Print Statement | | | 8/18/2015 | | DONE |
|
|
|
|
Print Statement | | | 8/18/2015 | | DONE |
|
|
|
|
First Notice | | 8/1/2015 | 8/11/2015 | | DONE |
|
|
|
Mailed 8-12
|
Permanent Occupancy | | | 7/22/2015 | | DONE |
|
|
|
|
BLD-Final | 7/20/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
FIRE-Final Inspection | 7/20/2015 | 7/21/2015 | 7/21/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
BLD-Ceiling Grid Inspection | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### ok to cover allbut for areas that need patched
|
BLD-Framing/Rough-in | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | PASS |
Jim Storey
|
|
|
Chris Phone #: ###-#### need steel col. fire protection all walls ok
|
Issue PAID IN FULL permit | | | 5/11/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/11/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/14/2015 | 4/14/2015 | 4/20/2015 | | PASS |
Carl Westfall
|
|
|
(7 days - April 22) owyhee place - 2nd story
|
Routing - PLAN CHECK | 4/14/2015 | | 4/20/2015 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 4/20/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/20/2015 | | DONE |
|
|
|
Need G.C. form and Revised certificate of value
|
Intake Approval | | | 4/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 4/14/2015 | | 4/14/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/14/2015 | | 4/14/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 4/14/2015 | | 4/14/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | | 4/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 8 2015 8:55AM
|