First Notice | | 7/17/2015 | 7/15/2015 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
BLD-Final | 7/7/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 7/7/2015 | 7/7/2015 | 7/7/2015 | A | CANC |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 7/7/2015 | | DONE |
|
|
|
|
BLD-Final | 7/1/2015 | 7/2/2015 | 7/2/2015 | P | PART |
Mike Jordan
|
|
|
Phone #: 2089571618 >> Inspection requested via mobile web by Todd Landvatter. Ok for temp oc. Will be ok for perm occ. once fire/life/safety signs perm. Floor plan on existing portion does not match current approved plan.
|
FIRE-Final Inspection | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy for life safety is ok per scott until the revised plan has been approved.
|
FIRE-Final Inspection | 6/30/2015 | 7/1/2015 | 7/1/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide address, provide single action hardware on the north east door, repair both new emergency lights, provide exit sign at corridor as per the approved plans, provide revised floor plans that match the field conditions.
|
BLD-Framing/Rough-in | 6/16/2015 | 6/17/2015 | 6/17/2015 | P | PASS |
Mike Jordan
|
|
|
Todd Phone #: ###-####. Interior steel stud framed walls ok
|
Issue PAID IN FULL permit | | | 5/28/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/28/2015 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/6/2015 | 5/6/2015 | 5/27/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, A Better Pet TI - Pending Mech
|
Routing - MECHANICAL | 5/27/2015 | | 5/27/2015 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/27/2015 | | DONE |
|
|
|
NEED GC form- applicant is GC
|
Routing - MECHANICAL | 5/8/2015 | | 5/8/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLAN CHECK | 5/6/2015 | | 5/7/2015 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 5/7/2015 | | FAIL |
Javier Guzman
|
|
|
Mech
|
Routing - MECHANICAL | 5/6/2015 | | 5/6/2015 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 5/6/2015 | | 5/6/2015 | | PASS |
Emily Dixon
|
|
|
Address changed to 2707 S Saturn Way, 5/6/2015
|
Routing - PUBLIC WORKS | 5/6/2015 | | 5/6/2015 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 5/6/2015 | | PASS |
|
|
|
|
Intake Approval | | | 5/1/2015 | | FAIL |
Javier Guzman
|
|
|
See changemarks for corrections
|
Application received | | | 4/29/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 29 2015 3:02PM
|