone #: ###-####
Select walls ....OK
BLD-Energy code compliance8/1/20168/1/20168/1/2016PPART
DetailsJim Sly
Jake Phone #: ###-####
West wall 1st floor.......OK
BLD-Energy code compliance6/30/20167/1/20167/1/2016ANR
DetailsJim Sly
Please call ahead for access - Jake Phone #: ###-####
BLD-Other6/17/20166/20/20166/20/2016PPART
DetailsJim Storey
Jake-steel deck-concrete Phone #: ###-####wip
BLD-Conference5/10/20165/10/20165/10/2016PDONE
DetailsJim Sly
Jake Phone #: ###-####
BLD-Footing3/22/20163/23/20163/23/2016APART
DetailsJim Sly
Late morning // Jake Phone #: ###-####
Special insp Required .......Footing pads at East and West walls of Bldg.......and just S. of Elevator. Elevator footing. OK pending MTI special inspections, tests and approvals.
Issue PAID IN FULL permit  3/18/2016 DONE
OVERRIDE  3/11/2016  
Routing - PLAN CHECK2/25/2016 3/11/2016 PASS
DetailsTim L. Woodard
Routing Off Site - STRUCTURAL2/25/2016 3/11/2016 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  3/11/2016 DONE
Permit Ready to Issue  3/11/2016 DONE
**ALL MET*** Need GC Form & Revised Certificate of value from GC
Plan assigned to (TLW)4/27/2015 3/11/2016 PASS
DetailsTim L. Woodard
1st Review Complete
Routing - FIRE2/29/20162/29/20163/2/2016 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - PLANNING Land Div2/25/2016 3/1/2016 PASS
DetailsTodd Tucker
Routing - Addressing2/25/2016 2/26/2016 PASS
DetailsLaura Hunter
Plan resubmittals received  2/25/2016 DONE
Extend Review Timeline  1/7/2016 DONE
DetailsJason Blais
Plan Reviewer's activity  12/18/2015 DONE
Sent email about pending expiration if no engagement is recieved. TLW
Routing PW Drainage9/16/2015 12/18/2015 PASS
DetailsBrian Murphy
Passed in E-Plan. TLW
Routing - Addressing10/16/2015 10/16/2015 PASS
DetailsEmily Dixon
Address shall be 1017 N Orchard St
Routing - PLANNING Land Div10/15/2015 10/15/2015 PASS
DetailsDave Abo
Parcel A on ROS #10270.
Routing - PLANNING10/8/2015 10/8/2015 PASS
DetailsSusan Riggs
Routing - PLAN CHECK9/16/2015 10/1/2015 FAIL
DetailsTim L. Woodard
Routing - FIRE9/16/20159/16/20159/25/2015 FAIL
DetailsScott Arellano
Revised comments attached to case and emailed to architect.
Routing Off Site - STRUCTURAL9/16/2015 9/25/2015 FAIL
DetailsTim L. Woodard
Routing PW Street Lights9/16/2015 9/25/2015 PASS
DetailsRob Bousfield
Routing - Design Review9/16/2015 9/23/2015 PASS
DetailsAndrea Tuning
Passed on 9-23-16 in E-Plan with Bicycle parking revisions. TLW
Routing - Addressing9/16/2015 9/17/2015 FAIL
Parcel consolidation necessary. Also building will need unique address.
Routing - PLUMBING9/16/2015 9/17/2015 PASS
DetailsDaryl Spivey
dcva required on water service upstream of any branch or fixture
Routing - PLANNING Land Div9/16/2015 9/16/2015 FAIL
DetailsDave Abo
Must complete Record of Survey (ROS15-00052) Mylar has been signed and Notice of Buildable Parcel but no documentation that documents have been recorded. Provide copies of recorded documents prior to issuance of building permit. 9-16-15
Routing - PLANNING9/16/2015 9/16/2015 FAIL
DetailsSusan Riggs
Waiting for the Noitice of Buildable Parcels and the mylar recorded. They have been approved, just not recorded.
Routing - Erosion and Sediment9/16/2015 9/16/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

(U-HAUL CLIMATE CONTROL STORAGE BUILDING) Permit to construct a new 37,616 square foot two story climate controlled storage building and related site improvements.
Plan resubmittals received  9/16/2015 DONE
Routing - PLANNING Land Div9/15/2015 9/15/2015 FAIL
DetailsDave Abo
Must combine parcels before issuance of building permit.
Routing PW Drainage9/15/2015 9/15/2015 FAIL
Routing - PLUMBING9/15/2015 9/15/2015 FAIL
DetailsBill VanDegrift
Christina said to fail this in E-Plan because the system failed
Routing - Erosion and Sediment6/23/2015 6/23/2015 PASS
DetailsEvan Jenkins
Permit was issued prior to ESC Reviewing/Approving the ESC Plan and Site Maps. Evan Reviewed them onsite during the Site Prep Inspection.
(U-HAUL CLIMATE CONTROL STORAGE BUILDING) Permit to construct a new 37,616 square foot two story climate controlled storage building and related site improvements. Approval contingent upon adhering to the approved plans on file, Planning Approvals and engineering. Work to include: construction of new foundation, new accessible parking, new accessible route, [construction of a tilt up concrete first floor, steel pan deck, and metal building second floor and roof structure], new electrical, new mechanical, new plumbing, and interior finishes
Route to Impact Fee Review5/18/20155/21/20155/19/2015 PASS
DetailsCindy M. Gould
Routing PW Solid Waste4/28/2015 5/18/2015 PASS
DetailsMegan Durrell
Approved in E-Plan Review. TLW
1st review completed  5/18/2015 DONE
Routing - PLANNING4/27/2015 5/18/2015 FAIL
DetailsSusan Riggs
Failed in E-Plan Reviewl. CUP14-00065
Routing - PLANNING Land Div4/27/2015 5/18/2015 FAIL
DetailsTim L. Woodard
Failed in E-Plan. TLW
Routing PW Drainage4/28/2015 5/18/2015 FAIL
DetailsBrian Murphy
c-33 sand pavers o and m isc

Failed in E-Plan Review. TLW
Routing PW Street Lights4/28/2015 5/18/2015 FAIL
DetailsMike D Hedge
Failed in E-Plan Review. TLW
Routing - PLAN CHECK4/27/2015 5/14/2015 FAIL
DetailsTim L. Woodard
Refer to change marks attached to drawings. TLW
Routing Off Site - STRUCTURAL4/27/2015 5/14/2015 FAIL
DetailsTim L. Woodard
Corrections attached in E-Plan Review. TLW
Routing - FIRE4/27/20154/27/20155/11/2015 FAIL
DetailsScott Arellano
Emailed report to architect and attached report to case.
Routing PW Sewer Design4/28/2015 5/1/2015 PASS
DetailsKyle S. Rosenmeyer
Routing - Design Review4/27/2015 4/30/2015 FAIL
DetailsSarah Schafer
The site plan, landscape plan and elevation do not match what was approved as parrt of DRH14-00379. The site plan does nto show all improvements including biycle parking and the site and landsacpe plans do not match.
Routing - PLUMBING4/27/2015 4/29/2015 FAIL
DetailsBill VanDegrift
1) provide civil plans showing sewer and water size and locations
2) provide a dcva on water service upstream of any branch lines
Routing PW Sewer Rating4/28/2015 4/28/2015 PASS
DetailsConnie Baumgartner
Routing - Addressing4/27/2015 4/28/2015 FAIL
Parcel consolidation necessary. Also building will need new unique address.
Routing - PUBLIC WORKS4/27/2015 4/28/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment4/27/2015 4/28/2015 FAIL
DetailsEvan Jenkins
ESC Site Map Required For Approval.
Intake Approval  4/23/2015 PASS
DetailsSam Zahorka
Intake Approval  4/1/2015 FAIL
DetailsSam Zahorka
Plan Reviewer's activity  4/1/2015 DONE
DetailsSam Zahorka
Please provide the following information:

1. Please see the items circled in red on the submittal checklist.

2. Please see the File naming Standards and rename sheets. http://pds.cityofboise.org/media/105041/electronicstandards.pdf

3. Please have the engineer provide his stamp and signature on Application #310 - Statement for Special Inspections.

4. Please separate all of the drawings sheets and upload them idividually rather than together.

5. Please provide a 4"X4" blank space located 3" off the lower right hand corner for the City approval stamp on the Cover Sheet.

6. Please provide a 4"X2" blank space located 3" off the lower right hand corner for the City approval stamp on the drawing Sheets.

7. Please provide the structual calculations.

8. Please provide the Verification of legal lot form signed by Subdivision staff. (###-#### or ###-####)
Please separate this form from the checklist and upload as its own document.

9. Please provide the ESC Narrative

10. Planning & Zoning Letter(s) of approval. (DRH)

11. Please provide a 2012 IECC Energy Code enevelope COMcheck.

12. Please provide the Landscape plan and plan schedules

13. Please provide a 2012 Mechancial COMcheck.

If assistance is needed please call me directly at ###-####
Application received  3/25/2015 DONE
Application submitted via PDS Online on Mar 25 2015 5:04PM