Second Notice | | 5/21/2016 | 6/14/2016 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
First Notice | 4/19/2016 | 4/19/2016 | 5/11/2016 | | DONE |
Mike Jordan
|
|
|
Mailed 5-12-16
|
BLD-Final | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/18/2016 | 4/19/2016 | 4/19/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue. All framing issues have been resolved.
|
BLD-Final | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | NR |
Mike Jordan
|
|
|
Shell Final Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Framing/Rough-in | 3/31/2016 | 3/31/2016 | 3/31/2016 | A | FAIL |
Mike Jordan
|
|
|
Shell Final Phone #: ###-#### Inspection requested via web by Mike McHargue. Nail off 2ply T17 trusses as per the truss engineering. Install all bearing blocks as shown on truss engineering. Noted anchor bolts on base plates for columns not long enough. Also noted thru bolts on beam to beam and beam to column connections are not long enough.
|
FIRE-Final Inspection | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 3/29/2016 | 3/30/2016 | 3/29/2016 | A | CANC |
Troy Cobbley
|
|
|
Retail Building 01 Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
|
PubWorks Occupancy Approval | 3/21/2016 | 3/21/2016 | 3/21/2016 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Wall Bracing | 10/21/2015 | 10/22/2015 | 10/22/2015 | P | PASS |
Mike Jordan
|
|
|
Sheer Phone #: ###-#### Inspection requested via web by Mike McHargue. Exterior shear walls and roof diaphragm ok.
|
BLD-Energy code compliance | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PASS |
Mike Jordan
|
|
|
Foundation Insulation Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | NR |
Mike Jordan
|
|
|
Late PM if possible for foundation insulation inspection. Phone #: ###-#### Inspection requested via web by Mike McHargue. Will reschedule for inspection tomorrow.
|
BLD-Foundation | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 8/10/2015 | 8/11/2015 | 8/11/2015 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/30/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/30/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 7/22/2015 | | |
|
|
|
|
Routing - FIRE | 7/22/2015 | 7/22/2015 | 7/22/2015 | | PASS |
Katie Marron
|
|
|
All resubmittals items addressed satisfactory. Revised report attached to case.
|
Routing - PLAN CHECK | 7/22/2015 | | 7/22/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/22/2015 | | DONE |
|
|
|
need GC, rev cert of val, RP & ACHD--- only need ACHD
|
Routing - PLAN CHECK | 7/9/2015 | | 7/22/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 5/6/2015 | | 7/22/2015 | | PASS |
Tim L. Woodard
|
|
|
1st Review Complete
|
Routing PW Sewer Design | 7/9/2015 | | 7/14/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - FIRE | 7/9/2015 | | 7/9/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to case and emailed to architect.
|
Routing - PUBLIC WORKS GRADING | 7/9/2015 | | 7/9/2015 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 7/9/2015 | | DONE |
|
|
|
|
Routing - Design Review | 7/9/2015 | | 7/9/2015 | | PASS |
Josh Wilson
|
|
|
|
Route to Impact Fee Review | 5/28/2015 | 5/31/2015 | 5/29/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 5/6/2015 | | 5/28/2015 | | FAIL |
Tim L. Woodard
|
|
|
Corrections noted as changemarks in E-Plan Review. TLW
|
Routing - Design Review | 5/6/2015 | | 5/28/2015 | | PASS |
Josh Wilson
|
|
|
Approved in E-Plan Review. TLW
|
Routing Off Site - STRUCTURAL | 5/6/2015 | | 5/28/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Drainage | 5/6/2015 | | 5/28/2015 | | FAIL |
Brian Murphy
|
|
|
3rd seepage bed new swale. Failed in E-Plan Review. TLW
|
Routing PW Solid Waste | 5/6/2015 | | 5/28/2015 | | PASS |
Peter J. McCullough
|
|
|
Approved in E-Plan Review. TLW
|
1st review completed | | | 5/28/2015 | | DONE |
|
|
|
|
Routing - FIRE | 5/6/2015 | | 5/18/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed and faxed architect plan review report. Attached report to case.
|
Routing PW Sewer Design | 5/6/2015 | | 5/8/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Submit request to vacate sewer easement for abandonment of existing line. If an existing sewer service is replaced to the main, contractor shall contact Boise Public works 48 hours prior to sewer work schedule inspection.
|
Routing - Erosion and Sediment | 5/6/2015 | | 5/7/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval required prior to earth disturbance)
New Shell and Core Building (Commercial) with utilities
|
Routing PW Street Lights | 5/6/2015 | | 5/7/2015 | | PASS |
Mike D Hedge
|
|
|
No street lighting required.
|
Routing - PLANNING Land Div | 5/6/2015 | | 5/7/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLUMBING | 5/6/2015 | | 5/6/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 5/6/2015 | | 5/6/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2015 | | 5/6/2015 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 5/6/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/6/2015 | | 5/6/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 5/6/2015 | | 5/6/2015 | | PASS |
Beverly Mountain
|
|
|
no plumbing
|
Intake Approval | | | 5/4/2015 | | FAIL |
|
|
|
Please provide the site drainage and O&M (See the attached changemarks on the checklist).
|
Application received | | | 4/28/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 28 2015 3:17PM
|