Third Notice | | 7/17/2017 | 8/10/2017 | | DONE |
|
|
|
Mailed 8-11-17
|
Third Notice | | 6/17/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
Third Notice | | 5/15/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
Second Notice | | 3/19/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
First Notice | | 2/4/2017 | 3/9/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/25/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/20/2017 | 1/20/2017 | 1/20/2017 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
PubWorks Occupancy Approval | 12/28/2016 | 12/28/2016 | 12/28/2016 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 11/18/2016 | 11/21/2016 | 11/21/2016 | P | NR |
Tony Young
|
|
|
Ed Phone #: ###-####,, needing temp glass
|
Zoning Approval | 11/21/2016 | 11/21/2016 | 11/21/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 11/17/2016 | 11/18/2016 | 11/18/2016 | P | NR |
Tony Young
|
|
|
Ed Phone #: ###-####,, needs tempered glass
|
BLD-Conference | 11/16/2016 | 11/18/2016 | 11/18/2016 | P | PEND |
Tony Young
|
|
|
Ed Phone #: ###-####,, zoning finals ?s
|
Print Occupancy Form | | | 11/18/2016 | | DONE |
|
|
|
|
BLD-Final | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | NR |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Final | 11/15/2016 | 11/16/2016 | 11/16/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, temp occ ok,, needs zoning,, temp glass,, signage,, drain burn protectors
|
BLD-Final | 11/9/2016 | 11/10/2016 | 11/10/2016 | A | NR |
Jim Sly
|
|
|
Ed Phone #: ###-#### Need Zoning.......and?
|
FIRE-Final Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Katie Marron
|
|
|
Life Safety Passed. Verified exit signs/emergency lighting, fire extinguishers and exit hardware.
|
Print Occupancy Form | | | 11/10/2016 | | DONE |
|
|
|
|
BLD-Aging Inspection | 8/26/2016 | 8/26/2016 | 8/26/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 8/25/2016 | 8/25/2016 | 8/26/2016 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 4/12/2016 | 4/13/2016 | 4/13/2016 | A | PASS |
Jim Sly
|
|
|
Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Tony Young
|
|
|
re-inspection ok,, ok to insulate
|
BLD-Framing/Rough-in | 3/21/2016 | 3/22/2016 | 3/22/2016 | A | NR |
Tony Young
|
|
|
Ed Phone #: ###-####,, correction posted on truss engineering
|
BLD-Footing | 11/25/2015 | 11/30/2015 | 11/30/2015 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, ok pending special inspection
|
Issue PAID IN FULL permit | | | 11/24/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/24/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/20/2015 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/12/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
Jan Welch
|
Routing - PLAN CHECK | 11/11/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 11/20/2015 | | DONE |
|
|
|
Routing completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/20/2015 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (CJW) | 5/21/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
ACTIVITY CENTER BUILDING
|
Routing - PLUMBING | 11/12/2015 | | 11/19/2015 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - MECHANICAL | 11/17/2015 | | 11/17/2015 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 11/11/2015 | | DONE |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 10/28/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/10/2015 | | 10/27/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - MECHANICAL | 10/10/2015 | | 10/23/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 10/10/2015 | | 10/22/2015 | | FAIL |
Daryl Spivey
|
|
|
see bld15-01107
|
Routing - PLAN CHECK | 10/20/2015 | | 10/21/2015 | | PASS |
Carl Westfall
|
|
|
Architect chose option to make the building Type V-A construction to avoid parapets
|
Routing PW Drainage | 10/10/2015 | | 10/20/2015 | | PASS |
Jason C. Taylor
|
|
|
Project approved under GRD15-00018 ODI 3398. JCT
|
Routing - PLANNING | 10/10/2015 | | 10/20/2015 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 10/8/2015 | | 10/16/2015 | | FAIL |
Carl Westfall
|
|
|
Fire rate wall required because the building is too close to Building Q
|
Routing - Design Review | 10/10/2015 | | 10/13/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 10/10/2015 | | 10/12/2015 | | FAIL |
Katie Marron
|
|
|
Hazardous Material Inventory statement not provided. Report attached to case and emailed to architect.
|
Routing PW Sewer Rating | 10/10/2015 | | 10/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Design | 10/10/2015 | | 10/12/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 10/10/2015 | | 10/12/2015 | | PASS |
Jennifer Bruner
|
|
|
1st work flow broke. Please route to all those in Public works who need to see it.
|
Plan resubmittals received | | | 10/8/2015 | | DONE |
Carl Westfall
|
|
|
|
Routing PW Drainage | 9/21/2015 | | 9/21/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plan resubmittals requested | | | 8/5/2015 | | DONE |
|
|
|
Workflow in ePlanReview completed
|
Routing PW Drainage | 6/1/2015 | | 8/5/2015 | | FAIL |
Jason C. Taylor
|
|
|
|
Route to Impact Fee Review | 7/25/2015 | 7/28/2015 | 7/28/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 7/25/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/21/2015 | | 7/25/2015 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 5/21/2015 | | 6/8/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing PW Sewer Design | 5/21/2015 | | 6/4/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Separate sewer review underway in Public Works.
|
Routing PW Drainage | 5/21/2015 | | 6/1/2015 | | |
Brian Murphy
|
|
|
Re-assigned to Jason Taylor
|
Routing - FIRE | 5/21/2015 | | 6/1/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed comments to architect and attached to plans.
|
Routing - MECHANICAL | 5/21/2015 | | 6/1/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 5/21/2015 | | 5/28/2015 | | PASS |
Dave Abo
|
|
|
|
Routing PW Sewer Rating | 5/21/2015 | | 5/28/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | 5/21/2015 | | 5/28/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLUMBING | 5/21/2015 | | 5/27/2015 | | FAIL |
Daryl Spivey
|
|
|
|
Routing - Design Review | 5/21/2015 | | 5/27/2015 | | PASS |
Josh Wilson
|
|
|
DRH14-00349
|
Routing - Erosion and Sediment | 5/21/2015 | | 5/26/2015 | | PASS |
Evan Jenkins
|
|
|
(ACTIVITY CENTER)
|
Routing PW Street Lights | 5/21/2015 | | 5/26/2015 | | PASS |
Mike D Hedge
|
|
|
|
Routing - Addressing | 5/21/2015 | | 5/21/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/21/2015 | | 5/21/2015 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 5/21/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/21/2015 | | 5/21/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Plan Reviewer's activity | | | 5/20/2015 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 5/15/2015 | | FAIL |
|
|
|
|
Intake Approval | | | 5/6/2015 | | FAIL |
|
|
|
|
Application received | | | 4/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2015 3:20PM
|