First Notice | | 4/28/2016 | 5/11/2016 | | DONE |
|
|
|
mailed 5-11-16
|
BLD-Final | 4/15/2016 | 4/18/2016 | 4/18/2016 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
Permanent Occupancy | | | 4/18/2016 | | DONE |
|
|
|
|
Telephone call | | | 4/18/2016 | | DONE |
|
|
|
called Jim to see if i could mail the C of O to him since the temp c of o was expired but all inspections were done-emailed it to jkboyd44@gmail.com
|
Zoning Approval | 4/15/2016 | 4/15/2016 | 4/15/2016 | | DONE |
Andrea Tuning
|
|
|
|
Telephone call | | | 4/5/2016 | | DONE |
|
|
|
called John to let know temp c of o will expire on 4/17/16. He said he would email Jason if he's not reaqdy for the final by then
|
BLD-Aging Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 | | NR |
Jim Storey
|
|
|
pending p&z
|
Temporary Occupancy | 1/14/2016 | 4/13/2016 | 1/14/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 1/11/2016 | | DONE |
|
|
|
called John to let know temp c of o wil expire on 10-16-16
|
BLD-Aging Inspection | 12/22/2015 | 12/22/2015 | 12/22/2015 | | NR |
Jim Storey
|
|
|
pending p&z
|
Temporary Occupancy | 10/27/2015 | 1/25/2016 | 10/27/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 10/26/2015 | | DONE |
|
|
|
John called and said he thought he was ok for another 30 days on his temp c of o. John said both Andrea T and Jim Storey said he could have an additional 30 days
|
Telephone call | | | 10/22/2015 | | DONE |
|
|
|
calledJohn to let know they still need an extension letter for the temp c of o. the final is a partial but the temp expired on the 18th of Oct-left message on his phone
|
BLD-Final | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | PART |
Jim Storey
|
|
|
Jim Phone #: ###-#### tactale signage required/ landscaping in the works with sharh in p&z.
|
Zoning Approval Temp | 10/19/2015 | 10/19/2015 | 10/19/2015 | | DONE |
Andrea Tuning
|
|
|
Temporary occupancy was originally given for 90 days. An extension to the temporary occupancy has been granted to allow the school have temporary occupancy until November 20, 2015. The applicant still has not completed the landscaping along the north property line.
|
Telephone call | | | 10/15/2015 | | DONE |
|
|
|
called John @ ###-#### to let know that the temp c of o expires in 3 days and they need to call in final or request an extension-left message on his phone
|
BLD-Aging Inspection | 9/16/2015 | 9/16/2015 | 9/16/2015 | | NR |
Jim Storey
|
|
|
no requist for insp.
|
BLD-Final | 7/17/2015 | 7/20/2015 | 7/20/2015 | P | PART |
Dave Hannah
|
|
|
Don Phone #: ###-#### ok for temp occ needs to finish installing door hardwear.ada signage on restrooms and path ada landging at front door
|
FIRE-Final Inspection | 7/17/2015 | 7/20/2015 | 7/20/2015 | A | PASS |
Jim Page
|
|
|
Previously noted items corrected, approved drawings with small documents on site, discharge egress lights installed, Life fire safety passed/complete
|
Temporary Occupancy | 7/20/2015 | 10/18/2015 | 7/20/2015 | | DONE |
Brittany Hill
|
|
|
|
Zoning Approval Temp | 7/20/2015 | 7/20/2015 | 7/20/2015 | | DONE |
Andrea Tuning
|
|
|
Temporary occupancy has been given for 90 days. The applicant still has not completed the landscaping along the north property line. They have been given temporary occupancy in order to allow them to open while they continue to work with the City to get an appropriate landscaping within the landscape buffer on the north side of the property.
|
FIRE-Final Inspection | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | FAIL |
Jim Page
|
|
|
City approved drawings/small documents not on job site, designated exit discharge areas do not have emergency egress illumination, needs to be installed.
|
FIRE-Final Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with project point of conact, John Phone #: ###-####. Flooring being installed, would not have access to areas until flooring done, will reschedule for later date.
|
BLD-Energy code compliance | 6/15/2015 | 6/15/2015 | 6/15/2015 | P | PASS |
Mike Jordan
|
|
|
Insulation // John Phone #: ###-####
|
BLD-Framing/Rough-in | 6/11/2015 | 6/12/2015 | 6/12/2015 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Footing | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/21/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/21/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/21/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 5/20/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 5/4/2015 | 5/4/2015 | 5/20/2015 | | PASS |
Carl Westfall
|
|
|
IKASTOLA PRESCHOOL (May 21 - 15 days) Level 3 TI - ePlan (wants to be open by June 23)
|
Routing - PLANNING | 5/14/2015 | | 5/20/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 5/14/2015 | | 5/20/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
IKASTOLA PRESCHOOL – CONVERT HOUSE TO CHILDCARE) This building does not have a fire sprinkler system. To convert an existing 1,495 square foot single family dwelling into a commercial childcare facility. Children that are 2.5 years of age or less are allowed only in the room having exterior doors directly to the outside. Interior demolition is also covered under this permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/20/2015 | | DONE |
Christina Prado
|
|
|
Need ACHD, GC, RP & Revised Certificate of Value for issuance. ALL REQUIREMENTS MET BLH 5-21-15 PDF
|
Plan resubmittals received | | | 5/14/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/14/2015 | | 5/14/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Routing - FIRE | 5/4/2015 | 5/4/2015 | 5/13/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 5/13/2015 | | DONE |
|
|
|
ESC, Planning, Plan Check
|
Plan resubmittals requested | | | 5/13/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/4/2015 | | 5/8/2015 | | FAIL |
Carl Westfall
|
|
|
Structural concerns.
|
Routing - PLANNING | 5/4/2015 | | 5/6/2015 | | FAIL |
Todd Tucker
|
|
|
The drive aisle must be setback a minimum of 5 feet from the north property line as per the approved CUP Site Plan and the Development Code.
|
Routing - Addressing | 5/4/2015 | | 5/5/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 5/4/2015 | | 5/5/2015 | | FAIL |
Evan Jenkins
|
|
|
Erosion & Sediment Control Narrative Required per BCC 8-17
Evan Jenkins 794.3958
|
Routing PW Drainage | 5/4/2015 | | 5/5/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 5/4/2015 | | 5/5/2015 | | PASS |
Mike D Hedge
|
|
|
No street lighting required.
|
Routing PW Sewer Rating | 5/4/2015 | | 5/5/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Reviewer's activity | | | 5/4/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to have him contact ACHD for evaluation of any impact fees due. Our Permit Counter will need written verification from ACHD prior to the building permit being issued.
|
Routing - PUBLIC WORKS | 5/4/2015 | | 5/4/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 5/4/2015 | | 5/4/2015 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH15-00087
|
Pending Assignment by JCB | 5/4/2015 | | 5/4/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/1/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Javier Guzman and plan review fees paid.
|
Application received | | | 4/27/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2015 4:30PM
|