Permanent Occupancy | | | 5/5/2015 | | DONE |
|
|
|
|
BLD-Final | 5/1/2015 | 5/4/2015 | 5/4/2015 | A | PASS |
Jim Storey
|
|
|
Phillip Phone #: ###-####-please call for access
|
FIRE-Final Inspection | 5/4/2015 | 5/5/2015 | 5/4/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 4/30/2015 | 5/1/2015 | 5/4/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguishers as discussed for both buildings. Provide single action hardware as marked on the plans and discussed (per the plans one exit required from each area). Provide sticker and remove the thumbturn deadbolt from the main exit.
|
BLD-Final | 4/30/2015 | 5/1/2015 | 5/1/2015 | P | CANC |
Phil Shearer
|
|
|
Phillip Phone #: ###-####-please call for access
|
Routing - FIRE | 4/29/2015 | 4/29/2015 | 4/30/2015 | | PASS |
Scott Arellano
|
|
|
No comments attached. Not approved for any high piled combustible storage.
|
Plan assigned to (CDM) | 4/27/2015 | 4/27/2015 | 4/30/2015 | | PASS |
Carl D Madsen
|
|
|
Occupancy due May 1st
|
Routing - PLAN CHECK | 4/30/2015 | | 4/30/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 4/30/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/30/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/30/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/30/2015 | | DONE |
|
|
|
|
Telephone call | | | 4/30/2015 | | DONE |
|
|
|
called Phillip to let know permit is ready
|
Issue PAID IN FULL permit | | | 4/30/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/27/2015 | | 4/29/2015 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 4/29/2015 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/27/2015 | | DONE |
|
|
|
|
Intake Approval | | | 4/27/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/27/2015 | | DONE |
|
|
|
|
First Notice | | 5/15/2015 | | | |
|
|
|
|
Application received | | 4/27/2015 | | | |
|
|
|
|