Third Notice | | 1/19/2016 | 2/11/2016 | | DONE |
|
|
|
|
Third Notice | | 12/15/2015 | 1/14/2016 | | DONE |
|
|
|
|
Second Notice | | 11/19/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
First Notice | | 10/16/2015 | 11/9/2015 | | DONE |
|
|
|
Mailed 11-10-15
|
Print Occupancy Form | | | 10/6/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/6/2015 | | DONE |
|
|
|
|
BLD-Final | 9/29/2015 | 9/30/2015 | 10/1/2015 | P | PASS |
Dave Hannah
|
|
|
Koby Phone #: ###-####
|
FIRE-Final Inspection | 9/29/2015 | 9/30/2015 | 9/30/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
Telephone call | | | 9/29/2015 | | DONE |
|
|
|
called Koby to let know Temp c of o is about to expire. He scheduled life safety and final for 9-30-15
|
BLD-Final | 7/1/2015 | 7/2/2015 | 7/2/2015 | P | PART |
Dave Hannah
|
|
|
Koby-please do as late PM as possible Phone #: ###-#### ok for temp needs new door hardwear
|
FIRE-Final Inspection | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
Temporary Occupancy | 7/2/2015 | 9/30/2015 | 7/2/2015 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | NR |
Dave Hannah
|
|
|
Koby Phone #: ###-#### plumbing and fire finals first
|
FIRE-Final Inspection | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | FAIL |
Jim Page
|
|
|
Both exterior entry doors have thumb-turn deadbolt type lock assemblies, deadbolts need to be changed to single action locking hardware. One restroom, located in corridor attached to tenant space (Included in tenant scope of work) has thumb-turn deadbolt type lock assembly, deadbolt needs to be changed to single action locking hardware. No fire extinguisher in tenat space, instructed point of contact that fire extinguisher needs to be installed in tenatnt common area.
|
Print Occupancy Form | | | 5/18/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/18/2015 | | DONE |
|
|
|
all requirements met
|
Telephone call | | | 5/18/2015 | | DONE |
|
|
|
called Koby- left message permit is ready for pick up and fees due
|
Issue PAID IN FULL permit | | | 5/18/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/14/2015 | | 5/16/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved as noted and attached
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/22/2015 | | 5/16/2015 | | PASS |
Carl Westfall
|
|
|
FULL STEAM BISTRO (May 12 - 15 days) Level 3 TI - Paper
|
Routing - PLUMBING | 5/13/2015 | | 5/15/2015 | | PASS |
Daryl Spivey
|
|
|
May require additional backflow protection on installed equipment.
|
Plan resubmittals received | | | 5/14/2015 | | DONE |
|
|
|
received 2 copies of cover sheet and plans/details- put on Carl Westfall's desk
|
Routing - PLAN CHECK | 5/12/2015 | | 5/13/2015 | | DONE |
Carl Westfall
|
|
|
Prepared resubmitted drawings for routing
|
Routing - MECHANICAL | 5/13/2015 | | 5/13/2015 | | PASS |
Troy James
|
|
|
No mechanical work as per the applicant. Internal gains generated by the Panini grill and microwave ok per the mechanical engineer.
|
Routing - FIRE | 5/7/2015 | | 5/12/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to plans
|
1st review completed | | | 5/12/2015 | | FAIL |
|
|
|
Failed plumbing, mechanical and plan check
|
Plan resubmittals received | | | 5/11/2015 | | DONE |
|
|
|
resubmittals received 2 each sheet-P0.0. P1.1, P1.2 & P2.0-took to Carl W
|
Routing - PLAN CHECK | 4/27/2015 | | 5/7/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required. See the plan review report.
|
Routing - PLUMBING | 4/27/2015 | | 4/27/2015 | | FAIL |
Bill VanDegrift
|
|
|
Provide a complete Idaho licensed stamped set of plumbing plans for TI space improvements.
|
Routing - MECHANICAL | 4/27/2015 | | 4/27/2015 | | FAIL |
Troy James
|
|
|
emailed corrections to Applicant
|
Routing PW Sewer Rating | 4/24/2015 | | 4/24/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Environmental | 4/24/2015 | | 4/24/2015 | | PASS |
Rick Christenson
|
|
|
Exsiting GI. Grease Line capped for future use.
|
Routing - PUBLIC WORKS | 4/23/2015 | | 4/24/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 4/22/2015 | | 4/23/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/22/2015 | | DONE |
|
|
|
|
Intake Approval | | | 4/22/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/22/2015 | | DONE |
|
|
|
|
Pending Assignment by JCB | 4/22/2015 | | 4/22/2015 | | DONE |
Jason Blais
|
|
|
|
Application received | | 4/7/2015 | | | |
|
|
|
|