Permit Information
Permit NumberBLD15-01151
StatusFinaled
Name VERTICAL CORP
Site Address 835 W FRONT ST
Project NameThe Aspen Lofts
Customer Number 
ePlanReviewYes
Description
(OPTIMUS MORTGAGE) (ASPEN BUILDING) For tenan improvements to an existing 1,378 sq. ft. tenant space with work to include the consruction of new interior nonbearing partition walls to create new office spaces, conference room and a breakroom areas. New lighting and mechanical is also being installed as well as related interior finishes. This building is fully fire sprinklered with afire alarm system because it is a high rise. Any alterations to the sprinkler system shal comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  12/4/2015 DONE
DetailsChristina Prado
Address correction
Second Notice 10/22/201510/20/2015 DONE
This permit finaled on the web by Todd Weltner
First Notice 9/28/201510/12/2015 DONE
Mailed 10-13-15
BLD-Final9/16/20159/17/20159/17/2015PPASS
DetailsTony Young
Please call Todd. Lockbox code is 0851 if door is locked. Phone #: ###-#### Inspection requested via web by Todd Weltner
FIRE-Final Inspection9/16/20159/17/20159/17/2015APASS
DetailsJim Page
Life fire safety passed/complete
BLD-Final9/15/20159/16/20159/15/2015PCANC
DetailsDave Hannah
Please call Todd. Lockbox code is 0851. Phone #: ###-#### >> Inspection requested via web by Todd Weltner Inspection cancelled from web by: Todd Weltner
FIRE-Final Inspection9/15/20159/16/20159/15/2015PCANC
DetailsJim Page
Please call Todd. Lockbox code is 0851. Phone #: ###-#### >> Inspection requested via web by Todd Weltner Inspection cancelled from web by: Todd Weltner
Plan Modification Accepted  7/30/2015 DONE
New M2.1 sheet with mechanical changes to conference room.
Routing - MECHANICAL7/30/2015 7/30/2015 PASS
DetailsTroy James
Approved new design for conference room M2.1 sheet.
BLD-Ceiling Grid Inspection7/17/20157/17/20157/17/2015PPASS
DetailsDave Hannah
If door is locked, please call for lockbox code. Phone #: ###-#### Inspection requested via web by Todd Weltner
BLD-Framing/Rough-in6/2/20156/3/20156/3/2015APASS
DetailsDave Hannah
Please call for lock code - Todd Phone #: ###-####
Plan assigned to (CDM)5/15/20155/15/20155/19/2015 PASS
DetailsCarl D Madsen
Plan Modification e plan Optimus Morgage
Routing - PLAN CHECK5/15/2015 5/19/2015 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  5/19/2015 DONE
CHANGE STATUS TO (ISS)  5/19/2015 DONE
Issue PAID IN FULL permit  5/12/2015 DONE
Print Occupancy Form  5/12/2015 DONE
Plan assigned to (CDM)4/14/20154/14/20154/22/2015 PASS
DetailsCarl D Madsen
Level 1 due 4/20 First review completed
Routing - PLAN CHECK4/22/2015 4/22/2015 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  4/22/2015 DONE
Permit Ready to Issue  4/22/2015 DONE
Need Revised Cert of Value and GC Form // all was emailed to KRS
Routing - PLAN CHECK4/14/2015 4/16/2015 FAIL
DetailsCarl D Madsen
1st review completed  4/16/2015 FAIL
Routing - PUBLIC WORKS4/14/2015 4/15/2015 PASS
DetailsJennifer Bruner
Routing PW Sewer Rating4/15/2015 4/15/2015 PASS
DetailsJennifer Bruner
Intake Approval  4/14/2015 PASS
DetailsAdele J Schaffeld-Griffin
Routing - Addressing4/14/2015 4/14/2015 PASS
DetailsEmily Dixon
Suite 108 added.
Intake Approval  4/13/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Please have the owner sign the #304 form.
The cover sheet of the drawings with the code analysis needs to be stamped and singed just like the rest of the drawings.
Application received  4/10/2015 DONE
Application submitted via PDS Online on Apr 10 2015 2:06PM