Print Occupancy Form | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
Permanent Occupancy | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval | 3/27/2017 | 3/27/2017 | 3/27/2017 | | DONE |
Andrea Tuning
|
|
|
|
PubWorks Occupancy Approval | 3/27/2017 | 3/27/2017 | 3/27/2017 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/24/2017 | 3/24/2017 | 3/24/2017 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Final | 3/1/2017 | 3/1/2017 | 3/1/2017 | P | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, temp occ. ok
|
BLD-Final | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | CANC |
Tony Young
|
|
|
Ed Phone #: ###-####
|
FIRE-Final Inspection | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are mounted with current inspection tags, knox box is in place. Final life fire safety inspection passed/complete.
|
BLD-Energy code compliance | 11/18/2016 | 11/21/2016 | 11/21/2016 | A | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####,, 1st and 2nd floor
|
BLD-Energy code compliance | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, need rims insulated
|
BLD-Framing/Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 1st and 2nd floor pre rock drops ok to cover
|
BLD-Energy code compliance | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PART |
Tony Young
|
|
|
Ed-1st and 2nd floors Phone #: ###-####,, pre rock areas ok to insulate
|
BLD-Energy code compliance | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | PASS |
Tony Young
|
|
|
3rd floor // Berry Phone #: ###-####
|
BLD-Energy code compliance | 10/21/2016 | 10/21/2016 | 10/22/2016 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####,, 3rd floor
|
BLD-Energy code compliance | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | NR |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 10/19/2016 | 10/20/2016 | 10/21/2016 | P | PEND |
Tony Young
|
|
|
Ed Phone #: ###-####,, 3rd floor,, ok pending sprinkler pass
|
BLD-Framing/Rough-in | 10/18/2016 | 10/19/2016 | 10/19/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 3rd floor only.. need sprinkler pass on 3rd floor,, ok to insulate the walls
|
BLD-Energy code compliance | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, plumbing walls ok
|
BLD-Wall Bracing | 8/22/2016 | 8/23/2016 | 8/23/2016 | A | PASS |
Tony Young
|
|
|
Ed// exterior and interior shear panel- every floor Phone #: ###-####
|
BLD-Footing | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, interior footings,, pending special inspection
|
BLD-Other | 5/17/2016 | 5/18/2016 | 5/18/2016 | A | PASS |
Jim Sly
|
|
|
Ed-underfloor concrete Phone #: ###-#### Pending Geotech special insp, tests and approvals.
|
BLD-Footing | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, pending special inspection report
|
Issue PAID IN FULL permit | | | 1/12/2016 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 1/12/2016 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 12/22/2015 | | DONE |
|
|
|
1st 180 day extension granted by Jason B
|
OVERRIDE | | | 11/20/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 11/11/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 11/12/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
Jan Welch
|
Plan Reviewer's activity | | | 11/20/2015 | | DONE |
|
|
|
Routing completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/20/2015 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (CJW) | 5/21/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
Building V (1st review done)
|
Routing - PLUMBING | 11/12/2015 | | 11/19/2015 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - MECHANICAL | 11/12/2015 | | 11/17/2015 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 11/11/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/28/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/10/2015 | | 10/27/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - MECHANICAL | 10/10/2015 | | 10/23/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 10/10/2015 | | 10/21/2015 | | FAIL |
Daryl Spivey
|
|
|
|
Routing PW Drainage | 10/10/2015 | | 10/20/2015 | | PASS |
Jason C. Taylor
|
|
|
Project approved under GRD15-00018 ODI 3398. JCT
|
Routing - PLANNING | 10/10/2015 | | 10/20/2015 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 10/8/2015 | | 10/16/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines after the 2nd IBC review
|
Routing - Design Review | 10/10/2015 | | 10/13/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 10/10/2015 | | 10/12/2015 | | FAIL |
Katie Marron
|
|
|
Comments not adequately addressed. Report attached to case and emailed to architect.
|
Routing PW Sewer Rating | 10/10/2015 | | 10/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Design | 10/10/2015 | | 10/12/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 10/10/2015 | | 10/12/2015 | | PASS |
Jennifer Bruner
|
|
|
The 1st work flow broke. Please route this to all those in Public Works who need to see it.
|
Plan resubmittals received | | | 10/8/2015 | | DONE |
|
|
|
|
Routing PW Drainage | 9/21/2015 | | 9/21/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plan resubmittals requested | | | 8/5/2015 | | DONE |
|
|
|
Workflow in ePlanReview completed
|
Routing PW Drainage | 6/1/2015 | | 8/5/2015 | | FAIL |
Jason C. Taylor
|
|
|
|
Route to Impact Fee Review | 6/20/2015 | 6/23/2015 | 6/25/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 6/20/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/21/2015 | | 6/20/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 5/21/2015 | | 6/8/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing PW Sewer Design | 5/21/2015 | | 6/4/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Separate sewer review underway in Public Works.
|
Routing - FIRE | 5/21/2015 | | 6/2/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed comments to architect and attached to plans.
|
Routing PW Drainage | 5/21/2015 | | 6/1/2015 | | |
Brian Murphy
|
|
|
Re-assigned to Jason Taylor
|
Routing - MECHANICAL | 5/21/2015 | | 6/1/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 5/21/2015 | | 5/28/2015 | | PASS |
Dave Abo
|
|
|
|
Routing PW Sewer Rating | 5/21/2015 | | 5/28/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | 5/21/2015 | | 5/28/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLUMBING | 5/21/2015 | | 5/27/2015 | | FAIL |
Daryl Spivey
|
|
|
|
Routing - Design Review | 5/21/2015 | | 5/27/2015 | | PASS |
Josh Wilson
|
|
|
DRH14-00349
|
Routing PW Street Lights | 5/21/2015 | | 5/26/2015 | | PASS |
Mike D Hedge
|
|
|
Street lights to be addressed in submittal #2
|
Routing - Erosion and Sediment | 5/21/2015 | | 5/26/2015 | | PASS |
Evan Jenkins
|
|
|
(APARTMENT BUILDING V)
|
Routing - Addressing | 5/21/2015 | | 5/21/2015 | | FAIL |
Emily Dixon
|
|
|
This subdivision needs to be recorded.
|
Routing - PUBLIC WORKS | 5/21/2015 | | 5/21/2015 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 5/21/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/21/2015 | | 5/21/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Plan Reviewer's activity | | | 5/20/2015 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 5/15/2015 | | FAIL |
|
|
|
|
Intake Approval | | | 5/6/2015 | | FAIL |
|
|
|
|
Application received | | | 4/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2015 3:20PM
|
First Notice | | 4/7/2017 | | | |
|
|
|
|