Third Notice | | 2/16/2016 | 3/10/2016 | | DONE |
|
|
|
|
Third Notice | | 1/19/2016 | 2/11/2016 | | DONE |
|
|
|
|
Second Notice | | 11/19/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
First Notice | 10/9/2015 | 10/9/2015 | 11/9/2015 | | DONE |
Dave Hannah
|
|
|
mailed 11-10-15
|
BLD-Final | 10/9/2015 | 10/9/2015 | 10/9/2015 | P | PASS |
Dave Hannah
|
|
|
Tony Phone #: ###-####
|
DOC - Permit Finaled | 10/9/2015 | 10/9/2015 | 10/9/2015 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Foundation | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PASS |
Mike Jordan
|
|
|
Tony-rebar Phone #: ###-####
|
BLD-Foundation | 6/1/2015 | 6/2/2015 | 6/2/2015 | A | PASS |
Mike Jordan
|
|
|
Spoke with you about 11/1130 Rebar // KC Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/1/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 4/27/2015 | | |
|
|
|
|
Plan assigned to (CDM) | | 3/27/2015 | 4/27/2015 | | PASS |
Carl D Madsen
|
|
|
New cell tower Due 4/30
|
Routing - PLANNING | 4/27/2015 | | 4/27/2015 | | PASS |
Cody Riddle
|
|
|
|
Case Summary (BLD) | | | 4/27/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/27/2015 | | 4/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/27/2015 | | DONE |
|
|
|
all requirments met
|
Print Occupancy Form | | | 4/27/2015 | | DONE |
|
|
|
|
Telephone call | | | 4/27/2015 | | DONE |
|
|
|
called Mark- left message that we need RP, Certificate of Value, and GC form- permit is ready for pick up
|
Routing - PLAN CHECK | 4/21/2015 | | 4/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 4/21/2015 | 4/24/2015 | 4/22/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 4/22/2015 | | DONE |
|
|
|
Two copies of Structural Calculations, Two copies of Valmont Structures (100ft monopole), Two copies of Walmont Microflect. One set to CDM and One set to AHJ Engineering
|
Routing - FIRE | 4/14/2015 | 3/27/2015 | 4/21/2015 | | PASS |
Scott Arellano
|
|
|
Plans are approved with no attached comments. Existing fire dept. vehicle access through storage facility shall be maintained to service this new tower. The electronic gate shall be outfitted with the Opticom system. The required smoke detection system within the pre-fabricated Verizon structure will be monitored by a proprietary facility and no fire alarm permit will be required.
|
1st review completed | | | 4/21/2015 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/13/2015 | | 4/13/2015 | | FAIL |
Carl D Madsen
|
|
|
E-mailed structural comments to Mark Kimber 4-13-15
|
Routing - Addressing | 3/30/2015 | | 3/31/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/31/2015 | | 3/31/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 3/30/2015 | | 3/30/2015 | | PASS |
Evan Jenkins
|
|
|
New Verizon Wireless Tower and small unmaned structure: BOI Auto Lane
|
Routing - PLANNING Land Div | 3/27/2015 | | 3/30/2015 | | PASS |
Dave Abo
|
|
|
Parcel has existing buildings with building permits.
|
Plan resubmittals received | | | 3/30/2015 | | DONE |
Christina Prado
|
|
|
Received two sets of ESC narratives and sheets marked C101; Plans stamped and taken to CDM for review
|
Plans ACCEPTED BY PLAN TECH | | | 3/27/2015 | | DONE |
|
|
|
|
Intake Approval | | | 3/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/26/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | 3/26/2015 | | | |
|
|
|
|