Permanent Occupancy | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
PubWorks Occupancy Approval | 3/27/2017 | 3/27/2017 | 3/27/2017 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/22/2017 | 3/23/2017 | 3/24/2017 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
FIRE-Final Inspection | 3/22/2017 | 3/23/2017 | 3/23/2017 | A | PASS |
Jim Page
|
|
|
Previous issues with fire alarm system have been resolved, final life fire safety inspection passed/complete.
|
BLD-Aging Inspection | 3/13/2017 | 3/13/2017 | 3/14/2017 | | PEND |
Tony Young
|
|
|
|
Temporary Occupancy | 1/30/2017 | 4/30/2017 | 1/30/2017 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval | 1/30/2017 | 1/30/2017 | 1/30/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, temp occ ok,, trades,, stairs
|
FIRE-Final Inspection | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | PART |
Jim Page
|
|
|
Partial final inspection complete for life fire safety, (TCO authorized on life fire safety per conversation with Scott Arellano) fire sprinkler inspection complete, partial completion for fire alarm system (contractor is troubleshooting sync issue on level 4, fire alarm permit will remain in issued status until issue is resolved), knox box is in place, fire extinguishers are in place with current inspection tags. Fire life safety can be finaled when FIR permit for fire alarms is complete.
|
Print Occupancy Form | | | 12/30/2016 | | DONE |
|
|
|
|
BLD-Energy code compliance | 11/1/2016 | 11/2/2016 | 11/2/2016 | A | PASS |
Tony Young
|
|
|
1st floor; Ed Phone #: ###-####,, building Q 1st or main floor ok
|
BLD-Framing/Rough-in | 11/1/2016 | 11/1/2016 | 11/1/2016 | P | PASS |
Tony Young
|
|
|
Ed// 1st floor Phone #: ###-####
|
BLD-Framing/Rough-in | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | PART |
Tony Young
|
|
|
Ed// 1st floor Phone #: ###-####,, needs mech pass 1st,, ok to insulate unaffected areas
|
BLD-Energy code compliance | 10/28/2016 | 10/31/2016 | 10/31/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 2nd floor ok
|
BLD-Framing/Rough-in | 10/28/2016 | 10/28/2016 | 10/28/2016 | P | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 2nd floor ok
|
BLD-Energy code compliance | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | PART |
Tony Young
|
|
|
3rd floor; Ed Phone #: ###-####,, corrections in paint,, ok to insulate
|
BLD-Energy code compliance | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####,, 4th floor
|
BLD-Energy code compliance | 9/19/2016 | 9/20/2016 | 9/20/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 4th floor,, ok pending fire sprinkler pass on 4th floor
|
BLD-Energy code compliance | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | NR |
Tony Young
|
|
|
Ed Phone #: ###-####,, 4th floor,, needs tenting approval on sprinklers
|
BLD-Framing/Rough-in | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | PART |
Jim Sly
|
|
|
Ed// 4th floor Phone #: ###-#### Framing OK.......Told Contr. to call us so we can look at Draftstops when completed.
|
BLD-Energy code compliance | 7/13/2016 | 7/14/2016 | 7/14/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, building Q plumbing walls ok
|
BLD-Wall Bracing | 7/11/2016 | 7/12/2016 | 7/12/2016 | A | PASS |
Tony Young
|
|
|
Ed-interior Shear Phone #: ###-####,, interior shear ok,, work in progress,, ok
|
BLD-Wall Bracing | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, exterior shear ok building Q
|
BLD-Footing | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | PART |
Jim Sly
|
|
|
Insulation // Ed Phone #: ###-#### South 3rd of Bldg........OK pending Geo Tech special inspection, tests and approvals.
|
BLD-Footing | 3/10/2016 | 3/11/2016 | 3/11/2016 | A | PEND |
Tony Young
|
|
|
Ed Phone #: ###-####,, ok pending special inspection
|
Issue PAID IN FULL permit | | | 11/24/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/24/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/20/2015 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/12/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
Jan Welch
|
Routing - PLAN CHECK | 11/11/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 11/20/2015 | | DONE |
|
|
|
Routing completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/20/2015 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (CJW) | 5/21/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
Building Q (1st review done)
|
Routing - PLUMBING | 11/12/2015 | | 11/19/2015 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - MECHANICAL | 11/12/2015 | | 11/17/2015 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 11/11/2015 | | DONE |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 10/28/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/10/2015 | | 10/27/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - MECHANICAL | 10/10/2015 | | 10/23/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 10/10/2015 | | 10/22/2015 | | FAIL |
Daryl Spivey
|
|
|
see bld15-01107
|
Routing PW Drainage | 10/10/2015 | | 10/20/2015 | | PASS |
Jason C. Taylor
|
|
|
Project approved under GRD15-00018 ODI 3398. JCT
|
Routing - PLANNING | 10/10/2015 | | 10/20/2015 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 10/8/2015 | | 10/16/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Routing - Design Review | 10/10/2015 | | 10/13/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 10/10/2015 | | 10/12/2015 | | FAIL |
Katie Marron
|
|
|
Comments not adequately addressed. Report attached to case and emailed to architect.
|
Routing PW Sewer Rating | 10/10/2015 | | 10/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Design | 10/10/2015 | | 10/12/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 10/10/2015 | | 10/12/2015 | | PASS |
Jennifer Bruner
|
|
|
The 1st work flow broke. Please route this to all those in Public works who need to see it.
|
Plan resubmittals received | | | 10/8/2015 | | DONE |
|
|
|
|
Routing PW Drainage | 9/21/2015 | | 9/21/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plan resubmittals requested | | | 8/5/2015 | | DONE |
|
|
|
Workflow in ePlanReview completed
|
Routing PW Drainage | 6/1/2015 | | 8/5/2015 | | FAIL |
Jason C. Taylor
|
|
|
|
Route to Impact Fee Review | 6/27/2015 | 6/30/2015 | 6/29/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 6/27/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/21/2015 | | 6/27/2015 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 5/21/2015 | | 6/8/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing PW Sewer Design | 5/21/2015 | | 6/4/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Separate sewer review underway in Public Works.
|
Routing - FIRE | 5/21/2015 | | 6/2/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed comments to architect and attached to plans
|
Routing PW Drainage | 5/21/2015 | | 6/1/2015 | | |
Brian Murphy
|
|
|
Re-assigned to Jason Taylor
|
Routing - MECHANICAL | 5/21/2015 | | 6/1/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 5/21/2015 | | 5/28/2015 | | PASS |
Dave Abo
|
|
|
|
Routing PW Sewer Rating | 5/21/2015 | | 5/28/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | 5/21/2015 | | 5/28/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLUMBING | 5/21/2015 | | 5/27/2015 | | FAIL |
Daryl Spivey
|
|
|
|
Routing - Design Review | 5/21/2015 | | 5/27/2015 | | PASS |
Josh Wilson
|
|
|
DRH14-00349
|
Routing PW Street Lights | 5/21/2015 | | 5/26/2015 | | PASS |
Mike D Hedge
|
|
|
Street lights to be addressed in submittla #2
|
Routing - Erosion and Sediment | 5/21/2015 | | 5/26/2015 | | PASS |
Evan Jenkins
|
|
|
(APARTMENT BUILDING Q)
|
Routing - Addressing | 5/21/2015 | | 5/21/2015 | | PASS |
Emily Dixon
|
|
|
Address should be 7472 W Saxton Dr.
|
Routing - PUBLIC WORKS | 5/21/2015 | | 5/21/2015 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 5/21/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/21/2015 | | 5/21/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Plan Reviewer's activity | | | 5/20/2015 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 5/15/2015 | | FAIL |
|
|
|
|
Intake Approval | | | 5/6/2015 | | FAIL |
|
|
|
|
Application received | | | 4/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2015 3:20PM
|
First Notice | | 4/7/2017 | | | |
|
|
|
|