Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-00989
StatusFinaled
Name BRIGHTON HOMES IDAHO INC
Site Address 6722 E PLAYWRIGHT DR
Project Name 
Customer Number 
ePlanReviewNo
Description
**Plan modification to extend the garage 10 feet towards the rear of the home and orientation of the home flipped** WUI Zone A, Class A Roof, Permit for the construction of a new 2810 sq. ft., two story (first story 2405 sq. ft., second story 405 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 272 sq. ft. of covered patio’s/porches and 995 sq. ft. attached garage per the approved plans, Rescheck, plan review report and any notations. SP-02 zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/9/201511/9/201511/9/2015PPASS
DetailsPhil Shearer
Garage open for access Inspection requested via web by Erby Gonzales
DOC - Permit Finaled11/9/201511/9/201511/9/2015PPASS
DetailsPhil Shearer
BLD-Final11/6/201511/6/201511/6/2015ACANC
DetailsPhil Shearer
>> Inspection requested via web by Erby Gonzales Inspection cancelled from web by: Erby Gonzales
BLD-Energy code compliance8/21/20158/21/20158/21/2015PPASS
DetailsPhil Shearer
###-#### Inspection requested via web by Erby Gonzales
BLD-Framing/Rough-in8/18/20158/19/20158/19/2015PPART
DetailsPhil Shearer
Truss bracing on A-8-10, Girder BG3. point load at FG6, fire bocking upstairs behind shower.
BLD-Wall cover8/18/20158/19/20158/19/2015APASS
DetailsPhil Shearer
Please inspect soffit WUII drywall fri or to installing fascia Inspection requested via web by Erby Gonzales
BLD-Wall cover8/18/20158/19/20158/19/2015APASS
DetailsPhil Shearer
Please inspect soffit WUII drywall fri or to installing fascia Inspection requested via web by Erby Gonzales
BLD-Framing/Rough-in8/18/20158/18/20158/18/2015PCANC
DetailsPhil Shearer
Plans on site >> Inspection requested via web by Erby Gonzales Inspection cancelled from web by: Erby Gonzales
BLD-Wall Bracing7/31/20157/31/20157/31/2015APASS
DetailsPhil Shearer
###-#### plans on site shear inspection Inspection requested via web by Erby Gonzales
BLD-Foundation6/24/20156/24/20156/24/2015PPASS
DetailsPhil Shearer
wall Phone #: ###-####
BLD-Footing6/19/20156/19/20156/19/2015PPASS
DetailsJim Storey
Doug Phone #: ###-####
CHANGE STATUS TO (ISS)  5/21/2015 DONE
OVERRIDE  5/20/2015  
Plan assigned to (JG)5/19/20155/19/20155/20/2015 PASS
DetailsJavier Guzman
plan mod
Routing - PLAN CHECK5/20/2015 5/20/2015 PASS
DetailsJavier Guzman
Routing - PLANNING5/20/2015 5/20/2015 PASS
DetailsSue Cummings
Routing - MECHANICAL5/20/2015 5/20/2015 PASS
DetailsTroy James
Case Summary (BLD)  5/20/2015 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  5/20/2015 DONE
Permit Ready to Issue  5/20/2015 DONE
Fees Due. DO NOT REISSUE PLAN MOD
Telephone call  5/20/2015 DONE
Left message with Seth letting him know plan mod is ready and there are fees due.
Inspection Record Card- Bld  5/20/2015 DONE
Plan Modification Accepted  5/19/2015 DONE
plan mod received cover sheet, 2-8 1/2 X 10 site plans, 2 res check, 1 manuals, 2 each sheet-11.1,A2.1, A3.1, A3.2, A4.1, A5.1, A6.1, A6.2, A6.3, A6.4, A7.1-Took to JG
Issue PAID IN FULL permit  5/11/2015 DONE
OVERRIDE  5/7/2015  
Plan assigned to (JG) 4/1/20155/7/2015 PASS
DetailsJavier Guzman
1st review completed, 4/17 F L2** Floodplain and PW
Routing - PUBLIC WORKS5/6/2015 5/7/2015 PASS
DetailsJennifer Bruner
Routing - PLAN CHECK5/7/2015 5/7/2015 PASS
DetailsJavier Guzman
Case Summary (BLD)  5/7/2015 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  5/7/2015 DONE
Permit Ready to Issue  5/7/2015 DONE
requirements met
Inspection Record Card- Bld  5/7/2015 DONE
Telephone call  5/7/2015 DONE
called Seth- told him permit is ready for pick up and fees due
Routing PW Flood Plain5/6/2015 5/6/2015 PASS
DetailsJason C. Taylor
Project approved. jct
1st review completed  4/8/2015 FAIL
Floodplain and PW
Routing - PLAN CHECK4/7/2015 4/8/2015 PASS
DetailsJavier Guzman
Routing - MECHANICAL4/3/2015 4/7/2015 PASS
DetailsTroy James
Routing - PLANNING4/3/2015 4/3/2015 PASS
DetailsSue Cummings
Routing - PUBLIC WORKS4/3/2015 4/3/2015 FAIL
DetailsConnie Baumgartner
Failed by Jason Taylor for flood plain
Routing PW Flood Plain4/1/2015 4/2/2015 FAIL
DetailsJason C. Taylor
Subdivision Drainage is incomplete. Jason Taylor ###-####.
Routing - Addressing4/1/2015 4/2/2015 PASS
DetailsJason C. Taylor
Plans ACCEPTED BY PLAN TECH  4/1/2015 DONE
Intake Approval  4/1/2015 PASS
Recd Pcfee & Taken To Pln CK  4/1/2015 DONE
Application received 4/1/2015