BLD-Aging Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | | PASS |
Jim Storey
|
|
|
wip for ceilling flame spread isue.
|
Extend Permit 90/180 days | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Jim Storey
|
|
|
wip for ceilling flame spread isue.
|
BLD-Aging Inspection | 3/8/2019 | 3/8/2019 | 3/8/2019 | | PASS |
Jim Storey
|
|
|
ncfi
|
BLD-Aging Inspection | 3/7/2019 | 3/7/2019 | 3/8/2019 | | PASS |
Jim Storey
|
|
|
ncfi
|
BLD-Final | 10/23/2018 | 10/24/2018 | 10/24/2018 | A | PART |
Jim Storey
|
|
|
Mandy Phone #: ###-#### need ceilling covered w/ 25 flame spread product
|
BLD-Final | 6/22/2015 | 6/23/2015 | 6/23/2015 | P | FAIL |
Jim Storey
|
|
|
Doug Phone #: ###-#### c/n
|
FIRE-Final Inspection | 6/22/2015 | 6/23/2015 | 6/23/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
Issue PAID IN FULL permit | | | 5/28/2015 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 5/12/2015 | | 5/21/2015 | | PASS |
Tim L. Woodard
|
|
|
Level 2 - Paper - Downtown Hound
|
Plan resubmittals received | | | 5/21/2015 | | DONE |
|
|
|
Two copies of Sheets A2.1 and M3.0. Taken to Tim
|
Routing - PLAN CHECK | 5/21/2015 | | 5/21/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/21/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/21/2015 | | DONE |
|
|
|
need GC and rev cert of val// all requirements met KRS 5-28-15
|
Print Occupancy Form | | | 5/21/2015 | | DONE |
|
|
|
|
Telephone call | | | 5/21/2015 | | DONE |
|
|
|
Informed John that a GC Form and Revised Value from the GC-
|
Routing - PLAN CHECK | 5/11/2015 | | 5/13/2015 | | FAIL |
Tim L. Woodard
|
|
|
Refer to Plan Review Report. TLW
|
1st review completed | | | 5/13/2015 | | DONE |
|
|
|
|
Plan assigned to (AJS) | | 5/1/2015 | 5/12/2015 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Level 2 - Paper - Downtown Hound
|
Routing - MECHANICAL | 5/8/2015 | | 5/11/2015 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 5/8/2015 | | 5/8/2015 | | PASS |
Josh Wilson
|
|
|
Must provide fence in rear.
|
Routing PW Environmental | 5/4/2015 | | 5/6/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLANNING | 5/6/2015 | | 5/6/2015 | | PASS |
Susan Riggs
|
|
|
|
Routing - PUBLIC WORKS | 5/4/2015 | | 5/6/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | | | 5/4/2015 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 5/4/2015 | | 5/4/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/2015 | | DONE |
|
|
|
|
Application received | | 5/1/2015 | | | |
|
|
|
|