Letter of compliance/Occupancy | | | 7/8/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (FNL) | | | 7/8/2015 | | DONE |
|
|
|
|
BLD-Final | 7/6/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Tony Young
|
|
|
Please call Tom Andrews prior to going. Thanks. Phone #: ###-#### Inspection requested via web by Tom Andrews
|
FIRE-Final Inspection | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Jim Page
|
|
|
Fire life safety passed/complete
|
BLD-Conference | 7/6/2015 | 7/7/2015 | 7/6/2015 | P | CANC |
Tony Young
|
|
|
Please call Tom Andrews prior to going. Thanks. Phone #: ###-#### >> Inspection requested via web by Tom Andrews Inspection cancelled from web by: Tom Andrews
|
FIRE-Final Inspection | 6/16/2015 | 6/16/2015 | 6/16/2015 | P | FAIL |
Jim Page
|
|
|
Insulation/sheeting reating on fire sprinkler heads. Needs to be removed/repaired so as to not impede spray pattern of fire sprinkler head
|
Issue PAID IN FULL permit | | | 4/8/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 4/1/2015 | 4/1/2015 | 4/6/2015 | | PASS |
Carl D Madsen
|
|
|
Vanilla level 1 due 4/7
|
Routing - PLAN CHECK | 4/1/2015 | | 4/6/2015 | | PASS |
Carl D Madsen
|
|
|
level 1 due 4/7
|
1st review completed | | | 4/6/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2015 | | DONE |
|
|
|
Need Revised Cert of Value and GC
All requirements met///4/8/15
|
Routing - PUBLIC WORKS | 4/1/2015 | | 4/2/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 4/1/2015 | | 4/1/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 4/1/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 3/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 30 2015 4:17PM
|