PubWorks Occupancy Approval | 11/30/2017 | 11/30/2017 | 11/30/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 11/30/2017 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval | 11/21/2017 | 11/21/2017 | 11/21/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 9/12/2017 | 9/13/2017 | 9/13/2017 | A | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####,, ok pending others
|
FIRE-Final Inspection | 9/11/2017 | 9/11/2017 | 9/11/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers have current tags and were being placed at time of inspection. Final life fire safety inspection passed/complete.
|
BLD-Energy code compliance | 7/12/2017 | 7/13/2017 | 7/13/2017 | A | PASS |
Tony Young
|
|
|
Ed-1st floor Phone #: ###-####
|
BLD-Other | 7/11/2017 | 7/12/2017 | 7/12/2017 | A | PASS |
Tony Young
|
|
|
Ed-fire caulking 1st floor Phone #: ###-####
|
BLD-Framing/Rough-in | 7/11/2017 | 7/12/2017 | 7/12/2017 | A | PART |
Tony Young
|
|
|
Ed-1st floor Phone #: ###-####,, ok pending trades
|
BLD-Energy code compliance | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PASS |
Jim Sly
|
|
|
2nd floor // Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 6/28/2017 | 6/29/2017 | 6/29/2017 | P | PASS |
Dave Hannah
|
|
|
2nd floor // Ed Phone #: ###-#### ok to insulate
|
BLD-Energy code compliance | 6/20/2017 | 6/20/2017 | 6/21/2017 | P | PASS |
Tony Young
|
|
|
3rd floor
|
BLD-Energy code compliance | 6/19/2017 | 6/20/2017 | 6/20/2017 | A | PEND |
Tony Young
|
|
|
3rd floor
|
BLD-Energy code compliance | 6/19/2017 | 6/19/2017 | 6/19/2017 | P | NR |
Tony Young
|
|
|
3rd floor // ed Phone #: ###-####,, needs mech pass
|
BLD-Other | 6/16/2017 | 6/16/2017 | 6/16/2017 | P | PEND |
Tony Young
|
|
|
Ed-tiniting-2nd and 3rd floors Phone #: ###-####,, needs fire person to inspect
|
BLD-Other | 6/15/2017 | 6/15/2017 | 6/15/2017 | P | PASS |
Tony Young
|
|
|
Ed-fire caulking-3rd floor Phone #: ###-####
|
BLD-Framing/Rough-in | 6/14/2017 | 6/15/2017 | 6/15/2017 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 3rd floor ok pending trades
|
BLD-Other | 6/14/2017 | 6/15/2017 | 6/15/2017 | A | PART |
Tony Young
|
|
|
Ed-fire caulking-3rd floor Phone #: ###-#### work in progress
|
BLD-Energy code compliance | 6/8/2017 | 6/8/2017 | 6/9/2017 | P | PASS |
Tony Young
|
|
|
Ed-pre-rock Phone #: ###-####
|
BLD-Other | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, pre rock fire caulking ok 2nd floor
|
BLD-Other | 6/2/2017 | 6/5/2017 | 6/5/2017 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, pre rock 1st floor
|
BLD-Wall Bracing | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Jim Sly
|
|
|
Ed Phone #: ###-#### Hold downs.....Anchor bolts in interior braced wall lines....OK.
|
BLD-Wall Bracing | 3/14/2017 | 3/14/2017 | 3/14/2017 | P | PASS |
Tony Young
|
|
|
Shear // Ed Phone #: ###-####
|
BLD-Other | 2/3/2017 | 2/6/2017 | 2/6/2017 | A | PART |
Tony Young
|
|
|
Roof nailing - Ed Phone #: ###-#### no inspection made,, weather and 4 story issues,, ok pending self certification
|
BLD-Foundation | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PEND |
Tony Young
|
|
|
Ed-slab Phone #: ###-####,, special inspection
|
BLD-Foundation | 10/20/2016 | 10/20/2016 | 10/21/2016 | P | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, special inspector on site
|
Routing - PUBLIC WORKS | 10/10/2016 | | 10/10/2016 | | PASS |
Rachael Beierle
|
|
|
|
BLD-Footing | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | PEND |
Tony Young
|
|
|
Ed Phone #: ###-####,, pending special insp
|
Issue PAID IN FULL permit | | | 5/20/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/20/2016 | | DONE |
|
|
|
|
Place hold on job | 4/8/2016 | | 5/20/2016 | | DONE |
Carlos Velazquez
|
|
|
Multiple permits under one ePlan case -
DO NOT ISSUE without the following permits: BLD15-01121 thru BLD15-01128, BLD15-01130, BLD15-01335 thru BLD15-01137, BLD16-00539 & BLD16-00540
|
Telephone call | | | 4/22/2016 | | DONE |
|
|
|
Left a message for Royce that these five permits are going to be 20 days their expiration date and that he would need to send in a request for a 180 day extension because normally if we don't hear back from anyone we expire the permits 20 days after the expiration date. Left the permit numbers and Jason B's email.
|
Extend Review Timeline | | | 4/22/2016 | | DONE |
|
|
|
1st 180 days approved by Jason B. See documents
|
Telephone call | | | 4/20/2016 | | DONE |
|
|
|
Spoke with Brenda and she informed me that James is the project manager and is acutally here in Boise, but they didn't have his new cell phone in the system so she transferred me to Royce, his assistant. Left Royce a message stated that there are five permits for the Kennsington Apartments that are 17 days past their expiration date and they would need to send in a request for an extension if they are not ready to pick them up. Asked Royce to give me a call as well so that I know he recieved my message and understood what I was saying
|
Telephone call | | | 4/14/2016 | | DONE |
|
|
|
Left a message for James informing him that some of the permits were picked up except for 5 of them. Informed him that, that is ok but he would need to send in a request for an extension to Jason B since they are past their expiration date.
|
Telephone call | | | 4/11/2016 | | DONE |
|
|
|
Left a message for James, with Bach Homes, informing him that the Kensington Apartment permits are 8 days past their expiration date and recommended he request another extension for 180 days. Also informed him that if he does request the extension it will be the final one that can be given.
|
Permit Ready to Issue | | | 4/8/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/31/2016 | | 4/7/2016 | | PASS |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 4/1/2016 | | 4/7/2016 | | PASS |
Carl Westfall
|
|
|
Dave Haugland
|
Plan assigned to (CJW) | 7/20/2015 | | 4/7/2016 | | PASS |
Carl Westfall
|
|
|
Building E - Phase 2
|
Routing PW Drainage | 4/1/2016 | | 4/5/2016 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - FIRE | 4/1/2016 | | 4/5/2016 | | PASS |
Katie Marron
|
|
|
Resubmittal to enclose stairways per IBC plan review. No revised report required.
|
Routing PW Sewer Design | 4/1/2016 | | 4/5/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Street Lights | 4/1/2016 | | 4/5/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 4/1/2016 | | 4/4/2016 | | PASS |
Megan Durrell
|
|
|
|
Routing - PUBLIC WORKS | 4/1/2016 | | 4/1/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Sewer Rating | 4/1/2016 | | 4/1/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 4/1/2016 | | 4/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Plan resubmittals received | | | 3/31/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/9/2016 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/22/2016 | | 3/8/2016 | | FAIL |
Carl Westfall
|
|
|
Dave Haugland
|
Routing - PLANNING Land Div | 2/22/2016 | | 3/1/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLUMBING | 2/22/2016 | | 3/1/2016 | | PASS |
Bill VanDegrift
|
|
|
|
Routing PW Solid Waste | 2/22/2016 | | 2/29/2016 | | PASS |
Megan Durrell
|
|
|
|
Routing PW Drainage | 2/22/2016 | | 2/26/2016 | | FAIL |
Jason C. Taylor
|
|
|
|
Routing - PLAN CHECK | 2/17/2016 | | 2/25/2016 | | FAIL |
Carl Westfall
|
|
|
|
Routing - MECHANICAL | 2/22/2016 | | 2/25/2016 | | PASS |
Troy James
|
|
|
|
Routing PW Sewer Design | 2/22/2016 | | 2/25/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 2/22/2016 | | 2/24/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - FIRE | 2/22/2016 | | 2/24/2016 | | PASS |
Katie Marron
|
|
|
No change from previous approval.
|
Routing - Addressing | 2/22/2016 | | 2/24/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - Design Review | 2/22/2016 | | 2/24/2016 | | PASS |
Josh Wilson
|
|
|
OK PER MODIFICATION DRH15-00313 JGW 2-24-16
|
Routing PW Sewer Rating | 2/22/2016 | | 2/24/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Plan resubmittals received | | | 2/17/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 12/17/2015 | | DONE |
Carl Westfall
|
|
|
Request approved by Jason Blais, Building Official. See attached document under BLD15-01118.
|
Routing PW Drainage | 9/21/2015 | | 9/21/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Route to Impact Fee Review | 8/27/2015 | 8/30/2015 | 8/28/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 8/27/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/27/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/22/2015 | | 8/26/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 7/22/2015 | | 8/19/2015 | | FAIL |
Carl Westfall
|
|
|
Dave Haugland
|
Routing PW Drainage | 7/23/2015 | | 8/6/2015 | | FAIL |
Jason C. Taylor
|
|
|
|
Routing PW Sewer Design | 7/23/2015 | | 8/6/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Sewer approved under separate Public Works project.
|
Routing - PLUMBING | 7/22/2015 | | 8/5/2015 | | FAIL |
Daryl Spivey
|
|
|
|
Routing PW Sewer Rating | 7/23/2015 | | 7/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - FIRE | 7/22/2015 | 7/22/2015 | 7/24/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Design Review | 7/22/2015 | | 7/23/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 7/22/2015 | | 7/23/2015 | | PASS |
Troy James
|
|
|
|
Routing PW Solid Waste | 7/23/2015 | | 7/23/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLANNING Land Div | 7/22/2015 | | 7/23/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 7/22/2015 | | 7/23/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 7/22/2015 | | 7/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 7/22/2015 | | 7/22/2015 | | PASS |
Andy J. Long
|
|
|
|
Pending Assignment by TLW | 7/22/2015 | | 7/22/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/20/2015 | | PASS |
|
|
|
|
Intake Approval | | | 6/25/2015 | | FAIL |
Carl Westfall
|
|
|
(6-23-15) Drawings submitted in ePlanReview.
(6-25-15) Please refer to the circled items on the plan intake checklist and resolve them as noted.
|
Application received | | | 4/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2015 3:20PM
|
First Notice | | 12/10/2017 | | | |
|
|
|
|
Routing PW Solid Waste | 10/10/2016 | | | | |
Evan Carpenter
|
|
|
|