Second Notice | | 12/20/2015 | 1/5/2016 | | DONE |
|
|
|
|
Print Statement | | | 1/5/2016 | | DONE |
|
|
|
|
First Notice | | 11/13/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
Permanent Occupancy | | | 11/3/2015 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/2/2015 | 11/2/2015 | 11/2/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 9/15/2015 | 9/16/2015 | 9/16/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Snow card on site
|
BLD-Final | 9/14/2015 | 9/14/2015 | 9/14/2015 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Snow need health dept sign off
|
BLD-Conference | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | PASS |
Jim Storey
|
|
|
Request framing inspection for new restroom ceiling drywall lid. Phone #: ###-#### Inspection requested via web by Ron Hack
|
BLD-Conference | 7/19/2015 | 7/20/2015 | 7/20/2015 | P | PASS |
Jim Storey
|
|
|
Rough inspection on wall framing for consult room. Would like to request last inspection of the day as our shift does not start until 10 pm.
Thanks, Ron Hack/ESI Phone #: ###-#### Inspection requested via web by Ron Hack
|
BLD-Conference | 7/16/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Jim Storey
|
|
|
Request frame inspection for new bathroom/consult room as per plan modification. Need to inspect so sales floor side of wall can be finished where the general public is. Working overnights, would like to request inspection as early as possible. Thanks, Ron Hack Superintendent. Phone #: ###-#### Inspection requested via web by Ron Hack
|
CHANGE STATUS TO (ISS) | | | 7/15/2015 | | DONE |
Christina Prado
|
|
|
plan mod fees paid, sewer permit uploaded into eplan
|
Plan assigned to (CDM) | 7/2/2015 | 7/2/2015 | 7/7/2015 | | PASS |
Carl D Madsen
|
|
|
Plan Mod - Rite-Aid
|
Routing - PLAN CHECK | 7/2/2015 | | 7/7/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/7/2015 | | DONE |
|
|
|
DO NOT ISSUE AGAIN; plan mod fees due
|
Routing - PUBLIC WORKS | 7/2/2015 | | 7/6/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 7/6/2015 | | 7/6/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 7/2/2015 | | 7/2/2015 | | PASS |
Emily Dixon
|
|
|
|
Plan Modification Accepted | | | 7/2/2015 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 7/2/2015 | | DONE |
|
|
|
per architect new plans for bathroom
|
BLD-Conference | 6/10/2015 | 6/10/2015 | 6/10/2015 | A | PASS |
Jim Storey
|
|
|
Request for frame inspection for demising wall. We are working overnight shifts, please schedule as early in the morning as possible.
Thanks, Ron Hack/ ESI ###-#### Phone #: ###-#### Inspection requested via web by Ron Hack dimizing wall ok pending ele
|
BLD-Conference | 6/6/2015 | 6/8/2015 | 6/8/2015 | A | PART |
Jim Storey
|
|
|
Working over night shifts on this project. If at all possible could inspections be scheduled as early as possible. Would like to schedule rough frame inspection for new consultation room.
Ron Hack/ESI ###-#### Phone #: ###-#### Inspection requested via web by Ron Hack framing ok conf rm pending ele demizing wall ok
|
Issue PAID IN FULL permit | | | 6/3/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/3/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 5/4/2015 | 5/4/2015 | 5/21/2015 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - Rite-Aid First review completed
|
Routing - PLAN CHECK | 5/21/2015 | | 5/21/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/21/2015 | | DONE |
|
|
|
Need G.C. form and certificate of value
|
1st review completed | | | 5/20/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/4/2015 | | 5/20/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 5/4/2015 | 5/4/2015 | 5/13/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - Addressing | 5/4/2015 | | 5/5/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/4/2015 | | 5/5/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 5/4/2015 | | PASS |
|
|
|
|
Pending Assignment by JCB | 5/4/2015 | | 5/4/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 4/29/2015 | | FAIL |
|
|
|
Please provide the form 520 checklist with all applicable items.
|
Intake Approval | | | 4/29/2015 | | FAIL |
|
|
|
Please see the changemarks on the checklist.
|
Application received | | 4/29/2015 | | | |
|
|
|
|