Permit Information
Permit NumberBLD15-01118
StatusFinaled
Name BACH LAND AND DEVELOPMENT LLC
Site Address 7380 W SAXTON DR
Project NameThe Kensington Apartments A
Customer NumberBLD15-01118 - BLD15-01137
ePlanReviewYes
Description
(15 PERMITS TOTAL FILED UNDER BLD15-01118 IN EPLANREVIEW) (THE KENSINGTON APARTMENTS - BUILDING A) The NFPA 13-R fire sprinkler system is used for occupancy. To construct a 9,258 square foot two story apartment building (5,342 sq. ft. 1st story with four 2.a units and 3,916 sq. ft. 2nd story with four 1.b units). All ground floor units are required to comply as Type B dwelling units. No elevator is provided in this building. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, fiber-cement board siding, manufactured stone veneer, 1-hr dwelling unit separations, .5-hr minimum fire-resistance-rated corridors with 20 minute smoke- and draft-control doors, exterior exit stairways fire rated like the corridor, steel stairways with concrete treads, interior nonbearing walls, millwork, and finishes. Special Inspection is required for soils and for concrete. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/30/201712/1/201712/1/2017APASS
DetailsTony Young
Ed Phone #: ###-####
PubWorks Occupancy Approval11/30/201711/30/201711/30/2017 DONE
DetailsTiffany Lowery
Permanent Occupancy  11/30/2017 DONE
Zoning Approval11/21/201711/21/201711/21/2017 DONE
DetailsAndrea Tuning
BLD-Final10/9/201710/9/201710/10/2017PPART
DetailsJim Sly
Ed Phone #: ###-####
Structural final only.....OK. OK for Perm Occ when all required sigatures are obtained for Perm Occ.
FIRE-Final Inspection10/9/201710/9/201710/9/2017PPASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by the fire sprinkler riser room. Final life fire safety inspection passed/complete.
BLD-Energy code compliance8/7/20178/8/20178/8/2017APASS
DetailsTony Young
Ed Phone #: ###-####
BLD-Other8/4/20178/4/20178/4/2017PPASS
DetailsTony Young
Fire colcking // Ed Phone #: ###-####
BLD-Framing/Rough-in8/4/20178/4/20178/4/2017PPASS
DetailsTony Young
Ed Phone #: ###-####,, ok pending trades
BLD-Energy code compliance7/20/20177/21/20177/21/2017PPART
DetailsTony Young
Insulation // Ed Phone #: ###-####,, drop areas ok on main floor
BLD-Energy code compliance6/28/20176/29/20176/29/2017PPART
DetailsDave Hannah
Ed Phone #: ###-#### second floor ok to cover
BLD-Energy code compliance6/27/20176/28/20176/28/2017APASS
DetailsTony Young
Second floor and fire colk. /// Ed Phone #: ###-####
BLD-Framing/Rough-in6/26/20176/27/20176/27/2017APART
DetailsTony Young
Second floor and fire colk. /// Ed Phone #: ###-####,, ok to insulate,, needs fire passed
BLD-Framing/Rough-in6/26/20176/26/20176/26/2017PNR
DetailsTony Young
Second floor and fire colk. /// Ed Phone #: ###-####,, needs sprinklers 1st
BLD-Wall Bracing6/19/20176/19/20176/19/2017PPASS
DetailsTony Young
Ed Phone #: ###-####,, exterior ok
BLD-Wall Bracing5/22/20175/22/20175/23/2017PPART
DetailsTony Young
interior shear // Ed Phone #: ###-####, interior hold downs
BLD-Footing2/23/20172/24/20172/24/2017APART
DetailsJim Sly
Ed Phone #: ###-####
OK pending Geotech special inspections, tests and approval.
BLD-Final11/16/201611/16/201611/16/2016PCANC
DetailsJim Sly
ed Phone #: ###-####
Routing - PUBLIC WORKS10/10/2016 10/10/2016 PASS
DetailsRachael Beierle
Place hold on job4/8/2016 5/20/2016 DONE
DetailsCarlos Velazquez
Multiple permits under one ePlan case -
DO NOT ISSUE without the following permits: BLD15-01121 thru BLD15-01128, BLD15-01130, BLD15-01335 thru BLD15-01137, BLD16-00539 & BLD16-00540
Issue PAID IN FULL permit  5/20/2016 DONE
Print Occupancy Form  5/20/2016 DONE
Telephone call  4/22/2016 DONE
Left a message for Royce that these five permits are going to be 20 days their expiration date and that he would need to send in a request for a 180 day extension because normally if we don't hear back from anyone we expire the permits 20 days after the expiration date. Left the permit numbers and Jason B's email.
Extend Review Timeline  4/22/2016 DONE
1st 180 days approved by Jason B. See documents
Telephone call  4/20/2016 DONE
Spoke with Brenda and she informed me that James is the project manager and is acutally here in Boise, but they didn't have his new cell phone in the system so she transferred me to Royce, his assistant. Left Royce a message stated that there are five permits for the Kennsington Apartments that are 17 days past their expiration date and they would need to send in a request for an extension if they are not ready to pick them up. Asked Royce to give me a call as well so that I know he recieved my message and understood what I was saying
Telephone call  4/14/2016 DONE
Left a message for James informing him that some of the permits were picked up except for 5 of them. Informed him that, that is ok but he would need to send in a request for an extension to Jason B since they are past their expiration date.
Telephone call  4/11/2016 DONE
Left a message for James, with Bach Homes, informing him that the Kensington Apartment permits are 8 days past their expiration date and recommended he request another extension for 180 days. Also informed him that if he does request the extension it will be the final one that can be given.
Permit Ready to Issue  4/8/2016 DONE
DetailsChristina Prado
All requirements met
PLANS/APPL TAKEN TO FRONT DESK  4/7/2016 DONE
Routing - PLAN CHECK3/31/2016 4/7/2016 PASS
DetailsCarl Westfall
(4-4-16) Waiting for results of the structural resubmittal review.

(4-7-16) Structural approved.
Routing Off Site - STRUCTURAL4/1/2016 4/7/2016 PASS
DetailsCarl Westfall
Dave Haugland
Plan assigned to (CJW)7/20/2015 4/7/2016 PASS
DetailsCarl Westfall
(1st done) (Mar 8 - 3 weeks) (Aug 28 - 6 weeks) Building A - Phase 2
Routing PW Drainage4/1/2016 4/5/2016 PASS
DetailsJason C. Taylor
Routing PW Street Lights4/1/2016 4/5/2016 PASS
DetailsTom Marshall
Routing PW Sewer Design4/1/2016 4/5/2016 PASS
DetailsKyle S. Rosenmeyer
Routing - FIRE4/1/2016 4/5/2016 PASS
DetailsKatie Marron
Resubmittal includes enclosing stairways per IBC plan review. No revised report required.
Routing PW Solid Waste4/1/2016 4/4/2016 PASS
DetailsMegan Durrell
Routing - PUBLIC WORKS4/1/2016 4/1/2016 PASS
DetailsRachael Beierle
Routing - Addressing4/1/2016 4/1/2016 PASS
DetailsLaura Hunter
Red lines to be transfered to most recent version
Routing PW Sewer Rating4/1/2016 4/1/2016 PASS
DetailsRachael Beierle
Plan resubmittals received  3/31/2016 DONE
Plan resubmittals requested  3/9/2016 DONE
Routing Off Site - STRUCTURAL2/22/2016 3/8/2016 FAIL
DetailsCarl Westfall
(Dave Haugland) Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - PLANNING Land Div2/22/2016 3/1/2016 PASS
DetailsTodd Tucker
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - PLUMBING2/19/2016 3/1/2016 PASS
DetailsBill VanDegrift
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW

1) horizontal venting is limited to bathroom groups per ISPC 908.2, vent toilets or pipe per code
2) Bldg's F and S, shutoff valve for the hose bibs must be above the insulation for freeze protection, provide access.
3) see redlines
Routing PW Solid Waste2/22/2016 2/29/2016 PASS
DetailsMegan Durrell
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing PW Drainage2/22/2016 2/26/2016 FAIL
DetailsJason C. Taylor
Requested 2 full size paper copies for review/approval. JCT
Routing PW Sewer Design2/22/2016 2/25/2016 PASS
DetailsKyle S. Rosenmeyer
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - MECHANICAL2/22/2016 2/25/2016 PASS
DetailsTroy James
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - PLAN CHECK2/17/2016 2/25/2016 FAIL
DetailsCarl Westfall
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - Design Review2/22/2016 2/24/2016 PASS
DetailsJosh Wilson
OK PER MODIFICATION DRH15-00313 JGW 2-24-16...Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - Addressing2/22/2016 2/24/2016 PASS
DetailsLaura Hunter
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - FIRE2/22/2016 2/24/2016 PASS
DetailsKatie Marron
No change from previous review.
Routing PW Sewer Rating2/22/2016 2/24/2016 PASS
DetailsJennifer Bruner
Buildings B, C, X, Y, Z, and AA have been removed from Phase 2. These buildings will be constructed under a future phase. Building R has been replaced with an expanded building F and building S. Garage #4 and Garage #5 have been added to Phase 2. Because the work flow broke, your changemarks have likely been lost from the report but should still be on the drawings. If you have “redlines” on the drawings, please transfer them to the most recent version. Some response documents have been uploaded by the Architect that may help with the 2nd review. CJW
Routing - PUBLIC WORKS2/24/2016 2/24/2016 PASS
DetailsRachael Beierle
Plan resubmittals received  2/17/2016 DONE
Extend Review Timeline  12/17/2015 DONE
DetailsCarl Westfall
Request approved by Jason Blais, Building Official. See attached document.
Routing PW Drainage9/21/2015 9/21/2015 PASS
DetailsJason C. Taylor
Route to Impact Fee Review8/27/20158/30/20158/28/2015 PASS
DetailsCindy M. Gould
1st review completed  8/27/2015 DONE
Plan resubmittals requested  8/27/2015 DONE
Routing - PLAN CHECK7/22/2015 8/26/2015 FAIL
DetailsCarl Westfall
Revised drawings required
Routing Off Site - STRUCTURAL7/22/2015 8/19/2015 FAIL
DetailsCarl Westfall
Dave Haugland
Routing PW Drainage7/23/2015 8/6/2015 FAIL
DetailsJason C. Taylor
Please upload the following revised sheets for approval: Civil Sheets C4.1-C4.4 & C5.1-C5.10, updated Stormwater Drainage Report, updated O&M Manual. Jason Taylor ###-####
Routing PW Sewer Design7/23/2015 8/6/2015 PASS
DetailsKyle S. Rosenmeyer
Sewer approved under separate Public Works project.
Routing - PLUMBING7/22/2015 8/5/2015 FAIL
DetailsDaryl Spivey
1) provide water plans for buildings A, B, C, the 1st-2nd and 3rd floors of uilding D and AA
2) WH-1 will not work for 3 bedroom units or larger.
3) provide suds relief
4) 4" min. sewer services to all buildings
5) horizontal wet venting systems must comply with ISPC 908.2.3.
6) 3/4" cold water branches serving 2 and 2 1/2 bath units are undersized.
7) If r.p.s are installed on water service lines they are not allowed in walls and must be provided with adequate drainage.
Routing PW Sewer Rating7/23/2015 7/27/2015 PASS
DetailsJennifer Bruner
Routing - FIRE7/22/20157/22/20157/24/2015 PASS
DetailsKatie Marron
Comments attached to case.
Routing - PLANNING Land Div7/22/2015 7/23/2015 PASS
DetailsDave Abo
Routing - Addressing7/22/2015 7/23/2015 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS7/22/2015 7/23/2015 PASS
DetailsJennifer Bruner
Routing - Design Review7/22/2015 7/23/2015 PASS
DetailsJosh Wilson
Routing - MECHANICAL7/22/2015 7/23/2015 PASS
DetailsTroy James
Routing PW Solid Waste7/23/2015 7/23/2015 PASS
DetailsMegan Durrell
Pending Assignment by TLW7/22/2015 7/22/2015 DONE
DetailsTim L. Woodard
Routing - Erosion and Sediment7/22/2015 7/22/2015 PASS
DetailsAndy J. Long
SWPPP narrative and site map submitted and approved on ePlan. Vald PD, need to designate RP. See ESC15-00504 for main site permit (21.9 acres)
Intake Approval  7/20/2015 PASS
Intake Approval  6/25/2015 FAIL
(6-23-15) Drawings submitted in ePlanReview.

(6-25-15) Please refer to the circled items on the plan intake checklist and resolve them as noted.
Application received  4/9/2015 DONE
Application submitted via PDS Online on Apr 9 2015 3:20PM
First Notice 12/10/2017   
Routing PW Solid Waste10/10/2016    
DetailsEvan Carpenter