Third Notice | | 1/17/2016 | 1/17/2016 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Barber
|
Second Notice | | 12/20/2015 | 1/12/2016 | | DONE |
|
|
|
mailed 1-13-16
|
First Notice | | 11/30/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
BLD-Final | 11/20/2015 | 11/20/2015 | 11/20/2015 | P | PASS |
Tony Young
|
|
|
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
Permanent Occupancy | | | 11/20/2015 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/19/2015 | 11/19/2015 | 11/19/2015 | P | PASS |
Jim Page
|
|
|
No fire sprinklers associated with this project, no fire alarms associated with this project. Life fire safety inspection passed/complete.
|
Zoning Approval | 11/19/2015 | 11/19/2015 | 11/19/2015 | | PASS |
Josh Wilson
|
|
|
|
BLD-Energy code compliance | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Jim Sly
|
|
|
Jody Phone #: ###-####
|
BLD-Framing/Rough-in | 9/15/2015 | 9/15/2015 | 9/15/2015 | A | PART |
Phil Shearer
|
|
|
Review stairs and handrail oprions. Please call Nic half an hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen. Interior nonbearing walls
|
BLD-Framing/Rough-in | 9/11/2015 | 9/11/2015 | 9/11/2015 | P | PART |
Jim Storey
|
|
|
Framing Inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen interior sheer nailling ok/ stair rise and run not corect/
|
BLD-Framing/Rough-in | 9/2/2015 | 9/2/2015 | 9/3/2015 | P | PASS |
Dave Hannah
|
|
|
Shear wall inspection in gym. Please call Nic half hour before inspection. Prefer late pm if possible. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Footing | 8/5/2015 | 8/5/2015 | 8/6/2015 | P | PART |
Dave Hannah
|
|
|
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen ok after mti spec inspection sign off
|
BLD-Footing | 7/23/2015 | 7/24/2015 | 7/24/2015 | P | PEND |
Dave Hannah
|
|
|
rebar, 2:00PM pour time; Chris Phone #: ###-#### ok after spec inspection signs off
|
Issue PAID IN FULL permit | | | 7/6/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/6/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 6/3/2015 | | |
|
|
|
|
OVERRIDE | | | 6/3/2015 | | |
|
|
|
|
CHANGE STATUS TO (FEE) | | | 6/3/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/3/2015 | | DONE |
Christina Prado
|
|
|
All requirements met////
Need G.C. form, Responsible Person, & Revised Certificate of Value
|
Routing - PLAN CHECK | 6/2/2015 | | 6/3/2015 | | PASS |
Carl Westfall
|
|
|
Beam analysis provided. Drawings approved with redlines
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/16/2015 | | 6/3/2015 | | PASS |
Carl Westfall
|
|
|
WHITEWATER CLUBHOUSE REMODEL (15 days - May 4) Level 3 - ePlan
|
Routing - PLAN CHECK | 6/1/2015 | | 6/2/2015 | | FAIL |
Carl Westfall
|
|
|
Emailed Matt Rhees, Architect. Hope to resolve this without failing the 3rd review. Need an analysis of a beam that represents the actual conditons.
|
Plan resubmittals received | | | 6/1/2015 | | DONE |
|
|
|
|
Telephone call | | | 5/22/2015 | | DONE |
|
|
|
Called the Architect. Decided to add a changemark and send the work flow back to the Architect.
|
Plan resubmittals requested | | | 5/22/2015 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/19/2015 | | 5/21/2015 | | PASS |
Troy James
|
|
|
|
Telephone call | | | 5/19/2015 | | DONE |
|
|
|
Called the Engineer of Record to discuss the 2 remaining items. Thought they would be resolved quickly and without further discussion so no changemarks were added. On 5-22-15 decided to add a changemark and send the work flow back to the Architect.
|
Routing - PLAN CHECK | 5/19/2015 | | 5/19/2015 | | FAIL |
Carl Westfall
|
|
|
Two structural items still need to be resolved.
|
Plan resubmittals received | | | 5/18/2015 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/8/2015 | 5/11/2015 | 5/12/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 5/8/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/8/2015 | | DONE |
|
|
|
|
Routing - FIRE | 4/16/2015 | | 5/6/2015 | | PASS |
Scott Arellano
|
|
|
Attached Fire Code comments to plans.
|
Routing - PLAN CHECK | 4/16/2015 | | 5/5/2015 | | FAIL |
Carl Westfall
|
|
|
See the plan review report
|
Routing - MECHANICAL | 4/16/2015 | | 4/22/2015 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - Erosion and Sediment | 4/16/2015 | | 4/20/2015 | | PASS |
Evan Jenkins
|
|
|
Remodel and addition to an existing apartment complex clubhouse. T.I including removal of concrete, demo parts of building, addition of new sidewalk.
|
Routing - PUBLIC WORKS | 4/16/2015 | | 4/17/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 4/16/2015 | | 4/17/2015 | | PASS |
Josh Wilson
|
|
|
|
Pending Assignment by JCB | 4/15/2015 | | 4/16/2015 | | DONE |
Carl Westfall
|
|
|
|
Routing - Addressing | 4/16/2015 | | 4/16/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 4/15/2015 | | PASS |
Carl D Madsen
|
|
|
Plan intake by Carl Madsen
|
Application received | | | 4/14/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 14 2015 4:28PM
|