First Notice | 2/9/2016 | 2/9/2016 | 2/12/2016 | | DONE |
Mike Jordan
|
|
|
sent with mail 2-16-16
|
Letter of compliance/Occupancy | | | 2/11/2016 | | DONE |
|
|
|
|
BLD-Final | 2/9/2016 | 2/9/2016 | 2/9/2016 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 2/9/2016 | 2/9/2016 | 2/9/2016 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 2/9/2016 | 2/9/2016 | 2/9/2016 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 2/8/2016 | 2/9/2016 | 2/9/2016 | A | CANC |
Mike Jordan
|
|
|
Please call ahead for access, Dave has plans in hand - Dave Phone #: ###-####. Moved to pm.
|
FIRE-Final Inspection | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Tyler Hildebrand Inspection cancelled from web by: Tyler Hildebrand
|
BLD-Final | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | CANC |
Mike Jordan
|
|
|
Carport Final Phone #: ###-#### >> Inspection requested via web by Tyler Hildebrand Inspection cancelled from web by: Tyler Hildebrand
|
BLD-Wall Bracing | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-#### Last 4 holes ......OK See previous inspection comments.
|
BLD-Foundation | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PART |
Mike Jordan
|
|
|
Rebar // Dave Phone #: ###-####. No plans or new engineering on site. Per Bob Archibald, allowed concrete to be placed, but engineering will be required prior to final inspection. Footings were approx. 4ft.x4ft. 34inches to 42 inches deep with two mats of 4#5 rebar each way.
|
BLD-Foundation | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PART |
Mike Jordan
|
|
|
rebar; Dave Phone #: ###-####. No plans or new engineering on site. Per Bob Archibald, allowed concrete to be placed, but engineering will be required prior to final inspection. Footings were approx. 4ft.x4ft. 34inches to 42 inches deep with two mats of 4#5 rebar each way.
|
BLD-Foundation | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | FAIL |
Mike Jordan
|
|
|
Rebar // Dave Phone #: ###-####. Holes not ready, will need to submit new engineering to city for approval for change in supplier.
|
BLD-Footing | 7/28/2015 | 7/28/2015 | 7/28/2015 | P | PASS |
Mike Jordan
|
|
|
Ken Phone #: ###-####
|
BLD-Footing | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/4/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 6/4/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/1/2015 | | |
|
|
|
|
Route to Impact Fee Review | 5/30/2015 | 6/2/2015 | 6/1/2015 | | PASS |
Cindy M. Gould
|
|
|
no impact fees cmg
|
Plan assigned to (CDM) | 4/27/2015 | 4/27/2015 | 6/1/2015 | | PASS |
Carl D Madsen
|
|
|
new due 5/21
|
Routing - PLAN CHECK | 6/1/2015 | | 6/1/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2015 | | DONE |
|
|
|
need RP, GC & rev cert of val
|
1st review completed | | | 5/30/2015 | | FAIL |
|
|
|
The uploaded plans are not legible or scalable in their current format.
|
Routing - PLAN CHECK | 4/21/2015 | | 5/30/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Solid Waste | 4/21/2015 | | 4/28/2015 | | PASS |
Megan Durrell
|
|
|
|
Plan assigned to (SRZ) | 4/21/2015 | | 4/27/2015 | | DEFR |
Carl D Madsen
|
|
|
|
Routing - FIRE | 4/21/2015 | | 4/24/2015 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. No separate comments attached.
|
Routing PW Drainage | 4/21/2015 | | 4/22/2015 | | PASS |
Brian Murphy
|
|
|
appreved bunder previous pemit
|
Routing - Erosion and Sediment | 4/21/2015 | | 4/22/2015 | | PASS |
Evan Jenkins
|
|
|
(CANTABRIA APARTMENTS - (22)4 Stall Carport) Permit is to install 22 new 4 stall carports on one parcel of land.
|
Plans ACCEPTED BY PLAN CHECK | | | 4/21/2015 | | DONE |
|
|
|
|
Routing - Addressing | 4/21/2015 | | 4/21/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/21/2015 | | 4/21/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 4/21/2015 | | 4/21/2015 | | PASS |
Andrea Tuning
|
|
|
DRH15-00111
|
Application received | | | 4/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2015 9:18AM
|
Intake Approval | | | 4/16/2015 | | PASS |
John Menard
|
|
|
|