Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-01181
StatusFinaled
Name CSF MAINTENANCE LLC
Site Address 350 N MILWAUKEE ST
Project NameBTS Space 2070 - AT&T Store
Customer Number 
ePlanReviewYes
Description
(AT&T)(BOISE TOWNE SQUARE - SPACE 2070) Interior remodel for new retail tenant within the Boise Towne Square Mall per approved plans. Scope of work to include minor demolition as shown on the approved plans. A new store front will be constructed with tempered glazing independent of the existing bulkhead. New interior finish shall be per IBC chapter 8. New ceiling grid with mechanical and lighting also included in the scope of this project. This facility includes an engineered smoke control system throughout the mall. Any modifications to smoke and/or fire dampers shall be reviewed and approved by the mall engineer. Modifications to the building fire protection systems will require separate permits. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.***ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 9/25/20159/21/2015 DONE
This permit finaled on the web by matthew greenman
First Notice 9/5/20159/15/2015 DONE
Mailed 9/16/15
Permanent Occupancy  8/26/2015 DONE
BLD-Final8/11/20158/12/20158/12/2015PPASS
DetailsMike Jordan
Please call for access.
Thanks Phone #: ###-#### Inspection requested via web by matthew greenman. OK for perm occ. No mech. work. Ceiling grid and diffusers remained in place.
FIRE-Final Inspection8/11/20158/12/20158/12/2015APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection8/10/20158/11/20158/11/2015ACANC
DetailsKatie Marron
Rescheduled in order to have personnel on site to test smoke evacuation system. Also bathroom door handle to be changed to lever.

BLD-Final8/10/20158/11/20158/11/2015PCANC
DetailsMike Jordan
Please call for access

Thanks Phone #: ###-#### >> Inspection requested via web by matthew greenman Inspection cancelled from web by: matthew greenman
BLD-Framing/Rough-in7/15/20157/16/20157/16/2015APASS
DetailsMike Jordan
Please call for access
thanks Phone #: ###-#### Inspection requested via web by matthew greenman
BLD-Framing/Rough-in7/8/20157/9/20157/9/2015ANR
DetailsMike Jordan
Please call prior for access
thanks Phone #: ###-#### Inspection requested via web by matthew greenman. Needs electrical rough in forst.
Print Occupancy Form  6/18/2015 DONE
Issue PAID IN FULL permit  6/17/2015 DONE
Print Occupancy Form  6/17/2015 DONE
Plan assigned to (AJS)5/6/20155/6/20156/5/2015 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Level 3 TI - ePlanReview - AT&T in Mall
Routing - PLAN CHECK6/3/2015 6/5/2015 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  6/5/2015 DONE
Permit Ready to Issue  6/5/2015 DONE
DetailsChristina Prado
Need G.C. form

All requirements met
Routing - PLAN CHECK5/6/2015 5/19/2015 FAIL
DetailsAdele J Schaffeld-Griffin
1st review completed  5/19/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE5/6/20155/6/20155/13/2015 PASS
DetailsScott Arellano
Attached comments to plans.
Intake Approval  5/6/2015 PASS
DetailsJason Blais
Prescreen approved by Sam Zahorka and plan review fees paid.
Pending Assignment by JCB5/6/2015 5/6/2015 DONE
DetailsJason Blais
Intake Approval  4/21/2015 FAIL
DetailsSam Zahorka
Plan Reviewer's activity  4/21/2015 DONE
DetailsSam Zahorka
Please provide the following information:

1. Please provide the #520 - Major Tenant Improvement Submittal Checklist. This checklist must be completed. This checklist not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed. (Note: Additional missing items might be identified once this checklist is provided.)

2. Please re-upload all documents and drawings sheets idividually. Please place the documents in the documents folder and the drawings in the drawings folder.

3. Please see the File naming Standards and rename sheets.

See - http://pds.cityofboise.org/media/105041/electronicstandards.pdf

4. Please provide a 4"X4" blank space located 3" off the lower right hand corner for the City approval stamp on the Cover Sheet.

5. Please provide a 4"X2" blank space located 3" off the lower right hand corner for the City approval stamp on the drawing Sheets.

6. Please provide form #304 Registered Design Professional Form.

7. This is not an all-inclusive Pre-Screen Review. Additional missing items might not be listed here. I have tried my best to indentify all needed items without the Plan Intake Submittal Checklist be submitted.

If assistance is needed please call me directly at ###-####. Thanks Sam Zahorka
Application received  4/14/2015 DONE
Application submitted via PDS Online on Apr 14 2015 1:31PM