BLD-Final | 11/23/2015 | 11/23/2015 | 11/23/2015 | A | PASS |
Phil Shearer
|
|
|
Please call for access If locked ###-#### Inspection requested via web by Erby Gonzales
|
DOC - Permit Finaled | 11/23/2015 | 11/23/2015 | 11/23/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Wall cover | 9/8/2015 | 9/8/2015 | 9/8/2015 | P | PASS |
Phil Shearer
|
|
|
Wuii inspection drywall at soffits Inspection requested via web by Erby Gonzales
|
BLD-Energy code compliance | 9/3/2015 | 9/3/2015 | 9/3/2015 | P | PASS |
Phil Shearer
|
|
|
Inspection requested via web by Erby Gonzales
|
BLD-Framing/Rough-in | 9/3/2015 | 9/3/2015 | 9/3/2015 | P | PASS |
Phil Shearer
|
|
|
Inspection requested via web by Erby Gonzales
|
BLD-Framing/Rough-in | 8/31/2015 | 9/1/2015 | 9/1/2015 | P | PART |
Phil Shearer
|
|
|
Truss bracing F8
|
BLD-Framing/Rough-in | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | CANC |
Phil Shearer
|
|
|
Plans on site ###-#### >> Inspection requested via web by Erby Gonzales Inspection cancelled from web by: Erby Gonzales
|
BLD-Wall Bracing | 8/17/2015 | 8/17/2015 | 8/17/2015 | A | PASS |
Phil Shearer
|
|
|
Shear inspect, plans on site Inspection requested via web by Erby Gonzales
|
BLD-Foundation | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
BLD-Footing | 6/26/2015 | 6/29/2015 | 6/29/2015 | A | PASS |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
BLD-Footing | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | NR |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
BLD-Footing | 6/16/2015 | 6/16/2015 | 6/16/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 5/27/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 5/7/2015 | | |
|
|
|
|
Plan assigned to (JG) | | 4/22/2015 | 5/7/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 5/04 M L1** Pending PW and Flood
|
Inspection Record Card- Bld | | | 5/7/2015 | | DONE |
|
|
|
|
Telephone call | | | 5/7/2015 | | DONE |
|
|
|
called Seth- told him permit is ready for pick up and fees due
|
Routing - PUBLIC WORKS | 5/6/2015 | | 5/7/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLAN CHECK | 5/7/2015 | | 5/7/2015 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 5/7/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/7/2015 | | DONE |
|
|
|
requirements met
|
Routing PW Flood Plain | 5/6/2015 | | 5/6/2015 | | PASS |
Jason C. Taylor
|
|
|
Project approved. JCT
|
Routing - PLAN CHECK | 4/28/2015 | | 5/1/2015 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 5/1/2015 | | FAIL |
|
|
|
Pending PW and Flood
|
Routing - MECHANICAL | 4/23/2015 | | 4/28/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/23/2015 | | 4/23/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/22/2015 | | 4/23/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 4/23/2015 | | 4/23/2015 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jason Taylor for flood plains issues.
|
Routing PW Flood Plain | 4/23/2015 | | 4/23/2015 | | FAIL |
Jason C. Taylor
|
|
|
Cannot approve project until subdivision grading and drainage is completed. Jason Talyor ###-####.
|
Plans ACCEPTED BY PLAN TECH | | | 4/22/2015 | | DONE |
|
|
|
|
Intake Approval | | | 4/22/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/22/2015 | | DONE |
|
|
|
|
Application received | | 4/22/2015 | | | |
|
|
|
|